DOMAR ESTREMADURA, Electrical Engineer

DOMAR ESTREMADURA

Electrical Engineer

OLAYAN GROUP

Location
Saudi Arabia - Khobar
Education
Bachelor's degree, BACHELOR IN SCIENCE IN ELECTRICAL ENGINEERING
Experience
22 years, 1 Months

Share My Profile

Block User


Work Experience

Total years of experience :22 years, 1 Months

Electrical Engineer at OLAYAN GROUP
  • Saudi Arabia - Khobar
  • My current job since August 2013

Project Title: Construction of Production Plant and Management Office of the Arabian Paper Products Company ( OLAYAN GROUP ) at Khobar Saudi Arabia.

• Supervision / Engineering of project assignments.

• Review shop drawings from contractor, Electrical, Medium and Low Voltage, Substation as per Saudi Electric Standard, Mechanical, ( Vacuum, Compressed Air, Chiller, HVAC system, Water System, Fire Protection System, Civil and and other trade works.

• Review plans and approved submittals from contractor, as per designed drawings and standard or on Bill of Quantities. Electrical (Cable XLPE, Direct Burial, Grounding Cable, Fire Protection and Alarm System, Telephone and Computer Data Cables.)

• Inspection and do recommendation work by the contractor that ensured as per design approved drawings, safety abd standard, on Electrical, Civil, Mechanical, and Plumbing works.

• Ensure safety of work environment inside the site work premises.

• Witness all activities done by contractor on minor or critical works, n Electrical, Mechanical, Civil, and Plumbing works.

• Assist in final testing, rotation check, control simulation and commissioning.

• Ensure that all materials used was on standard specification and quantity as per Bill of Quantities, and Drawing.

• Review the submit work schedule of the contractor, and ensure progress work was on schedule and not delay.

Operational Staff at Ford Motor Company Philippines
  • Philippines
  • April 2002 to April 2014

Operational Staff
TCF Assembly Dept.
April 2002 to April 2004


• Assigned as door mechanism process assembly.
• Also perform other process on assembly section, ( instrumental panel, heater, cooling, assembly, radiator, headlights and tail lights, assembly of computer box and fuses.)
• Ensure electrical wiring and coupling was tightly locked together, and wiring harness was free from any open and grounded circuit.
• Perform process finished on time, and ensure no delays and failure upon doing process to decrease downtimes.
• Managed parts free from defects, and was on its location for sequential and no delaying tactics.
• Ensure all pneumatic and hydraulic tools were calibrated to make sure all process was done well.
• Assigned at final test process for test drive and water leak process.

Building Electrical Auditor/ Electrical Engineer at FPD Asia Property Management Services
  • Philippines
  • November 2011 to July 2013

Position:
Building Technical Auditor
Nov. 21, 2011 to Present


Regular

• Responsible for implementing the standard audit checklist of FPD Asia Property project particularly Electrical/ Mechanical / Electronic equipment of managed of FPD such as not limited to the following:

(ELECTRICAL)
• Power Center
• Power Transformer
• High, Medium, Low Voltage Switch Gear
• Load Break Switch
• Electrical Panels
• Power Capacitor
• Distribution Lines and protective devices
• Electrical Rooms
• Manual/Automatic Transfer Switch
• Fire Detection & Alarm System
• Building Management/Automation System
• CCTV System
• Traffic Alarm System
• General Lighting
• General Power & Auxiliary
• General Wiring and Conducting & other electrical appurtenances
• Electrical Permits including ERC, Certificate of Inspection
• As Built Plans & Equipment Manuals.
• Responsible for preparing the electrical audit report and the corresponding corrective action & preventive action report that will issued to the audited project.


(MECHANICAL)
• HVAC including controls and Instrumentation
• Water Supply Pumps and Tanks Including Control and Instrumentation
• Sewage Pump and STP facilities including Controls and Instrumentation
• Submersible Pumps Including Controls and Instrumentation
• Elevators including Control and Instrumentation
• Generators including Control and Instrumentation
• Fire and Jockey Pumps
• All riser pipes and distribution (Plumbing, Sanitary, and Fire Protection)
• Attend to the meetings with the auditee or client concerning the audit conduct as necessary.



Occasional
• Responsible for inspection and preparation of scope of work, estimation and terms of reference for upgrading project of managed project.
• Responsible in auditing properties that are not under management of FPD which are treated a revenue project.
• Responsible for Project Management of Services of FPD on certain revenue accounts.
• Assigned to projects as a reliever for Building Engineer, Fit-out Engineer if so needed.

Trade Engineer at Hotel Sogo
  • Philippines
  • August 2011 to November 2011

Position:
Trade Engineer
August to November 2011

• Supervision/ Engineer of all trade works (Electrical, Mechanical, Plumbing Auxiliary of assigned projects.
• Do estimation (BOM) of Electrical, Mechanical, Plumbing for in-house estimates.
• Responsible for preparation of Bid docs for contractors.
• Do work schedule milestone of the projects.
• Conduct meeting of all contractors for daily, weekly, monthly accomplishments and update.
• Responsible for the safety of the contractors on activities.
• Signing of permits, gate pass of all materials going in and out on the site.
• Conduct site inspection for the progress of work schedule.

Project Electrical Engineer at Harmonic System Inc
  • Philippines
  • February 2011 to August 2011

Position
Project Engineer
February 7, 2011 to August 2011

Petron Bataan Refinery ( assigned project )
Limay, Bataan
Title: ( Transfer of Power Source from Substation F to Substation N )

• Supervision / Engineering of work on Electrical and Civil works.
• Handled 25 person including electricians and civil.
• Excavation, concrete cutting, restoration and concreting.
• Cable lying of Power and Control cables.
• Fabrication and Installation of RSC pipes.
• Termination of Power Supply.
• Assist in final testing, rotation check, control simulation and commissioning.
.




Union Bank Philippines ( assigned project)
Ortigas, Pasig City
Title: ( Electrical Engineer )

• Supervision / Engineering of electrical activities of the building.
• Implement assignments and tasks of electricians.
• Do weekly accomplishments report
• Coordinate issues and problem with building manager and engineer.
• Do working schedule and Daily Time Records of electricians.

Equipment Engineer at Analog Devices Inc
  • Philippines
  • September 2005 to December 2010

Equipment Engineering
Probe/WLCSP Department
September 13, 2005 December 2010

• Maintains specified working conditions of all production line equipment.
• Perform preventive maintenance of all machines as per schedule to ensure machine efficiency and performance.
• Conduct effective corrective actions for minor / intermediate and major machine breakdown.
• Performs machine parameters checking and calibration as required.
• Participates in the various line activities aiming to continuously improve machine and process efficiency and reliability either through self-initiatives or direct assignment by superior or team.
• Performs other related duties that may be assigned by the superior from time to time.
• Provided Interim, corrective and preventive actions supported evaluations and data.
• Involved in the Optimization of vision inspection parameters thru the Design of Experiment to reduce over rejection and over acceptance.
• Increased Manufacturing yield by optimization of visual mechanical inspection parameters to reduce the over rejection

Assembly Operator at Fujitsu
  • Philippines
  • April 2005 to September 2005

Assembly Operator
Mechatronics Division
April 2005 to September 2005

• Perform assigned process on assembly of ATM machines on internal parts, by mechanical electrical and electronic parts.
• Do electrical checking that free from faulty electrical wiring, and insure good and quality wire harnessing on BDU and BRU units.
• Conduct mechanical and electrical action as encounter machine
problem.
• Ensure mechanical alignment and parts sequential process on installing mechanical parts.
• Perform calibration on equipment used on prior doing process assembly.
• Test machine efficiency by performing demo run, and effectiveness at given machine trial data.

Education

Bachelor's degree, BACHELOR IN SCIENCE IN ELECTRICAL ENGINEERING
  • at TECHNOLOGICAL UNVERSITY OF THE PHILIPPINES
  • August 2002

Specialties & Skills

Property Management
Project Management
Engineering