Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
Razvan Gabor, P6 Planning & Estimating Engineer

Razvan Gabor

P6 Planning & Estimating Engineer·Global Rail Construction

United Kingdom

Master's degree, Construction Rehabilitation

Work experience

Total years of experience: 15 years, 9 months

P6 Planning & Estimating Engineer

September 2016 - Present

Global Rail Construction

London, United Kingdom

September 2016 - Present

At GRCL I am responsible for Tender Planning and Project Planning, scheduling, resource loading/management, progress updates and relevant reporting of various project for major Rail, Civils and DNO companies by using Primavera P6.
Creating estimates with quantity lists and prices.

Company industry:
Construction & Building
Job role:
Other

Primavera P6 Planning Engineer

September 2015 - August 2016

Deva Gold

Romania

September 2015 - August 2016

Construction of a Gold Mine in Certej, Hunedoara County, Romania with the major shareholder Eldorado Gold (http://www.eldoradogold.com/assets/europe/projects/certej/) which involves: Modifying the existing pit, Erection of tailings facilities(Embankments), Utilities, Roads and the Process Plant.
▪My principle role in this company is Planning Engineer. I use Primavera P6 or MS Project depending by the contractor. I use those programs to plan the works for each contract.
▪I plan activities with relationship between them, roles, resources and cost.
▪I maintain contact with each contractor to receive weekly reports of the status of their works to be able myself to update the Plan and create reports for my Project Manager.
▪I supervise carefully each milestone or each critical activity and report to the Project Manager.
▪I am able to create any kind of reports: red line progress reports, earned value reports, cost and labour reports.
▪I am able to re-plan a schedule witch has delays, level resources, create roles, supervise budgeted cost with actual costs.
Beside this, I have other roles depending of the tasks of each day:
▪Maintain contact with the designer, verify drawings, list of quantities and costs.
▪Prepare documentation for permitting.
▪Prepare documentation for biding, compare offers, award contract.
▪If needed, drawing or modify drawings in AutoCad / Tekla Structures.
▪Prepare estimates for the construction works realised on our own.
Setting out and Supervising teams of 5-15 people and equipment for different activities on site: Site clearance, Deforestations, Earth levelling, Foundations, Roads rehabilitation, Old buildings rehabilitation, Demolitions, Steel structures erection, Power supply (water, energy), Drainages.

Company industry:
Mining & Quarrying
Job role:
Other

Estimating & P6 Planning Engineer

May 2015 - September 2015

Global Rail Construction LTD

United Kingdom

May 2015 - September 2015

At GRCL I am responsible for Tender Planning and Project Planning, scheduling, resource loading/management, progress updates and relevant reporting of various project for major Rail, Civils and DNO companies by using Primavera P6.
Creating estimates with quantity lists and prices.

Company industry:
Civil Engineering
Job role:
Other

Project Manager Assistant

September 2010 - April 2015

Deva Gold SA

Romania

September 2010 - April 2015

Planning Engineer
S.C. Deva Gold S.A., Dragos Voda St, No.9, 330034, Deva, Hunedoara County, Romania.
▪ Construction of a Gold Mine in Certej, Hunedoara County, Romania with the major shareholder Eldorado Gold (http://www.eldoradogold.com/assets/europe/projects/certej/) which involves: Modifying the existing pit, Erection of tailings facilities(Embankments), Utilities, Roads and the Process Plant.
▪ My principle role in this company is Planning Engineer. I use Primavera P6 or MS Project depending by the contractor. I use those programs to plan the works for each contract.
▪ I plan activities with relationship between them, roles, resources and cost.
▪ I maintain contact with each contractor to receive weekly reports of the status of their works to be able myself to update the Plan and create reports for my Project Manager.
▪ I supervise carefully each milestone or each critical activity and report to the Project Manager
▪ I am able to create any kind of reports: red line progress reports, earned value reports, cost and labour reports.
▪ I am able to re-plan a schedule witch has delays, level resources, create roles, supervise budgeted cost with actual costs.

Beside this, I have other roles depending of the tasks of each day:
▪ Maintain contact with the designer, verify drawings, list of quantities and costs.
▪ Prepare documentation for permitting.
▪ Prepare documentation for biding, compare offers, award contract.
▪ If needed, drawing or modify drawings in AutoCad / Tekla Structures.
▪ Prepare estimates for the construction works realised on our own.
▪ Setting out and Supervising teams of 5-15 people and equipment for different activities on site: Site clearance, Deforestations, Earth levelling, Foundations, Roads rehabilitation, Old buildings rehabilitation, Demolitions, Steel structures erection, Power supply (water, energy), Drainages.


Business or sector Civil and Industrial Construction Works.

Company industry:
Civil Engineering
Job role:
Management

Education

Construction Faculty from Timisoara

July 2012

July 2012

Master's degree, Construction Rehabilitation

Romania

GPA (percentage): 85%

GPA (percentage): 85%

Construction Faculty, Politechnic University from TImisoara

July 2010

July 2010

Bachelor's degree, Civil Engineering

Romania

GPA (percentage): 85%

GPA (percentage): 85%

Skills

Construction Design
Expert
Construction Design
Expert
Construction Monitoring
Expert
Construction Monitoring
Expert
Microsoft Excel
Intermediate
Microsoft Excel
Intermediate
Microsoft Project Management
Intermediate
Microsoft Project Management
Intermediate
Autocad
Expert
Autocad
Expert
Primavera P6
Expert
Primavera P6
Expert
Construction Design
Expert
Construction Design
Expert
Construction Monitoring
Expert
Construction Monitoring
Expert

Languages

English
Expert
French
Intermediate

Training and Certifications

Certifications
Catia V5
Nov 2014
Primavera Project Management User
Apr 2012
Tekla Structure User
Jul 2014

Hobbies