Project Engineer
ITEFAQ Steel Company
Total years of experience :17 years, 1 Months
• Erection and Install 22KV &6.6KV Switchgear (Bus bar System, Rectifiers and Reactors for DC Arc Furnace).
• Erection and Install 52MVA &22MVA Transformers for Arc Furnaces.
• Follow up cable laying, cable termination and installation of cable tray according to project specification.
• Carry out Installation, Commissioning and Calibration of Analog and Digital Instruments.
• Install and commissioning complete automation system, Siemens plc. S7-400, Siemens wincc “HMI”.
• Install and commissioning RCB Burner using Gas and Oxygen PI&PID Control system by SVAI Germany.
• Install and commissioning for RHF reheating furnace using gas and oxygen to reach temperature 1200 degree for steel billet for rolling mill.
• Erection and install complete hydraulic units 150 bar to using in all movement of furnace.
• Erection and install motors from 22KW up to 750KW with Siemens and ABB drives.
• Erection and install complete water treatment plant using for direct and indirect cooling system for steel plant.