supervision of quality control tests of embankment materials, borrow areas, and quarries activities carried out by the project contractor CCMD, arranges the working schedule and coordination for the laboratory staff, in addition to review of monthly and annual testing activities reports.
b. Embankment Dam Laboratory Engineer
tasks include supervision of construction material testing such as cement, fly ash, silica fume, reinforcing steel bars, etc…, as well as review of concrete mix deign for normal and high strength concrete etc…
Ministry of Water Resources and Electricity -Dams Implementation Unit, Seconded to Lahmayer Int (GmBh) in October 2005 for the construction supervision of Merowe Dam Project ( Value of 1500 million US$ of which about 700 US$ million is for the Civil works).
Elfatih Osman Ahmed Khalid-Consultant Civil Engineer (Sudan)-Curriculum Vitae Page 4 of 6
Project: Merowe Dam Project (Sudan)
* The project is consisting of a concrete dam, incorporating the spill and 1250 MW powerhouse, two concrete rock fill dams(5million m3), an earth core rock fill dam (ECRD)(7.5 million m3), two earth core rock fill dykes (0.6million m3), and a cutoff wall for seepage control under ECRD.
* Responsibilities: the main tasks are
tasks include but not limited to supervision of all quality control testing for embankment materials, roads to the dam, review and approval of routine test results and preparation of daily and monthly reports on work progress, as well as following up of training program for fresh engineers.
supervision of construction of plastic concrete cut-off wall, responsibilities including quality control and construction supervision of the twp phase plastic concrete cut-off wall for the Earth core rock fill dam (ECRD) performed by the subcontractor
supervision of geotechnical testing works performed by the contractor CCMD J.V responsibilities include but not limited to Quality control and quality assurance of materials used for embankment construction and concrete works.
supervision of earth works construction activates carried out by contractor (CCMD), including excavation, fill materials, and roads
testing and Practice in Sudan’’, a presentation at Roseries Dam Heightening Project Site, 11 November 2011.
3. Ahmed M. Elsharief, Elfatih O. Ahmed, and Yahia A. M. Zien
Building and Road Research Institute -University of Khartoum (BRRI) Project: Infrastructure Projects (Sudan)
* Responsibilities:-
Elfatih Osman Ahmed Khalid-Consultant Civil Engineer (Sudan)-Curriculum Vitae Page 5 of 6
1. The main task is technical and administration follows up of all site investigation, lab testing, report writing for various infrastructures such as buildings, dams, Transmission lines etc...
2. To plan, manage and coordinate the effort of team members in order to execute the works as per plan, and in compliance with the international specifications as well as with the projects requirements and to deliver the project in time and within the budget.
Engineering Services and Design (ESD) Project: Infrastructure Projects (Sudan)
* The projects cover a wide ranges of civil engineering structures and applications such as piling, laboratory testing, field testing, geotechnical investigation and reporting for educational and industrial facilities
* Responsibilities: include but not limited to: lead the geotechnical field and laboratory staff, participation on structural design of some medium size to large buildings.
Piling Foundation for Ariab Head Quarter-Elbaladia Street.
* Responsibilities:-
1. Supervision of pile foundation construction, a total of 78 concrete piles.
2. Supervision of quality control of casted concrete (such as slump test, concrete cubes)
Publications: -