Project Director
Generic Engineering Technologies
مجموع سنوات الخبرة :17 years, 8 أشهر
Project Director of a luxurious 80 Million USD palace for a key public figure in the GCC, including a number of recreational facilities, indoor and outdoor activities, guest houses, etc.
Led and supervised the implementation of the project, including activity planning and oversight to ensure completion of project milestones in a timely manner and within the allocated budget.
- Managing and supervising all Lindenberg projects in UAE,
- Covering all the areas of project management: Project Planning, Cost Management, Time Management, Quality Management, Contract Administration, and Safety Management,
- Leading the civil works for substations in Abu Dhabi, Ruwais and Al-Ain,
- Monitoring and controlling all construction teams in order to achieve the target assigned to every team member,
- Driving efficiently team performance ...
- Managing the renovation of Qatari embassy in Abu Dhabi in the Embassies’ Area,
- Responsible for overall project planning and scheduling, resource allocation, project accounting, and control, while providing technical direction and ensuring compliance with quality standards,
- Covering all the areas of project management: Project Planning, Cost Management, Time Management, Quality Management, Contract Administration, and Safety Management.
- Instructing and monitoring all phases of construction from permit, excavation until the handing over,
- Applying very high standards in the finishing process ...
- Managing the ROTANA hotel project in Abu Dhabi at ADNEC area,
- Instructing all stages of the 28 stories’ construction,
- Responsible for overall project planning and scheduling, resource allocation, project accounting, and control, while providing technical direction and ensuring compliance with quality standards ..
- Managing the construction of concrete cubic water tanks of 1000 m3 capacity each, tens of warehouses (60m*50m*16m each) and barracks (40m*12m*5.5m each),
- All projects in favor of the American army established in Iraq at the time to build the Iraqi army and strengthen its infrastructure.
Construction of 4 international highways with high standards:
- Ashanti region: 45 km
- Ashanti region: 55 km
- Ashanti region: 36 km
- Northern region: 50 km
- Designing and supervising 12 residential and commercial buildings,
- Leading the team engineers and workers.