Aqeel Ur rehman, Planning Engineer

Aqeel Ur rehman

Planning Engineer

KBR

Lieu
Émirats Arabes Unis
Éducation
Etudes secondaires ou équivalent, Civil Engineering
Expérience
18 years, 5 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :18 years, 5 Mois

Planning Engineer à KBR
  • Émirats Arabes Unis - Abu Dhabi
  • novembre 2023 à juin 2024

Control and implementation of EPC Contractors’ procedures and schedules, scheduling and progress control methodology, to monitor EPC contractors’ execution schedule on site, to check and approve EPC Contractors’ progress measurement and progress reports.
Reviewing contractor master EPC baseline schedule in line with Client requirement.
Coordinate with the Project Control team, and specifically with the GMP Planning & Reporting Lead, from whom he shall comply with rules and requirements.

Define and update as necessary, in liaison with the MP/PM Planning & Reporting Lead, suitable Weekly and Monthly report structure complying with Project needs and to develop and issue accordingly detailed and accurate GMP weekly and Monthly Reports (and any other report as requested).

Planning Engineer à BP ROO ( Tuner & Towsend)
  • Irak - Bassorah
  • février 2022 à février 2023

Control and implementation of EPC Contractors’ procedures and schedules, scheduling and progress control methodology, to monitor EPC contractors’ execution schedule on site, to check and approve EPC Contractors’ progress measurement and progress reports.

Support to Manager’s to develop works break down for baseline schedule.

Attending weekly, monthly progress meeting in order to line to match projects milestones.

Planning & Costing Engineer à TA'AZ Construction
  • Irak - Bassorah
  • décembre 2019 à janvier 2022

Road Work, Earth Work, Equipment's Foundations, Fencing Work, Concrete Paving, Concrete Demolition, Structure Work, Grouting Work
• Preparation of monthly valuation, submission to client, and agree the interim valuation with cost consultant.
• Attend WOP opening meetings, clarification meeting to finalized the requested
• Submission of VOWD (Volume of Work Done)
• Level -4 Schedule preparation & monitoring according to approved WOP.
• Preparing the measurement sheet for monthly Interim Payment Application (IPA) to submit consultant.
• Making variation order as per contract
• Solving the ongoing issue as per management direction.

Planning Engineer à Ghantoot General Contracting Road & Transport
  • Émirats Arabes Unis - Abu Dhabi
  • décembre 2012 à décembre 2019

• Preparation baseline schedule and monitoring at Level 4 according to agreed progress measurement sheet.
• Preparation of Weekly report monthly report as per project requirement.
• Preparation and monitoring of 3month look ahead schedule at level 4 details.
• Preparation of main activity KPI sheet as per requirement.
• Review the of for monthly Interim Payment application and finalizing with Consultant.
• Attend weekly and monthly progress meeting with consultant.
• Submission of VOWD (Volume of Work Done)
• Level -4 Schedule preparation & monitoring according to approved WOP.
• Preparing the measurement sheet for monthly Interim Payment Application (IPA) to submit consultant.
• Making variation order as per contract
• Solving the ongoing issue as per management direction.

Project à Expansion of District Cooling Plant Khalifa University Al
  • Émirats Arabes Unis
  • novembre 2011 à décembre 2011

Estimated Project Cost: 23 Million AED
Project Task. EPC Project 400ton District Cooling Plant (EPC)

6.3 PROJECT PLANNING ENGINEER | AFIC UAE / QATAR
Project-1 | Cathodic Protection of 460 Wellheads ADCO ASAB, Sahil, Shaha, QASAVIRA
Estimated Project Cost: 63 Million AED
Project-2 | Cathodic Protection of 7 Wellheads RASGAS QATAR.

project planning engineer à AFIC Abudulla Fouad
  • Émirats Arabes Unis - Abu Dhabi
  • novembre 2008 à novembre 2011

Project Task. EPC Project 460 Nos Wellhead in UAE & EPC of 7 Nos H2s Gas Injection Wells in Qatar

CIVIL SUPERVISOR à SANAMPROGETTI SPA
  • Arabie Saoudite
  • novembre 2007 à juillet 2008

Tasks. Sub-Station, Heavy Equipment’s Foundation, Electrical Trenches, Dike Walls of Evaporation Ponds. Pipe Sleepers FND.

Project Cost à Heavy Equipmen
  • avril 2003 à septembre 2006

130 Million $ US
Work Task. Sub-Station 130 KV,

planning engineer à DESCON Engineering UAE
  • Émirats Arabes Unis - Abu Dhabi
  • mars 2003 à juillet 2006

9. Planning site activities in detail, setting targets and accurately forecasting completion dates.
10. Preparation of Weekly report, Monthly report and updated Master baseline schedule as per the PMS.
11. Preparation of Extension of Time Claim and record the delay events as per claim.
12. Preparation of detail level -4 and KPI schedule for site construction team.
13. Conduct regular project meetings with (consultants, Sub-contractors) for project tracking and progress review.

Éducation

Etudes secondaires ou équivalent, Civil Engineering
  • à GCT LAHORE
  • janvier 1996

Specialties & Skills

OIL PAINTING
CABLEADO
CUSTOMER RELATIONS
DRIVING
ENGINEERING
FIRST AID
FORECASTING
MEETING FACILITATION
NETWORKING
PRIMAVERA

Langues

Anglais
Expert

Formation et Diplômes

Primavera P6 (Certificat)
Date de la formation:
March 2003