Project Manager
Petrocorp Company
Total years of experience :12 years, 10 Months
Working with a Spanish Client (TSK) in Shagaya 50 MW Concentrated Solar Thermal Power Plant in Al Salmi, The project owner is (KISR) Kuwait Institute For Scientific Research, And the consultant is WorleyParsons. Our Company was the responsible for the infrastructures and the concrete foundations,
And the Tasks that I was doing is:
- Managing the project at all
- Checking the drawings
- Checking the changes in the drawings with all versions, and make the (change orders)
- Planning management
- Procurement management
- Quality control management
- Cost control management
- Materials control management
- Heavy and Light Equipment's management
- Manpower management
- Tendering a new projects
- Deals with subcontractors.
- Attending for all the meetings.
working in installation the marble in a big projects, checking the drawing, attendance of the meeting, checking quantities, materials, and getting new projects to the company,
Working in H.O.T Company, Project KOC1 Pipe Line project, installation of LSFO, FG and Gas Oil Pipe Line From Mina Al Ahmadi to Sabiya and Doha Power Station, As a Site Engineer, and I was managing all my stuff that consist of more than 300 of man powers and 60 to 80 of heavy equipment’s, and my responsibility was for more than 60 Km Run Away installing pipe line, following-up my supervisors, employments, and observers.
Dealing with the subcontractors, following up the meetings.
Designing Formwork And checking the Exact quantity of Scaffolding,
I participated in the university field training at the Saudi Oger Company in Al Abdali project in Jordan. Has been trained on the receipt and delivery of small projects of columns, nodes, foundations, stairs, iron, iron and retaining walls,