Manager Projects
Exide Industries
Total years of experience :16 years, 4 Months
Addition of new building and new machine / Line, improving OEE
Distress and Asset identification and analysis for HIghway Management
Starting up of a new pet food plant - Soil to plant
1. Installation of Cassava Handling equipments (Unloading, peeling / washing equipments) imported from EBS Brazil.
2. Installation of Utilities including 1000KVA Genset and Weigh Bridge.
3. Maintenance of Process equipments and Utilities (Gensets, Boiler, Pumps, conveyors, Drier, Centrifuges / Separators)
4. Inventory Management - Both stores and ware house.
5. A lead mentor for Engineers and other employees.
1. Execution of Installation activity through single window.
2. Commissioning and training the end users in operation and maintenance
1. Maintenance of Process equipments and Utilities (Gensets, Boilers (Oil fired, coal fired, fluidized bed), Air-compressors, Chillers, Distillation columns, Reactors, filters, Driers, Conveyors, Heat exchangers, Pumps, centrifuges)
75.5 % in Aggregate of all 8 semesters. Passed with distinction.
65 % in Aggregate of all 3 years, Passed with first class