Antonio santos, Supervisor

Antonio santos

Supervisor

Technip-France Abu Dhabi

Location
Philippines
Education
Bachelor's degree, Mechanical
Experience
17 years, 1 Months

Share My Profile

Block User


Work Experience

Total years of experience :17 years, 1 Months

Supervisor at Technip-France Abu Dhabi
  • China
  • April 2016 to March 2017

. -Conduct line checking of system before air blowing.
.-conduct drying and innerting.
.-Conduct Gross Air Leak Test (GALT)
.-Conduct Maximum Operating Process (MOP)
.-Conduct inspection and commissioning of Fire Monitor.
.-Conduct final Reinstatement and final punch list.
.-Hand Cleaning inspection of Hook-ups pipes before injecting of Chemical preservation.

QA-QC Mechanical Inspector at Petron Bataan Refinery
  • Philippines
  • June 2014 to July 2014

-Assigned in hydrostatic testing and pipes inspection including leak testing.
-Conduct walkthrough for hydrostatic testing including safeness.
- Assigned in commissioning and pre-commissioning inspection such as steam blowing for HP, MP and LP steam, including rapture blowing and Air blowing.
-Popping test of pressure safety valves.
-Mechanical solo run inspection.
-System test.
-Leak test inspection.(pneumatic and Nitrogen).

Field Metal Mechanic I- Grade code 9 at Saidi Aramco Refinery
  • Saudi Arabia
  • March 2014 to May 2014

-Assigned in South refinery
-Coordinate to the mechanical Supervisor for the work order task.
--Obtain PTW for the Mechanical maintenance jobs.
-Coordinate to the Operation Shift Supervisor and to the field operator if the auxiliaries are already isolated for the safety precautions.
-Installation and alignment of a new reconditioned pumps and compressors.
-Removal of nonfunctional valves, gaskets and replace into new one.
-Assigned for the removal and installation of tubing in Heat Exchanger,
-Replacement of Internal parts for plate exchangers such as rubber gaskets and assembling.
-Assigned for the removal in the Steam Turbines damaged blades and replacing into new one.
-Assigned for the HP Steam blowing lines that connected to the Steam Turbine.
-Assigned for steam turbine solo run.
-Performed corrective and preventive maintenance for steam traps, condensate and distribution manifolds, pumps and motors.

QA-QC Mechanical Inspector at Petron Bataan Refinery
  • Philippines
  • December 2013 to February 2014

-Assigned in hydrostatic testing for pipes inspection including leak testing.
-Conduct walkthrough for hydrostatic testing including safeness.
- Assigned in commissioning and pre-commissioning inspection such as steam blowing for HP, MP and LP steam, including rapture blowing and Air blowing.
-Popping test of pressure safety valves.
-Mechanical solo run inspection.
-System test.
-Leak test inspection.(pneumatic and Nitrogen).

Mechanical supervisor at Daelim Philippines
  • Philippines
  • June 2012 to August 2013

-Assigned in pipe rack structural at 8100 common, interconnecting 8300 p/r 1 & 2
-Supervision of installation of rotating equipment such as centrifugal pumps and
positive displacement pumps including motor solo run until commissioning with the
suction and discharge lines.
-Supervision of erection and double ending activities of pipes in the pipe rack including fitting fit-up.
-Supervision in fabrication shop such as fit-up of all joints of pipes and fittings. Including underground piping.
-Supervision of erection for flare structures.

Mechanical commissioning supervisor at JGC-KBR Joint Venture
  • Qatar - Doha
  • December 2010 to December 2011

-Obtain permit to work for the commissioning activities.
-Conduct safety talk and tool box meeting for commissioning activities.
-Assigned in night shift duty for commissioning activities in process area such as:
-Nitrogen purging for reactors (shell side and tube side), light and stripper lines and condenser lines.
-Commissioning of pin fan cooling motors such as vibration, temperature and sounds abnormality.
-Conduct air blowing preparation and installation of knife valve for rapture blowing as per mark up PEFS and procedures.
-Conduct safety walk through with the client field operators.
-Conduct air blowing, rapture disk, tightness test, nitrogen purging, air freeing, leak test, operational testing and functional test.
-Conduct final inspection with the client field operators for acceptance.
-Conduct final reinstatements.

Mechanical supervisor at D.J. Roque construction
  • Philippines
  • January 2010 to August 2010

-Obtain PTW for the Mechanical jobs.
-Coordinate to the Operation Shift Supervisor and to the field operator if the auxiliaries are already isolated for the safety precautions.
-Assigned in the Utility area such as Installation and alignment of a new reconditioned pumps and compressors.
-Assigned for the removal and installation of tubing in Heat Exchanger,
-Replacement of Internal parts for plate exchangers such as rubber gaskets and assembling.
-Assigned for the removal in the Steam Turbines damaged blades and replacing into new one.
-Assigned for the HP Steam blowing lines that connected to the Steam Turbine.
-Assigned for steam turbine solo run.
-Performed corrective maintenance for steam traps, condensate and distribution manifolds.

PreMechanical commissioning Supervisor at Chiyoda-Technip Joint Venture
  • Qatar - Doha
  • February 2008 to November 2009

-Obtain PTW for the Pre-Commissioning activities
-Conduct air blowing preparation and reinstatement
-N2, C3, MR Turbine Compressor Lube Oil Flushing
-Motor Solo Run
-Instrument / Plant air system
-MP, LP, HP steam system
-Fuel gas system
-Commissioning of steam tracing system, distribution and condensate manifolds.
-Responsible for the PTW for the Pre- mechanical commissioning activities.
-Perform preparation of air blowing and reinstatement as per method of statement.
-Perform air blowing by using rapture disk as per method of statement.
-Request to the lead commissioning engineer for the inspection of the circuit with the client representative field operator.
-Responsible for the MP, LP, HP steam blowing activities and conduct inspection with the client representative field operator.
-Commissioning of all steam traps, distribution and condensate manifolds.
-Assisted to vendor representative for HP steam blowing for all steam turbine lines.
-Perform conformity check line and tightness test.
-Assisted to vendor representative for chemical cleaning, lube oil flushing, turbine compressor / generator functional testing.
-Conducted in leak testing and rectify leakage found during testing.
-Commissioning of fire hydrants and deluge system.
-Coordinate final punch and punch clearing.

Power Plant Field Operator at Alstom Power Philippines
  • Philippines
  • October 2005 to January 2008

Gas turbine generator system
Auxiliary oil pump and power oil pump system
HRSG/ Heat Recovery Steam Generator
Steam turbine generator system
Demineralization unit

Responsible for the shift Manager, Supervisor and control room operator for exact status of all main and auxiliary plant equipment’s, routine plant monitoring check, plant pre-start checks, system chemical monitoring and completion of comprehensive log sheet. Also involved in the implementation and preparation of mechanical and electrical permit to work for Preventive and corrective plant maintenance.

Responsible for all Operation tasks, start-up, shutdown and efficient operation of:
-Three (3) 72 mw ABB GT 11N Gas Turbine with standard Combustion Chamber with water injection.
- Three (3) 127 T/hr 50 bar KHI-VOGT Heat Recovery Steam Generator
- One (1) 120 mw ABB 18 single pressure Condensing Steam Turbine Generator.
- Two (2) stages PETROLITE FUEL OIL TREATMENT PLANT.
- Three train DE MINERALIZED WATER TREATMENT PLANT with force Regeneration
Plus the BALANCE OF PLANT inclusive of:
Main seawater circulating water system with integral Electrolyte Hypochlorite Chlorination System, de Ionization water treatment plant, effluent treatment plant, effluent neutralization and disposal pumping system, comprehensive water fire suppression system. Follow all station ISO quality, EMS, and OHSAS work procedures.

Job description:

Area Unit: Gas Turbines( GT )


Area Unit: Heat Recovery Steam Generator ( HRSG )


Area Unit: STEAM TURBINE ( ST )


Area Uni: Fuel Oil Treatment Plant ( FOTP )

Mechanical Commissioning Supervisor at CLOUGH NIUGINI LTD
  • Papua New Guinea
  • October 2003 to February 2005

Instrument / Service Air System
Emergency Diesel Generator System
Fire Water System
Boiler Unit
BFW System
Demineralization Unit
Desalination Unit
Stabilization Unit
Feed / Product Tankage System

-Obtain PTW for the Pre-Commissioning activities
-Conduct air blowing preparation and reinstatement
-N2, C3, MR Turbine Compressor Lube Oil Flushing
-Motor Solo Run
-Instrument / Plant air system
-MP, LP, HP steam system
-Fuel gas system
-Commissioning of steam tracing system, distribution and condensate manifolds.
-Responsible for the PTW for the Pre- mechanical commissioning activities.
-Perform preparation of air blowing and reinstatement as per method of statement.
-Perform air blowing by using rapture disk as per method of statement.
-Request to the lead commissioning engineer for the inspection of the circuit with the client representative field operator.
-Responsible for the MP, LP, HP steam blowing activities and conduct inspection with the client representative field operator.
-Commissioning of all steam traps, distribution and condensate manifolds.
-Assisted to vendor representative for HP steam blowing for all steam turbine lines.
-Perform conformity check line and tightness test.
-Assisted to vendor representative for chemical cleaning, lube oil flushing, turbine compressor / generator functional testing.
-Conducted in leak testing and rectify leakage found during testing.
-Commissioning of fire hydrants and deluge system.
-Coordinate final punch and punch clearing.

Mechanical Commissioning Supervisor at JayRay McDermott
  • Indonesia
  • August 2000 to November 2001

Instrument/ Service Air System
Emergency Diesel Generator System
Fire Water System
Boiler Unit
BFW System
Demineralization Unit
Desalination Unit
Stabilization Unit
Feed / Tank age System


-Reports to the Lead Commissioning Engineer of the Commissioning Department.
-Perform pre-commissioning activities as per commissioning Engineer’s.
Instructions that includes air blowing, water flushing and performs functional testing as per commissioning procedures.
-Conducted Motor Solo Run Test taking vibration, bearing temperature and RPM
-Assisted vendor representative for chemical cleaning, Lube oil flushing, Turbine Compressor/ Generator functional testing.
-Perform vessel internal cleaning until final closure.
-Conducted in leak testing and rectify leakage found during testing.

Mechanical Commissioning Supervisor at National Power Corporation
  • Philippines
  • April 1998 to January 1999

Boiler Units
Steam Turbine Generator
Utility Area
Demineralization Unit
Condensate System
Waste Water System

-Conducted and performs pre-commissioning / commissioning, start up and operation of Instrument / Plant Air System, Potable Water System, Fire Water System, Demineralization Unit, Steam Boiler, BFW System.
-Conduct routine checking, inspection, observe running condition of all machinery equipment, operates utility unit safely while providing the required utility to process units,

Piping Supervisor at KUMAGAI GUMI CO.LTD
  • Hong Kong
  • January 1997 to February 1998

- Receiving the approved drawing for fabrication.
-Preparing the fabrication schedule according to priority.
- Preparing the spool pack for traceability.
- Allocating the task according to the ability of foremen.
-Preparing the material request according to the requirement of spool.
- Inspect the pipes and piping materials as per specification.
- Visual inspection and receiving the materials from store.
- Guiding the sub -ordinate and workers regarding proper use of tools and tackles.
- Resolving field problems and liaison client under the supervision of Mech. Engg. and process Depts.
- Adherence to construction safety and special safety requirement for working at plant.
- Allocation of jobs among various working groups.
- During the fabrication activities visual inspection of pipes and all fittings, edge preparation, fit up of the pipe, welding quality of the pipe and D.P.T.
- Co-ordination with concerned person. during fabrication & erection.
- Planning & supervision of piping fabrication.
- Checking the daily progress report .
- Reporting the Senior Engineer and construction manager regarding whole day production Monitoring the front availability.

Piping Supervisor at D.J. Roque Construction
  • Philippines
  • May 1995 to July 1996

- Receiving the approved drawing for fabrication.
-Preparing the fabrication schedule according to priority.
- Preparing the spool pack for traceability.
- Allocating the task according to the ability of foremen.
-Preparing the material request according to the requirement of spool.
- Inspect the pipes and piping materials as per specification.
- Visual inspection and receiving the materials from store.
- Guiding the sub -ordinate and workers regarding proper use of tools and tackles.
- Resolving field problems and liaison client under the supervision of Mech. Engg. and process Depts.
- Adherence to construction safety and special safety requirement for working at plant.
- Allocation of jobs among various working groups.
- During the fabrication activities visual inspection of pipes and all fittings, edge preparation, fit up of the pipe, welding quality of the pipe and D.P.T.
- Co-ordination with concerned person. during fabrication & erection.
- Planning & supervision of piping fabrication.
- Checking the daily progress report .
- Reporting the Senior Engineer and construction manager regarding whole day production Monitoring the front availability.

Piping Foreman at BONNATI S.P.A. Gas Plant
  • Libya - Tripoli
  • January 1994 to February 1995

- Receiving the approved drawing for fabrication.
-Preparing the fabrication schedule according to priority.
- Preparing the spool pack for traceability.
- Allocating the task according to the ability of foremen.
-Preparing the material request according to the requirement of spool.
- Inspect the pipes and piping materials as per specification.
- Visual inspection and receiving the materials from store.
- Guiding the sub -ordinate and workers regarding proper use of tools and tackles.
- Resolving field problems and liaison client under the supervision of Mech. Engg. and process Depts.
- Adherence to construction safety and special safety requirement for working at plant.
- Allocation of jobs among various working groups.
- During the fabrication activities visual inspection of pipes and all fittings, edge preparation, fit up of the pipe, welding quality of the pipe and D.P.T.
- Co-ordination with concerned person. during fabrication & erection.
- Planning & supervision of piping fabrication.
- Checking the daily progress report .
- Reporting the Senior Engineer and construction manager regarding whole day production Monitoring the front availability.

Piping Foreman at BECHTEL
  • Papua New Guinea
  • October 1992 to October 1993

- Receiving the approved drawing for fabrication.
-Preparing the fabrication schedule according to priority.
- Preparing the spool pack for traceability.
- Allocating the task according to the ability of foremen.
-Preparing the material request according to the requirement of spool.
- Inspect the pipes and piping materials as per specification.
- Visual inspection and receiving the materials from store.
- Guiding the sub -ordinate and workers regarding proper use of tools and tackles.
- Resolving field problems and liaison client under the supervision of Mech. Engg. and process Depts.
- Adherence to construction safety and special safety requirement for working at plant.
- Allocation of jobs among various working groups.
- During the fabrication activities visual inspection of pipes and all fittings, edge preparation, fit up of the pipe, welding quality of the pipe and D.P.T.
- Co-ordination with concerned person. during fabrication & erection.
- Planning & supervision of piping fabrication.
- Checking the daily progress report .
- Reporting the Senior Engineer and construction manager regarding whole day production Monitoring the front availability.

Education

Bachelor's degree, Mechanical
  • at University of the East
  • April 1990

working Student

Specialties & Skills

Construction Supervision
Mechanical Maintenance
Plant Commissioning

Languages

English
Intermediate

Training and Certifications

Operation trainee-ship program (Training)
Training Institute:
ABB Operation and Maintenance,Bataan Combine Cycle Power Plant
Date Attended:
February 1999
Duration:
1248 hours
Computer Technology course (Training)
Training Institute:
Polytechnic University of the Philippines
Date Attended:
January 1996
Duration:
1056 hours
Machine shop (Training)
Training Institute:
Bataan National of Arts and Trades
Date Attended:
June 1984
Duration:
832 hours
Practical Electricity (Training)
Training Institute:
Petron Bataan Refinery
Date Attended:
April 1987
Duration:
208 hours
Incident and Injury Free Supervisor skills (Training)
Training Institute:
Qatar Pearl shell-GTL
Date Attended:
December 2010
Duration:
8 hours

Hobbies

  • Studying in Internet/Google
    Searching for other techniques regarding to industrial plant such as rotating and static jobs.