Project Manager
SEG
Total years of experience :13 years, 7 Months
Managed a Government construction project of 5 regional hospitals (secondary-level hospitals) in key areas in Cameroon: turnkey projects of 14, 000 m2 each - delivery scheduled within 18 months.
Collaborated with bureau VERITAS.
Organized and headed site progress and quality control meetings with project engineers.
Managed and controlled tendering and estimation.
Supervised and followed up shop drawings, material submittals and procurement.
Managed planning, cost control and subcontracting.
Prepared cycle reports to the board of SEG.
Participated and represented SEG in cycle meetings held with the government of Cameroon to discuss the advancement of the project.
Managed Earthwork construction project for crude oil storage tank for Total refineries in Congo.
Prepared and designed work procedures outlining the objectives, the activities and the execution,
Developed the project execution plans,
Prepared and followed up the initiation of the work permit with the HSE department,
Prepared and supervised field procurement, cost control, progress reports and planning updates in accordance with the project’s requirements.
Supervised the site activities and the distribution of machinery and vehicles.
Collaborated and coordinated with QA/QC for geotechnical testing.
Participated in the preparation of toolbox talks and procedural compliance with HSE regulations.
Managed and delivered a turnkey residential project of 40 apartments located in prime area in Central Beirut.
Monitored and supervised concrete and finishing work.
Prepared and signed BOQs, payment certificates, purchase orders, site inspections and variation orders.
Supervised the accordance between Design and execution.
Collaborated with subcontractors the accordance of Planning and Cost with Design.
Ensured and coordinated shop drawings submittals.
Shop drawings submittals follow up.
Variation order preparation.
Supervised and Coordinated technical aspects of 2 construction projects in Beirut:
1. Damac Tower - Versace home (32 floors tower, Downtown Beirut) : from excavation phase till handing over
2. Toyota Lexus city (Hazmieh-Mount Lebanon): from excavation phase till handing over.
Followed up daily site activities.
Checked execution in accordance with the drawings, specs and BOQ.
Supervised and monitored daily the site labor force and the work of subcontractors.
planned the work and efficiently organized the plant and site facilities to meet deadlines.
oversaw quality control and health and safety matters on site.
Toyota Lexus city - Hazmieh: From excavation till handing over, (concrete phase).