Project Manager
Six Sigma NYC Inc.
Total years of experience :17 years, 10 Months
1- Manage demolition and alternation of residential building while ensuring compliance as per DoB, DEP DoT, FDNY and other regulatory agencies.
2- Working closely with construction team to prepare construction schedule and to maintain said schedule for completion of project within budget. Build SOP for company operation and code compliance.
3- Schedule & manage trades, subcontractor & in-house crew, quality control inspections for completion of high end units.
4- Monitoring day to day activities and up keeping job site documentations & logs
5- Developing & presenting status reports, progress reports, updated budget & cash flow to senior management.
6- Certification of all interim and final invoices of vendors, subcontractors & general contractors.
7- Managing the liaison with contractors, subcontractors, government and other regulatory authorities.
1- Pre-qualification of potential contractors with the assistance of the Consultant/Designer.
2- Administered the contract with the designer in terms of scope and deadlines.
3- Implemented a master plan incorporating all the activities during the design, construction and handing-over stage.
4- Verified the QA/QC system and evaluated the CV’s of the design firm.
5- Provided the Designer with the Client’s general requirements including but not limited to design brief, milestones, cost, quality, function, programming guidelines, execution strategy, climatic and environmental data, boundary limit, location of utilities, building codes and availability of local materials.
6- Evaluated and followed up the tendering processing in conjunction with the Consultant and recommend the most optimal offer.
7- Reviewed the mobilization, HS&E, planning, QA/QC and schedules of the Contractor.
Daily coordination of progress of works for all Packages.
8- Reviewed all projects weekly to ensure tasks and activities are coordinated in line with those outlined in the project document and according to the agreed work plan.
9 -Scheduled and chaired weekly progress and coordination for all contractors; discussing key matters such as progress, safety, adherence to program, as well as technical issues that are potentially delaying the works. Prepared and distributed minutes.
10. Collaborated in resolving the complications in between consultants and contractors.
11- With the assistance of the contractors, prepared cash flow and budgets.
12- Attended handing-over site visits and safe keep all the manuals, spare parts, as-built, etc. on behalf of the Client.
13- With the assistance of an accountant, verified all payments and invoices.
14- Liaised with Contractor, Subcontractor, Government and other Regulatory Authorities.
1- Over all in charge for the all projects, leading and representing the project to the top management and client.
2- Closely monitored the performance of the projects on a day-to-day basis.
3- Administered construction contracts, estimation and bidding for new projects.
4- Responsible for approving mobilization plan of manpower, machinery, materials and other necessary resources by coordinating with Head office and clients.
5- Supervised all construction activities and assuring project quality to relevant building codes.
6- Prepared and implemented Bar Bending Schedule.
7- Participated in Handing Over process of projects.
8- Liaised with Client, Subcontractor and Government and other Regulatory Authorities.
9- Daily progress review meeting with General Manager.
1- Ensured achievements of milestones set in the contract documents through a comprehensive construction management system of manpower, material, equipment deployment, construction team.
2- Administered construction contracts, estimation and bidding for new projects.
3- Supervised of all construction activities and assuring project quality to relevant prevailing building codes.
4- Prepared and implemented Bar Bending Schedule.
5- Participated in Handing Over process of projects.
6- Liaison with client, subcontractors and government and other regulatory authorities.
7- Daily progress review meeting with General Manager.
1- Inspected setting out of all works to be constructed in relation to the required points and levels of references.
2- Inspected all elements of project according to approved drawings and project specifications.
3- Supervised of placing of Stone Apron, Block Apron and Concrete Lining.
4- Performed field quality tests.
5- Verified Interim payment certificate of contractors.
6- Liaised with the client in connection with execution of project and to ensure all the elements operates in a seamless mode to fulfill contractual commitments.
7- Interpreted contract documents and construction drawings.
8- Collaborated in sorting out problems in between consultants and contractors.
1- Responsible for the complete construction management and execution of cast in situ bored tension piles, SBMA ground anchors for Diaphragm Wall.
2 -Raising site material indents to be used in civil construction.
3- Communicated the technical queries about site to the consultant
4- Daily progress review meeting with field engineers and supervisors.
5- Meetings and coordination with client on site related issues.
6- Prepared method statements of different construction activities.
1- Responsible for the project coordination, planning, organizing and supervision of execution of assigned works.
2- Ensured that work is executed according to approved drawings, standards, contract conditions, specifications and client’s satisfaction for construction of Valve Chamber, Head Regulator, Subsidiary Weir, Curtain Wall
1-Awarded academic scholarships and merit certificates. 2-Finished education amongst top 3 % students.