LEAD ENGINEER HVAC
Fortune Engineering & Energy
Total years of experience :21 years, 1 Months
Key responsibilities include;
• Managing complete Mechanical Scope for buildings, Power supply skids, Active Cooled Shelter &
Passive cooled Shelter, liaising with Sub-contractors, Vendors and Client.
• Site Survey, Site co-ordination and project co-ordination.
• Specification and RFQ preparation, TBE and CBE for HVAC & Plumbing system.
• Detailed Engineering and EPC activities.
• Assisting in Planning and scheduling EPC activities.
Projects Involved:
ADNOC ONSHORE : EPC for Process Control and Power Systems Upgrade at BAB
ADNOC GP : EPC for Replacement of Obsolete sales gas Metering Systems (Ongoing)
Dolphin Energy : EPC for Upgrade of EGA Facility for Continuous Gas Supply
Key responsibilities include;
• HVAC Design and adequacy checking of existing HVAC system in running Gas plants of ADNOC GP.
• HVAC design adequacy checking of offshore platforms for TOTAL Qatar, Qatar Petroleum and in
Abu Dhabi for ADNOC group of companies.
• Managing HVAC & Plumbing scope of projects liaising with Sub-contractors, Vendors and Client.
• HVAC/Plumbing FEED Engineering and detailed Engineering.
• Planning and scheduling EPC activities.
• Leading the Tendering and Estimation of small to medium sized Projects (both EPC and FEED)
• Specification and RFQ preparation, TBE and CBE for HVAC & Plumbing system.
• HVAC Design Engineering including Design Basis, Technical Specifications, Heat Load calculation
using HAP software, Duct sizing, Pipe sizing, Layout preparation, SLD’s, P&ID’s, Control
Philosophy, Equipment schedule, BOQ etc.
• Site Survey, Site co-ordination and project co-ordination.
• Attending FAT at suppliers premises.
• Participation in HAZOP, HAZID and design review meetings.
Projects Involved:
Qatar Petroleum : FEED For Halul Integrated Control System Capacity Expansion & New
LER-1
TOTAL Qatar : FEED for WP2 Technical Room upgrade in offshore platform.
ADNOC GP : FEED for GASCO HABSHAN 2 ESD System & Compressor 91/92 Control
System Upgrade
Rabigh II Refinery and Petrochemical project, Rabigh, Saudi Arabia
Client: Aramco Overseas and Sumitomo chemical.
This turnkey project includes 11 buildings (7 sub-station and 4 PIB’s) in HVAC scope.
Key responsibilities include;
• Leading a team of 2 Engineers + 2 Designers
• FEED Verification and preparation of Technical queries to client.
• Preparation of HVAC basic design philosophy, P&ID's, Control and Flow diagrams, Data sheets
and verification reports.
• Attending Kick-off meeting with client.
• Reviewing the Load calculations and equipment selection by the Engineers to be in-line with
ASHRAE and other applicable standards.
• Preparing HVAC Inquiry / technical specification for Vendors as per the preliminary design.
• Technical meeting with Clients.
• Weekly and monthly Project Progress reporting to Engineering manager.
• Allocating work to the Engineers and Designers.
• Preparation of Project deliverables with milestones.
• Attending Weekly Engineering meeting and discuss the various Issue of the Project.
• Coordinating with internal departments for various interfaces like civil, piping, Electrical,
Instrumentation Fire fighting etc.
• Reviewing / checking of Vendors quotation and assisting in Tender evaluation.
Karan Utilities and Cogeneration project, Khursaniya, Saudi Arabia.
Client: Saudi Aramco
This is a Turnkey Project for Petrofac (LSTK-3 contractor), in which the HVAC scope includes Design,
Installation, Erection and Commissioning in 3 buildings (Substation, PIB building and EDG building.
Key responsibilities include;
• Site co-ordination and engineering with the client for our design approval, other construction
related activities and closure of punch list to obtain the mechanical completion certificate.
NUON Power Plant: 1200 MW IGCC Power Plant, Netherlands.
Client: NUON Power
This is a Turnkey Project for MHI, including Design, Installation, Erection and Commissioning of 1200
MW IGCC power plant in Eemshaven, Netherlands. HVAC System is provided for 3 Turbine buildings,
3 Feed water pump buildings, Control building, Chemical storage, Air compressor, GIS buildings etc.
GULF JP NS & UT, Thailand.
Client: Gulf JP
This is also turnkey projects, which consists of 2 identical sites GNS and GUT each of 1600 MW,
which consists of various buildings which are supplied with Ventilation systems and Air conditioning
systems.
Proposal Projects:
a) Wang Noi Power plant, Thailand
b) Tuas 5 power plant: Extension of existing Tuas 3 and 4 Power plant, Singapore
c) Sembcorp Power plant, Singapore
d) Keppel Power plant, Singapore
Projects Involved, (Saudi Aramco Projects):
1) EWO-06C178: Upgrade Yanbu NGL Fire Training Ground and Replace Fire Training building.
The Job involved designing of HVAC systems for the new Fire training building and storage
facilities.
2) BI-10-00345: Khurais common facilities (buildings) Package 1.
The project has 2 packages, one with buildings and other plant facilities. My job involved basic
designing of HVAC systems for 12 buildings found in the utilities area.
3) BI-10-00209: Upgrade wastewater systems, Southern area Oil operations.
The Job involved designing of HVAC systems for the new chemical storage building, 2 nos.
Substations and guard house.
4) BI-10-00087: Upgrade JGP water & Spent caustic Systems, Ju’aymah Gas Plant.
The Job involved HVAC design and plumbing design for the new MBR building and waste water
treatment building.
Designing of the HVAC systems of a multi-storey building with complete detailed drawings of
the various parts involved like the ducts, ventilators, smoke dampers, fire dampers, grilles,
fittings, diffusers etc.,
▪ Input got from the client is the whole site layout, building layouts, architectural plan of the
building with the complete set of individual room details.
▪ Areas of each and every room are taken and the HVAC design is carried out according to the
needs.
▪ Calculations were done in ELITE HVAC software.
▪ Selection of each and every fixture such as diffusers, duct sizes, AHU’s is made and the layout
of the HVAC system is clearly drawn in AutoCAD.
▪ Output is of double line diagram according to the needs of the client.
▪ Diffuser schedules, temperature control notes and mechanical detail notes were clearly shown
as separate sheets.
▪ Detailing of pressure vessel (Autoclave) using the standard provided by the client (AS, AWS, API-
RP2standards).
▪ Detailing was done on primary basis where various details were done and the designing was
carried out based on those derived data.
▪ Assembly drawing was done using AutoCAD and exported to Microstation for utility purpose