YEAR PROJECT COMPANY DESIGNATION COUNTRY
Sept.2013 to Present Multipurpose Sports Hall & Administration Offices
Qatar Handball association Complex
(Stadium Project)
Voltas Ltd.Doha Qatar QA/QC Electrical Inspector Duhail North Doha,
State of Qatar
June -Sept.2013 Msheireb Downtown Doha Project-Phase 1A(Doha Land)
Voltas Ltd, Doha Qatar QA/QC Electrical Inspector Doha, State of Qatar
January 2011-June 2013 Sidra Medical and Research Center (HOSPITAL PROJECT)
VOLTAS LTD.Doha Qatar
QA/QC Electrical Inspector Doha, State of Qatar
December 2010- 2011 New Doha International Airport (CP-19 Project)
Passenger Railway Station(CP-2201)(NDIA
Government) VOLTAS LTD.Doha Qatar
QA/QC Electrical Inspector Doha State of Qatar
September 1997 - January 2010
Al-Khafji Crude Onshore Production Facilities and Development plant
project (KFDP) Consolidated Contractors Intl.Company(CCIC) GROUP OF COMPANY-W.L.L / SICON OIL COMPANY ELECTRICAL/INSTR.FOREMAN Ras Al-Khafji Kingdom of Saudi Arabia (KSA)
Al-Khafji joint operation, Oil &Gas Refiner project (AGOC/KGOC)
(Oil & Gas Project)
March 2006- May 2007 Museum of Islamic Arts.(Bldg. Project) MERCURY ENGINEERING ELECTRICAL FOREMAN Doha, State of Qatar
April 2004 up to May 2005
Alba Phase 2A&B Expansion,
Oil & Gas refiner project.
(Oil & Gas Project)
Marathon Equatorial Guinea Production Ltd /Consolidated Contractors Int'l.Co (CCIC).
CHARGE HAND -Installation Pre Commissioning / Commissioning&Maintenance(E&I)
Equatorial EquatorialGuinea, West Africa
September 2001 to October 2003 KMWC Project (Substation) Karachaganak Petroleum Operating BV
(Oil & Gas Project) Consolidated Contractors Int'l Co. (GROUP OF COMPANIES) CHARGE HAND E&I
SUBSTATION Burlin Region,
Republic of Kazakhstan.
September 1999 to March 2001 ADNOC-On Shore Gas Development Project(OGD II) Consolidated Contractors Int'l Co. (GROUP OF COMPANIES) CHARGE HAND E&I
SUBSTATION Habshan Abu Dhabi,
United Arab Emirates(UAE)
September 1997 to December 1999 SAFCO 2 Ammonia & Urea Plant Project Consolidated Contractor Company WLL (CCIC GROUP) ELECTRICIAN Jubail, Kingdom of Saudi Arabia (KSA)
Residential and Industrial Complex
(RIC PROJECT) Consolidated Contractor Company WLL (CCIC GROUP) ELECTRICIAN CHARGEHAND Shayba, Kingdom of Saudi Arabia (KSA)
June 1991 - Aug. 1997 FERTELIZER INDUSTRIAL PLANT
(Production Plant) ATLAS FERTELIZER CO. (AFC) PRODUCTION SUPERVISOR Toledo City Cebu, Philippines
Electrical / Electronics Serviceman Course University of Visayas Toledo City, Cebu, Philippines ALFREDO MISSION TROCIO JR. Applicant