erection manager
MAPNA group
Total years of experience :31 years, 9 Months
my role in hist CCPP (4 GT +2 ST)in north of iran as erection manger was:
1- cordination and arrangemen of several contractors which were invovled to erection of different diciplines( mech, elec, i&c)according to erection plan
2- participate in daily meetings
3-report to project manager
4- preparing letters and reply to relevant parties
5-site visit and solve the remaining problems
i worked for Siemens company Iran branch (SSSK)for 3 years as field service eng in gas compression plants in iran
i started my job in CCPP(6GT +3ST)operation company in north of Iran. during commissiong time of this power plant we joint in SIemens commissiong team and after i was part of this team during all the tests for 5 years and after delivery of plant our maintenance job started for 7 years