PROJECT ENGINEER
Shell India Ltd
Total years of experience :5 years, 1 Months
A. C8 Campaign. (Onshore and Offshore)
•PPA to PA (Panna Alpha platform) Process Platform 8” Fire Water Line with fire monitors Installation (8” =250 Mtr long).
•Satellite Platform Shutdown activities- 8 day’s (Tie point 12”/8”/6” Spool and Valves Hook up and new valves Replacements).
•Gas lift and water dumping lines installation at two satellite platform for 3 each Wells.
•Structural Job materials Erection at site. (More then. 30 MT).
•Piping Spools Installation and leak test/commissioning/handover to Process team. (Approx. 4200 Inch Dia)
•Satellite Platform Well head mezzanine deck Framing and Main deck Beams Replacement (Approx.= 6 MT& 8 MT)
•Satellite Platform (PC/PG/PF) CO2 Snuffing Skid with line installation and Commissioning.
B. Electrical Re-vamping Project Season-1 and 2. (Onshore and Offshore)
•Satellite platform (MA/PD/PB/PE/PA Platform) Battery charger panels and GDS, Telemetry, Lighting panels removal and New model (new version) panels’ installation.
•Satellite platform (MA/PD/PB/PE/PA Platform) Emergency and normal lights replacement.
•MCC and Switch Gear Room Revamping.
•All Panels Base plate replacement (Switch gear/ Telemetric Rooms)
C-7 Campaign/Electrical Re-vamping Project Season-1 (Onshore and Offshore)
•Satellite platform (MA/PD/PB/PE/PA Platform) Battery charger panels and GDS, Telemetry, Lighting panels removal and New model (new version) panels installation
•Satellite platform (MA/PD/PB/PE/PA Platform) Emergency and normal lights replacement.
•All Panels Base plate replacement.
•Switch gear/Telemetry room louvers and Doors replacement.
•Shutdown job at PPA and related satellite platforms. (7 day’s
C-6 Campaign (Onshore and Offshore)
•Piping & Pipe supports fabrication & installation work at Onshore/Offshore.
•At Spider deck level 12” and 10” tubular bracing replacement job at offshore.
•Solar panel frames fabrication & installation at Onshore/ Offshore.
•Shutdown job at PPA and related satellite platforms. (7 day’s)
•To Coordinating with Process Team to Execute the Job’s in Well Head Area/Production and Test Header Area
BPA-BPB RE-CONSTRUCTION Project. (Onshore and Offshore).
•7 metre Height Helideck lifting at BPA Platform.
•Existing Offshore Platform Crane Replacement (4 No’s) Part by part by using Barge crane,
•Involving in Procumbent of Carne Engines, Carbonates and Structural materials fabricating the A-Frame and Diesel Storage Shell’s.
•Involving the Fabrication of A Frame Structure and Diesel Storage Shell’s.
•Three major shutdowns at BPA & BPB platform. (15 Day’s each)
•Revamping of BPA & BPB process & related satellite platforms (piping, structural, Pipe Supports)
British Gas Exploration Production Indian Ltd
Project name: C3 & C4 Campaign (Onshore & Offshore). (
BE Mechanical Engineering