Maximum upload file size: 3MB. File types allowed: jpg, jpeg, gif only.

Click the above 'Browse' button to select a photo.
Guidelines
  1. Only upload a photograph of yourself
  2. Photos of children, celebrities, pets, or illustrated cartoon characters will not be approved
  3. Photos containing nudity, gore, or hateful themes are not permissible and may lead to the cancellation of your account
  4. Photos of your passport, ID, or photos containing any personal information such as your address, passport number, or contact details are not permissible for your own security.

Delete Guidelines

Adil Asad Khan

Lead Project Control Engineer

Bombardier Transportation

Location:
Saudi Arabia - Riyadh
Education:
Master's degree, Masters in Project Management
Experience:
17 years, 4 months

Work Experience

What's your work experience? Your experience is one of the most important sections in a CV.
List all relevant responsibilities, skills, projects, and achievements against each role.  If you're a fresh grad, you can add any volunteer work or any internship you've done before.
Add Experience

Total Years of Experience:  17 Years, 4 Months   

February 2012 To Present

Lead Project Control Engineer

at Bombardier Transportation
Location : Saudi Arabia - Riyadh
Key Deliverables:
• Provide planning interface to all internal departments associated with the project.
• Preparation of discipline wise interlink project schedule into various WBS level and providing percentage weightage factors on budgeted cost.
• Elaborating Level-3 project schedule using Primavera P6 & TILOS and identifying the Critical Paths based on planned logic and float analysis, notifying the critical activities and risks to managers.
• Preparation and update of Time Chainage schedules on TILOS.
• Developing and updating periodically S-Curves, Manpower Histogram loading curves for all disciplines and for overall project.
• Liaise with the client, subcontractors and suppliers for updates and to ensure their schedules are aligned to the project schedule. Monitor contractor’s actual progress versus planned.
• Periodically preparation of Job Cost Report (JCR) and presenting to management.
• Periodically Management / Client Report Generation (MIS), Client Invoicing & Subcontractor Billing etc.
• Preparation and updating Margin Enhancement Program (MEP), Risk Opportunity Program (ROP), Change Requests, Variation Orders & Change Control Board (CCB).
November 2010 To February 2012

Senior Planning & Cost Control Engineer

at IL&FS Engineering & Construction Company (Formerly Maytas Infra)
Location : Saudi Arabia - Khobar
Key Deliverables:
• Preparing Quantity Take-Offs for all major items listed in the BOQ and Tender Drawings.
• Preparing Tender Stage Resource Loaded Schedule (Level 2 & Level 3) on Primavera Project Planner P6.
• Preparation of Daily / Weekly / Monthly Progress Reports, 2-3 Week Look ahead schedules, Cost / Manpower Histograms, Project Cost Forecasts, Organizational Charts.
• Establishing Project Budget, Scope of Work, Manpower / Equipment Requirement and Cash Flow.
• Mapping Project Cost Review with Project Teams, Cost Trends, Risks and Exposures.
• Preparing the Final Tender Presentation.
• Preparation of Material Inventory and Material Stock Tracking Database.
• Preparation of Submittal Registers.
• Involving in the site visits to get an update of the percentage complete of each activity.

Key Highlights:
• Efficiently generated and got approval for Daily / Weekly / Monthly Progress Reports.
• Submittal and Approval of Resource / Cost Loaded Level 3 & Level 2 Schedules using Primavera Project Planner P6.
March 2008 To September 2010

Cost Engineer

at Parsons International Limited
Location : Qatar - Doha
Key Deliverables:
• Overseeing Marine works, Light Rail Transit, Underground Car Parks, Sewage Treatment Plant & Utility Tunnel along with Contractor Proposals Review and Tracking (within timeframe per contract).
• Developing, establishing, and maintaining all aspects of the Cost Control Effort.
• Handling Progress Payment review and certification, Bill of Quantities review and approval.
• Developing and managing Project Budgets using the Project Database (MS-Access).
• Tracking all Cost Information, Contracts, Variation Orders and Invoices in the cost system.
• Updating Project Budget, Cost Information & distributing Payment Information as per Bill of Quantities and other costs in the cost system.
• Mapping Project Cost Review with Project Teams, Cost Trends, Risks and Exposures.
• Preparing Monthly Updates, Project Performance Measures, Project Forecasts & Cost Performance Reports, Project Cost Reports, Trends and Graphs.
• Updating PRISM (Parsons Resource Information System Manager).

Key Highlights:
• Efficiently generated Monthly Cost Reports and Monthly Progress Reports.
• Created sufficient backup for Parsons Invoices so there are no deductions in amount and Write-Offs.
• Maintained healthy working relation with the Clients & Contractors.
April 2007 To March 2008

Planning Engineer

at Saudi Binladin Group
Location : Saudi Arabia - Jeddah
Key Deliverables:
• Preparing Critical Path Method Tender Stage Schedule (Resource & Cost Loaded) on Primavera Project Planner P5 and later on imported to P6.
• Identifying the Critical Path of the Schedule & calculating Total Manpower and Equipment Requirement for the Project.
• Detailed study of the Productivity of each Equipment to be used on site and the Performance Index of Manpower on site
• Structuring the Schedule in accordance with the Project’s WBS. This included breaking the work down into detailed activity level using a coded hierarchical structure consistent with the project’s WBS (Work Breakdown Structure)
• Updating Master Schedule on monthly basis based on percentage complete and forecast completion dates for remaining efforts.
• Involving in the site visits to get an update of the percentage complete of each activity.
• Preparing Cash Flow, Monthly Progress Reports and Daily Progress Reports & updating the Project Organization Chart.

Key Highlights:
• Successfully submitted and got approval for Daily Progress Report and Monthly Progress Report format.

Education

What's your educational background?
Let employers know more about your education; remember, be clear and concise.
February 2007

Master's degree, Masters in Project Management

at University of New South Wales
Location : Sydney, Australia
Grade: 60 out of 100
June 2005

Bachelor's degree, Bachelors in Civil Engineering

at Aligarh Muslim University
Location : Aligarh, India
Grade: 65 out of 100

Specialties & Skills

Primavera Project Planner (P5 & P6)

MS Project / Powerpoint / Access / Excel / Word

Primavera P6

Cost Control

Project Management

Schedule Planning

Languages

Do you speak more than one language?
For some jobs, fluency in one or more foreign languages is a plus, so add your language skills to get better results.

English

Expert

Hindi

Expert

Urdu

Expert

Training and Certifications

Earthquake Disasters in India, Role of a Civil Engineer ( Certificate )

Issued in: September 2004 Valid Until: - September 2004

TILOS Quick Jump Start Program (Basic & Advanced) Training ( Certificate )

Issued in: March 2014 Valid Until: - March 2014

Project Management Essentials ( Certificate )

Issued in: January 2014 Valid Until: - January 2014

Master Class (Delay, Disruption, Dispute Resolution & Effective Management of Construction Contrac ( Certificate )

Issued in: February 2014 Valid Until: - February 2014