Senior Quantity Surveyor
Trags
Total years of experience :7 years, 5 Months
Roads & Infrastructure (Client: PWA / ASHGHAL)
Project Brief:
The works include Construction and upgradation of roads, Bridges, underpass, Culverts,
relocation & protection of existing services and services including Water, Irrigation, Drainage,
Sewer, Electrical, Street Lighting, Ooredoo, etc.
Projects Summary: Highârise, luxury residential apartments, and Landscape Works (Client: Musherib
Downtown Doha, Phase 1B (MDDPH1B) & Aspire Zone & QAPCO
Project Brief:
The works includes club house including multipurpose hall, swimming pool, bowling center, and
restaurant luxury apartment complex, villas, utility services and authority approvals.
Responsibilities:
ï· Prepared subcontractor packages, drafting contracts, and other correspondence
ï· Advise the appropriate procurement routes
Page 2 of 3
ï· Analyze rates for Labor, Plant & Material, Direct/indirect costs and assist buildâup costing
ï· Tender evaluation, Contractor / Supplier Evaluation and recommendation
ï· Preparation, Review, and approved Interim Payment Application
ï· Prepared and managed project budgets, Cash flow and keeping costs down
ï· Scrutinize tender and contract drawings for ambiguities and discrepancies with the SOW
ï· Assessment, preparation and submission of Variation Orders for approval to client
ï· Prepared Bill off quantities, Estimation.
ï· Coordinate with Client, Engineer and consultant Team and respond to the tenderers queries.
ï· Chaired negotiation, and progress meetings with stakeholders.
ï· Review the contractors claims, Variations and new rates as per contractual provisions
ï· Prepare cost reports for management and other departments.
ï· Preformed cost control activities by using tools such as CVR, CTC, etc.
ï· Assisted to Project Managers on contractual and commercial matters
ï· Maintain log sheets to monitor warranties, bonds, insurances, guarantees, etc., are in place as per contractual
provisions.
ï· Prepared and Submitted potential variations and claims, check for compliance with applicable.
ï· Identified contractual risks and problems and take appropriate action to ensure a satisfactory resolution.
ï· Evaluated and prepared final account/close out for old contracts in (Penultimate and Release of Retentions,
etc.)
ï· Successfully completed many projects with expected profit margins and client satisfaction.
Projects Summary: Proposed Chinese Hotel, Shopping complex and School hostel (B2+G+3)
Responsibilities:
ï· Take off quantities from drawings and site measurements
Page 3 of 3
ï· Prepared and submitted monthly Progress Valuation to the Consultant
ï· Maintained log sheet for warranties, bonds, supplier details, material onsite, etc.
ï· Attended the meeting with the consultant representative to finalize the Progress Valuation
ï· Priced the Variation and agreeing with a
LANKA
Projects Summary: Government housing projects and rehabilitation of school projects.
Responsibilities:
ï· Taking off quantities & BOQ preparation
ï· Assisted & Prepare monthly valuations and issued for approval.
ï· Preparation of quotation for subâcontract works and evaluate.
ï· Obtained Quotations from various contractors and suppliers.
ï· Prepared the weekly and monthly progress report and cash flow report.
ï· Order the materials whichever is required for site and checking the invoices
in
in
courses: BTEC Quantity Surveying and Construction Economics, Pearson, Edexcel. Certified Cost Professional (CCP) â AACE, USA Project Management Professional âPMP âUnder Process