EPIC FOR EARLY SITE PREPARATION WORKS FOR NGL-5, MESAIEED INDUSTRIAL CITY
RAS LAFFAN TERMINAL OPERATION (RLTO) EXPANSION AND OFF PLOT FACILITIES OF THE NORTH FIELD EXPANSION PROJECT (EPC-3) - Subcontract
RAS LAFFAN TERMINAL OPERATION (RLTO) EXPANSION AND OFF PLOT FACILITIES OF THE NORTH FIELD EXPANSION PROJECT (EPC-4) - Subcontract
DESIGN & BUILD OF AL KHOR EXPRESSWAY PROJECT
Subcontract for Q-Rail Tunnel Earthworks, drainage and Structure works at Package 4
Project Value : QR 177 mil
Subcontract for Piling works at Package 4
Subcontract for Bridge Barrier & Architectural Element at Package 4
Project Value : QR 9.5 mil
Subcontract for Structure works for Interchange - G & Interchange - H at Package 4
Project Value : QR 62 mil
Subcontract for MSE Wall Interchange - G, Interchange - G1 & Interchange - H at Package 4
Project Value : QR 34 mil
Subcontract for Pedestrian Bridge Crossing at Al Bayt Stadium (Package 4)
Project Value : QR 29 mil
ROAD AND INFRASTRUCTURE IN SEMAISMA - PACKAGE (WEST)
Project Value : QR 317 mil
ROLE AND RESPONSIBILITIES: Technical Engineer
• Report to the QA/QC & Technical Manager, control, and monitor all activities related to Quality and Technical Submission.
• Liaise for submission of Material submittals and Specific Method Statement as required according to site work.
• Develop a Specific Method Statement for the required activity including risk assessment and Inspection Test Plan including Checklist based on specifications of the project.
• Manage all work methods and maintain knowledge on all quality assurance standards and monitor continuous application for all quality assurance processes and recommend corrective actions for all processes.
• Working closely with procurement and design department on preparing price and technical evaluation report.
• Ensure all commissioning and handing over document in order
TENDER AND PROPOSAL FOR NEW PROJECT
ROLE AND RESPONSIBILITIES:
• Manage associated technical tender preparation including tender drawing, specification and bill of quantities review
• Responsible for the tender submission process for formatting, completeness, consistency and compliance
• Ensure tenders meet company commercial guidelines and have the necessary sign off in accordance with the delegation of authority guidelines.
• Responsible for all associated handover documentation in the event of an order.
• Participate in and actively support company initiatives.
• Ensure tender technical submission comply with the general specifications and market requirements.
• Respond on Tender clarification if required by client
DESIGN AND CONSTRUCTION OF AN ENGINEERED SANITARY LANDFILL, IN BURAIMI
Project covers the design and construction of an Engineered Sanitary Landfill (500, 000 cu.m capacity) including 3.5km access road, perimeter landfill road, administrative building, Labour facility building, workshop building and weighbridges
ROLE AND RESPONSIBILITIES: Construction Engineer
• Responsible in site correspondence letter and MEMO.
• Prepare Material submission, and Method Statement for consultant /client approval.
• Responsible in preparing detail taking-off quantity for the project.
• Prepare procurement plan and review construction program schedule.
• Prepare overall construction methodology and method statement.
• Ensuring all works carry out according to standard & project specification and safety requirement.
• Preparing monthly progress report for submission.
• Update monthly progress schedule
• Coordinate a meeting between sub-contractors to resolve any issue arise.
• Attend meeting with client and consultant.
• Responsible in commissioning and final hand over project
METRO RED LINE SOUTH ELEVATED & AT-GRADE
Project covers the design (Civil and MEP) and construction of 7.2 km metro line including 3 no. elevated metro stations, namely QEZ (Qatar Economic Zone), Barwa and Al Wakra. The line starts from Old Airport Road and continues on the median of Al Wakra Main Road as elevated viaduct to depot area and ends at Al Wakra
Project Value : USD 654 mil
ROLE AND RESPONSIBILITIES: Methods Engineer
• Prepare overall construction methodology and method statement for the whole package of construction.
• Defining the work site installation, execution principles and working method.
• Establish sequence of operation for QA/QC Department (for ITP preparation)
• Recommend methods for improving utilization of personnel, material and utilities.
• Communicate with construction team and sub-contractor to develop methodology in accordance to design standards.
• Prepare Traffic Diversion Plan (TDP) and Temporary Traffic Management Plan (TTM) for submission and approval.
BRUNEI INTEGRATED WASTE MANAGEMENT SYSTEM, SUNGAI PAKU & SUNGAI AKAR, BRUNEI DARUSSALAM.
Design and built contract comprises of Transfer Station Building, engineered landfill and treatment plant at Sungai Paku, waste transfer and logistics station plus three years of operations and maintenance of the Facility.
Project Value : SGD 66.5 mil
ROLE AND RESPONSIBILITIES: Project Engineer
• Preparing construction method statement for consultant approval. Civil & Structural and Infrastructure works as request by consultant or client.
• Conducting the inspection with consultant to verify & approve the works prior concrete placement activity.
• Ensuring all test done according to standard & project specification.
• Responsible to supervise 8 awarded subcontractors based on work package, and ensuring that all works meet the contract quality and specifications.
• Assist Project manager in preparing the monthly progress report
• Responsible in coordinate meeting between all sub-contractors
• Liaison with consultant to resolve any design issue at site.
• Responsible in commissioning and final hand over to the completion of the project.
DESIGN AND CONSTRUCTION OF EAST COAST EXPRESSWAY PROJECT PHASE 2, FROM PAHANG TO KUALA TERNGGANU.
EAST COAST EXPRESSWAY PACKAGE 2. (BUKIT PAYUNG SPUR ROAD)
BRIDGE CROSSING AT KIARA 5 ROAD FOR KUALA LUMPUR CITY HALL.
DEVELOPMENT OF COMMERCIAL COMPLEX AT PHASE 7, SAUJANA IMPIAN KAJANG.
DESIGN AND CONSTRUCTION OF TWO BLOCK OF FOUR STOREY STAFF HOUSE FOR FOREST RESEARCH INSTITUTE MALAYSIA.
PROPOSED ELEVATED ROAD CROSSING EXISTING RAILWAY TRACK AT PASIR MAS, KELANTAN.
DEVELOPMENT FOR INTERNATIONAL FISHERY PORT AND MALAYSIA FISHERY COMPLEX AT BATU MAUNG, PENANG FOR LKIM.
DESIGN AND CONSTRUCTION OF EAST COAST EXPRESSWAY PROJECT PHASE 2, FROM PAHANG TO KUALA TERNGGANU.
ROLE AND RESPONSIBILITIES: - Design Engineer
• Responsible in preparing design calculations and design report.
• Responsible in preparing road design calculations and report.
• Prepared tender evaluation report for client.
• Prepared civil & structural design and drawings for tender purpose.
• Prepared tender specification as per design and client requirement.
• Liaised with authority for design approval and submission.
• Review drawing and discrepancy for final submission to client.
Bachelor of Technology/Engineering (Civil) in 2002, - University Technology of Malaysia