Islam abd Elrhman Hussein, Instrumentation Engineer PMT

Islam abd Elrhman Hussein

Instrumentation Engineer PMT

WOOD PLC

Location
Egypt - Alexandria
Education
Bachelor's degree, industerial electronic &control engineering
Experience
19 years, 0 Months

Share My Profile

Block User


Work Experience

Total years of experience :19 years, 0 Months

Instrumentation Engineer PMT at WOOD PLC
  • Egypt - Alexandria
  • My current job since October 2022

▪ Leading and managing complete instrumentation, FGS and Telecommunication construction works and teams.
▪ Support quality assurance and verification role on engineering deliverables.
▪ Review / approve of all the remaining engineering deliverables (Hook ups, Index, Loop Drawing, Logic diagram, Data sheets, layouts.... etc.) and Review Final Record Book and Vendor Print .
▪ Identify issues and problems, develop appropriate solutions.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Ensure the project scope is clear and that changes comply with project change management processes.
▪ Witness instrumentation loop checking activities.
▪ Witness Instrumentation installation and testing QC inspections according to Project Inspection and test plan ITP .
▪ Issue instrumentation installation progress reports(daily and monthly ).
▪ Witness the calibration activities of all type of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
▪ Review instrumentation installation and testing procedure with reference to project specs and standard.
▪ Ensures the review and timely submission of the Marked-Up As-Built drawings and availability of all Final Documentation prior to the Provisional Acceptance.
▪ Witness and lead of the Instrumentation MC mechanical completion walk down for Process and non process instrumentation systems and punch list clearance.
▪ Ensure Quality inspection of all the activity at the site as per the specs and standard of the project.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures.
▪ Understand the Project standards and ensure the design meets the requirements.

Instrumentation Senior Engineer PMT at Worley
  • Egypt - Asyut
  • June 2020 to June 2022

▪ Leading and managing complete instrumentation, FGS and Telecommunication construction works and teams.
▪ Support quality assurance and verification role on engineering deliverables.
▪ Review / approve of all the remaining engineering deliverables (Hook ups, Index, Loop Drawing, Logic diagram, Data sheets, layouts.... etc.) and Review Final Record Book and Vendor Print .
▪ Identify issues and problems, develop appropriate solutions.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Ensure the project scope is clear and that changes comply with project change management processes.
▪ Witness instrumentation loop checking activities.
▪ Witness Instrumentation installation and testing QC inspections according to Project Inspection and test plan ITP .
▪ Issue instrumentation installation progress reports(daily and monthly ).
▪ Witness the calibration activities of all type of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
▪ Review instrumentation installation and testing procedure with reference to project specs and standard.
▪ Ensures the review and timely submission of the Marked-Up As-Built drawings and availability of all Final Documentation prior to the Provisional Acceptance.
▪ Witness and lead of the Instrumentation MC mechanical completion walk down for Process and non process instrumentation systems and punch list clearance.
▪ Ensure Quality inspection of all the activity at the site as per the specs and standard of the project.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures.
▪ Understand the Project standards and ensure the design meets the requirements.

Instrumentation Senior Engineer PMT at ERC (DNV GL)
  • Egypt - Cairo
  • January 2018 to February 2021

▪ Leading and managing complete instrumentation, FGS and Telecommunication construction works and teams.
▪ Support quality assurance and verification role on engineering deliverables.
▪ Review / approve of all the remaining engineering deliverables (Hook ups, Index, Loop Drawing, Logic diagram, Data sheets, layouts.... etc.) and Review Final Record Book and Vendor Print .
▪ Identify issues and problems, develop appropriate solutions.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Ensure the project scope is clear and that changes comply with project change management processes.
▪ Witness instrumentation loop checking activities.
▪ Witness Instrumentation installation and testing QC inspections according to Project Inspection and test plan ITP .
▪ Issue instrumentation installation progress reports(daily and monthly ).
▪ Witness the calibration activities of all type of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
▪ Review instrumentation installation and testing procedure with reference to project specs and standard.
▪ Ensures the review and timely submission of the Marked-Up As-Built drawings and availability of all Final Documentation prior to the Provisional Acceptance.
▪ Witness and lead of the Instrumentation MC mechanical completion walk down for Process and non process instrumentation systems and punch list clearance.
▪ Ensure Quality inspection of all the activity at the site as per the specs and standard of the project.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures.
▪ Understand the Project standards and ensure the design meets the requirements.

Instrumentation Construction Superintendent Engineer at RINA
  • Egypt
  • January 2017 to January 2018

▪ Leading and managing complete electrical, instrumentation, FGS and Telecommunication construction works and teams.
▪ Identify issues and problems, develop appropriate solutions.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Ensure the project scope is clear and that changes comply with project change management processes.
▪ Witness instrumentation loop checking activities.
▪ Witness electrical and Instrumentation installation and testing QC inspections according to Project Inspection and test plan ITP .
▪ Issue E&I installation progress reports(daily and monthly ).
▪ Review E&I installation and testing procedure with reference to project specs and standard.
▪ Ensures the review and timely submission of the Marked-Up As-Built drawings and availability of all Final Documentation prior to the Provisional Acceptance.
▪ Witness and lead of the E&I MC mechanical completion walk down for Process and non process systems and punch list clearance.
▪ Ensure Quality inspection of all the activity at the site as per the specs and standard of the project.
▪ Monitors and administers EPC Contractor quality performance through to achieving the Provisional Acceptance.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures.

E&I construction Supervisor at SITEK Caspian LLP Company
  • Kazakhstan
  • August 2016 to October 2016

 Supervise the Construction and execution activities related to various field instruments, analyzers, JB junction boxes, and secondary cable trays.
 Supervise the instrument main and secondary cable laying activities.
 Supervise the cable termination and testing (megger and continuity tests) activities.
 Supervise the impulse tubing installation and testing activities.
 Responsible for cost effective and scheduled completion of E&I construction activities.
 Ensures that all the works done are in accordance with the approved construction drawings, and project procedures.
 Issue of site E&I installation progress reports ( daily, weekly and monthly ).
 Prepare E&I system marked-up / as-built drawing and handover to the main contractor.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

Instrumentation construction supervision/ QC Engineer at ENPPI
  • Saudi Arabia - Yanbu
  • January 2016 to August 2016

▪ Leading instrumentation, FGS, and telecommunication systems construction activities and teams.
▪ Supervise the Construction and execution activities related to various instruments, control valves, analyzers, control systems, shutdown systems to insure all as per project specs and procedures.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Responsible for cost effective and scheduled completion of activities.
▪ Prepare technical specifications for purchase of instrument construction materials, consumables and equipment.
▪ Estimation of materials, resources and tools required for the execution of the project.
▪ Develop budgets, estimating labor, material, and construction costs.
▪ Issue of site instrument installation progress reports (weekly and monthly ).
▪ Identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
▪ Responsible for the achievement of the MC instrumentation mechanical completion certificate according to P&ID system limits, and leading instrument PLWD (Punch List Walk Down) and punch list clearance.
▪ Responsible for all instrumentation installation and testing inspections according to SATIP (Typical Inspection plan) including SAIC (inspection checklist) or SATR (Test Report) .
▪ Raise NCR (Non Conformances Report) as required.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
▪ Understand the Project standards and ensure the design meets the requirements

Instrumentation QC Senior Engineer at Egyption polyethylene Project (ENPPI)
  • Egypt - Alexandria
  • December 2014 to December 2015

▪ Review and approve all instrument installation and testing procedures prepared by subcontractors and sent to Clint to final confirmation.
▪ Leading the instrument QC inspectors teams and prioritizes the QC inspection activities according to project schedule and plan.
▪ Attend the project QA/QC weekly meeting to discuss QC proactive and standard violation issues.
▪ Prepare instrument QC database of project according to project instrument Index.
▪ Manage the QC inspection activities of instrumentation material receiving, installation and pre-commissioning power down activity and ensure all following the procedure compare all the result to the standard and arrange for walk down with the Clint QA\QC supervisor for final approval and signature.
▪ Ensure Quality inspection of all the activity at the site as per the specs and standard of the project.
▪ Raise (NCR ) Non Conformances report and / or instrument damage reports as required.
▪ Ensure the achievement of the MC certificate according to priority and system limits done by commissioning, and leading instrument PLWD (Punch List Walk Down) and punch list clearance.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures.
▪ Understand the Project standards and ensure the design meets the requirements.

Instrumentation Construction supervision /QC Engineer at YASREF Refinery Project SP-1 SAUDI ARAMCO (ENPPI)
  • Saudi Arabia - Yanbu
  • February 2013 to December 2014

▪ Leading instrumentation, FGS, and telecommunication systems construction activities and teams.
▪ Supervise the Construction and execution activities related to various instruments, control valves, analyzers, control systems, shutdown systems to insure all as per project specs and procedures.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Responsible for cost effective and scheduled completion of activities.
▪ Prepare technical specifications for purchase of instrument construction materials, consumables and equipment.
▪ Estimation of materials, resources and tools required for the execution of the project.
▪ Develop budgets, estimating labor, material, and construction costs.
▪ Issue of site instrument installation progress reports (weekly and monthly ).
▪ Identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
▪ Responsible for the achievement of the MC instrumentation mechanical completion certificate according to P&ID system limits, and leading instrument PLWD (Punch List Walk Down) and punch list clearance.
▪ Responsible for all instrumentation installation and testing inspections according to SATIP (Typical Inspection plan) including SAIC (inspection checklist) or SATR (Test Report) .
▪ Raise NCR (Non Conformances Report) as required.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
▪ Understand the Project standards and ensure the design meets the requirements

Instrumentation Construction supervision /QC engineer at YCOT Saudi ARAMCO(YASREF crud oil supply facility )ENPPI
  • Saudi Arabia - Yanbu
  • April 2014 to September 2014

▪ Leading instrumentation, FGS, and telecommunication systems construction activities and teams.
▪ Supervise the Construction and execution activities related to various instruments, control valves, analyzers, control systems, shutdown systems to insure all as per project specs and procedures.
▪ Coordinate the interfaces with all construction disciplines and commissioning departments.
▪ Responsible for cost effective and scheduled completion of activities.
▪ Prepare technical specifications for purchase of instrument construction materials, consumables and equipment.
▪ Estimation of materials, resources and tools required for the execution of the project.
▪ Develop budgets, estimating labor, material, and construction costs.
▪ Issue of site instrument installation progress reports (weekly and monthly ).
▪ Identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
▪ Responsible for the achievement of the MC instrumentation mechanical completion certificate according to P&ID system limits, and leading instrument PLWD (Punch List Walk Down) and punch list clearance.
▪ Responsible for all instrumentation installation and testing inspections according to SATIP (Typical Inspection plan) including SAIC (inspection checklist) or SATR (Test Report) .
▪ Raise NCR (Non Conformances Report) as required.
▪ Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
▪ Understand the Project standards and ensure the design meets the requirements

Instrumentation construction supervision/Field Engineer at 200,000 MTA POLYSTYRENE Project (ENPPI)
  • Egypt - Alexandria
  • February 2012 to February 2013

 Supervise and monitor instrumentation and FGS detection system construction works and teams.
 Identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
 Coordinate the interfaces with all construction disciplines and commissioning departments.
 Responsible for cost effective and scheduled completion of instrument and fire and gas detection system construction activities.
 Prepare technical specifications for purchase of instrument and FGS detection system construction materials, consumables and equipment.
 Estimation of materials, resources and tools required for the execution of the project.
 Review of site instrument/FGS installation progress reports ( daily, weekly and monthly ).
 Issue the instrument/FGS damage reports as required.
 Supervise the calibration activities of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
 Attend the project LOSH (limits of system handover ) walk through with the commissioning and operation teams.
 Supervise and tracking the clearance of instrumentation punch items resulting from LOSH walk through.
 Provides recommendation on all F&G detection system construction work to assure a functionality and final product.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

Instrument Construction Supervision/Field Engineer at WDDM PHASE VII Main Compression BURULLUS GAS (ENPPI)
  • Egypt - Alexandria
  • July 2011 to February 2012

 Supervise and monitor instrumentation and FGS detection system construction works and teams.
 Ensures that all the works done are in accordance with the approved construction drawings, contract documents, project specifications, and all applicable standards whether local, national or international standards.
 Coordinate the interfaces with all construction disciplines and commissioning departments.
 Identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
 Responsible for cost effective and scheduled completion of instrument and fire and gas detection system construction activities.
 Prepare technical specifications for purchase of instrument and FGS detection system construction materials, consumables and equipment.
 Estimation of materials, resources and tools required for the execution of the project.
 prepare of site instrument/FGS installation progress reports ( daily, weekly and monthly ).
 Issue the instrument/FGS damage reports as required.
 Supervise the calibration activities of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
 Attend the project LOSH (limits of system handover ) walk through with the commissioning and operation teams.
 Supervise and tracking the clearance of instrumentation punch items resulting from LOSH walk through.
 Witness the FGS control system SAT (site acceptance test) activities.
 Witness the Fire and Gas detection system (FGS) loop checking activities.
 Witness FGS control system cause and effect tests.
 Provides recommendation on all F&G detection system construction work to assure a functionality and final product.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

Instrumentation Construction Supervision/Field Engineer at Upgrade of Aqaba Compression Station (ENPPI)
  • Jordan - Aqaba
  • March 2011 to July 2011

 Supervise and monitor instrumentation and FGS detection system construction works and teams.
 Coordinate the interfaces with all construction disciplines and commissioning departments.
 Identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
 Responsible for cost effective and scheduled completion of instrument and fire and gas detection system construction activities.
 Ensures that all the works done are in accordance with the approved construction drawings, contract documents, project specifications, and all applicable standards whether local, national or international standards.
 Prepare technical specifications for purchase of instrument and FGS detection system construction materials, consumables and equipment.
 Estimation of materials, resources and tools required for the execution of the project.
 Review/ approve of site instrument/FGS installation progress reports ( daily, weekly and monthly).
 Review the instrument/FGS damage reports as required.
 Supervise the calibration activities of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
 Arrange for project LOSH ( limits of system handover ) walk through with the commissioning and operation teams.
 Supervise and tracking the clearance of instrumentation punch items resulting from LOSH walk through.
 Provides recommendation on all F&G detection system construction work to assure a functionality and final product.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

Instrumentation construction supervision engineer at ENPPI (C2&C3 MAXMIZATION L.P.G Project)
  • Egypt - Alexandria
  • December 2009 to February 2011

 Supervise the Construction and execution activities related to various field instruments, analyzers, JB junction boxes, main& secondary cable trays and control system panels.
 Supervise the instrument main and secondary cable laying, termination and testing activities.
 Supervise the impulse tubing installation and leak /pressure testing activities.
 Supervise the instrument supports and farms fabrication activities.
 Ensures that all the works done are in accordance with the approved construction drawings, and project procedures.
 Prepare technical specifications for purchase of instrument construction materials, consumables and equipment.
 Estimation of materials, resources and tools required for the execution of the project.
 Issue of site instrument/FGS installation progress reports ( daily, weekly and monthly ).
 Issue the instrument/FGS damage reports as required.
 Supervise the calibration activities of instrumentation transmitters, Control/ON-OFF valves and Pressure relive/safety valves.
 Supervise and tracking the clearance of instrumentation punch items resulting from LOSH walk through.
 Review of all the engineering drawings (PID, Loop Drawing, Logic diagram, schedule, layouts etc.) and identify any Modification as required as site condition, Discuss and solve any technical Query and Final Review of marked-up / as-built drawing and handover to the client.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

Instrumentation Construction Supervisor Engineer at xervon thysenkrup
  • Egypt - Alexandria
  • March 2009 to December 2009

 Supervise the Construction and execution activities related to various field instruments, analyzers, JB junction boxes, and secondary cable trays.
 Supervise the instrument main and secondary cable laying, termination and testing activities.
 Supervise the impulse tubing installation and testing activities.
 Supervise the instrument supports and farms fabrication activities.
 Responsible for cost effective and scheduled completion of instrument and fire and gas detection system construction activities.
 Ensures that all the works done are in accordance with the approved construction drawings, and project procedures.
 Estimation of materials, resources and tools required for the execution of the project.
 Issue of site instrument/FGS installation progress reports ( daily, weekly and monthly ).
 Issue the instrument/FGS damage reports as required.
 Prepare instrumentation and FGS system marked-up / as-built drawing and handover to the main contractor.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

Instrumentation Construction Supervisor engineer at sidikrir combined cycle project (2*250MW Gas turbin) khromika company
  • Egypt - Alexandria
  • January 2008 to March 2009

 Supervise the Construction and execution activities related to various field instruments, analyzers, JB junction boxes, and secondary cable trays.
 Supervise the instrument main and secondary cable laying activities.
 Supervise the cable termination and testing (megger and continuity tests) activities.
 Supervise the impulse tubing installation and testing activities.
 Supervise the calibration activities of field instruments and control /ON-OFF valves.
 Responsible for cost effective and scheduled completion of instrument and fire and gas detection system construction activities.
 Ensures that all the works done are in accordance with the approved construction drawings, and project procedures.
 Estimation of materials, resources and tools required for the execution of the project.
 Issue of site instrument/FGS installation progress reports ( daily, weekly and monthly ).
 Issue the instrument/FGS damage reports as required.
 Prepare instrumentation and FGS system marked-up / as-built drawing and handover to the main contractor.
 Responsible for ensuring all aspects of the project comply with statutory HSE requirement and corporate HSE policies and procedures
 Understand the Project standards and ensure the design meets the requirements

I&C maintenance Engineer at west delta electricity production(sidi krir power station)
  • Egypt - Alexandria
  • October 2004 to October 2007

 Leads the I&C Maintenance Technicians and ensures a high level of efficiency within the Team;
 Trouble shooting instrumentation loops including PLC, DCS & ESD.
 Supervise the calibration activities of all type of instrumentation transmitters, switches, Control/ON-OFF valves.
 Ensures that all necessary tools are available to ensure safety whilst working on equipment;
 Ensures all necessary precautions are taken by himself, the I&C Technicians whilst undertaking any jobs, Installing & Configure the new instruments.
 Attempts all possible means of reducing equipment downtime and ensuring high plant availability.
 Performs Root Cause Analysis of failures.
 Works with Plant Operations Personnel to resolve problems encountered with I&C equipment.
 Verifies equipment settings, testing and energization requirements.
 Plans for and ensures that maintenance on all I&C equipment is in accordance with OEM Manuals for the equipment;.

Education

Bachelor's degree, industerial electronic &control engineering
  • at fuclty of electronic engineering \menofia universty
  • August 2004

Specialties & Skills

Instrumentation
Instrument Control
Commissioning
Relay based control system
PLC trubleshooting
PLCprogramming
operating of steam power plant
ms office
Control system understand

Languages

Arabic
Expert
English
Expert

Memberships

Egyptian Engineering Syndicate.
  • Instrument Engineer
  • October 2004
Saudi Council of Engineers
  • Instrument Engineer
  • February 2014

Training and Certifications

Instrument QC inspector Approval for YASREF(Yanbu Aramco Sinopec Refinary) Projects (Certificate)
Date Attended:
March 2013
Valid Until:
March 2015
Instrument QC inspector Approval for YST(Yanbu South Terminal ) Projects (Certificate)
Date Attended:
February 2016
Valid Until:
January 2018
Instrument QC inspector Approval for YASREF(Yanbu Aramco Sinopec Refinary) Projects (Certificate)
Date Attended:
August 2015
Valid Until:
August 2017