جيرارد Hayes, EPC contractor

جيرارد Hayes

EPC contractor

Sumitomo Corporation

البلد
استراليا
التعليم
الثانوية العامة أو ما يعادلها,
الخبرات
0 years, 0 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :0 years, 0 أشهر

EPC contractor في Sumitomo Corporation
  • فييتنام - Ho Chi Minh City
  • فبراير 2015 إلى يناير 2020

Duyen Hai 3 Extension (DH3E) 688 MW Thermal Power
Plant (Vietnam)
Description: DH3E is Sumitomo as EPC contractor comprising of
Black & Veatch (technical leader), Babcock & Wilcox,
Mitsui Engineering & Shipbuilding (Boiler), Toshiba
(Turbine & Generator

في ENERFLEX - Middle East & Australi
  • فبراير 2014 إلى يناير 2015

Oman Oil Company Exploration and Production LLC
(OOCEP), Abu Tubul Block 60 Gas Processing Plant,
Sultanate of Oman.
Description: The Abu Tubul (ABB) Gas Processing Plant (GPP)
(4x25MW) facility is to process gas, condensate & water
produced from wells at the ABB gas field located on
Block 60 in Sultanate of Oman
ENERFLEX Role: Construction and commission of entire plant including

في Parsons
  • المملكة العربية السعودية
  • يونيو 2013 إلى يناير 2014

Contract: Saudi Electrical Company Power Project, PP12, in
Dhuruma, Riyadh, Saudi Arabia.
Description: PP12 was a 2000MW Combined Cycle Power Project for
Saudi Electrical Company (SEC).
Parsons Brinckerhoff Role:
Parsons Brinckerhoff was the owners engineer (Saudi
Electrical Company) for construction and commission of
the entire plant.
My Responsibility: Senior Electrical Engineer for:
● Design Review.
● Providing technical interpretation of engineering
documents as appropriate.
● Reviewing required interface documentation between
design and construction, review engineering information
to ensure delivery in accordance with construction
schedule and cost control requirements.
● Participating in regular design reviews with Contractor
senior management and Client.
● Coordinating, controlling and reviewing engineering
documentation.
● Ensuring field compliance with approved engineering
drawings and specifications.
● Review Commissioning procedure
● Construction/Commissioning of SCADA/DATA Centre
for HV Substations, Water, Waste Water Treatment
plants, Sewage station & Oil stations

في CH2M HILL
  • استراليا
  • مايو 2011 إلى ديسمبر 2012
في CH2M HILL
  • استراليا
  • نوفمبر 2008 إلى أبريل 2011
في Fichtner Consulting Engineers
  • ألمانيا
  • يونيو 2007 إلى مايو 2008

Rembang (Indonesia) 600MW Thermal Power Plant
Description: Rembang Thermal Power Plant was a contract made up of
Fichtner Consulting Engineers (Germany) and Zelan
Contracting (Malaysia) for Indonesia Electricity Company

في Fichtner Consulting Engineers
  • ألمانيا
  • يوليو 2006 إلى مايو 2007

Tanjung Priok (Indonesia) 750MW
Gas Turbine Combined Cycle Power Plant (CCPP)
Description: Tanjung Priok was a consortium contract made up of

في Sumitomo Corporation
  • الإمارات العربية المتحدة
  • نوفمبر 2003 إلى ديسمبر 2005

Tanjung Jati B (Indonesia) 1320 MW (IPP)
Thermal Power Plant
Description: Tanjung Jati B is a consortium contract made up of
Sumitomo (Toshiba) Babcock & Wilcox / Black &
Veatch Int. and Mitsui.
Sumitomo Role: Construct & commission Turbine Island, Boiler Island
BOP areas including Water Treatment Systems, 500 &
150KV HV Switchyards & 500KV HV overhead lines
including Medium and Low Voltage systems,
DCS/PLC/Scada & Communication Systems

في Sumitomo Corporation
  • إيطاليا
  • مايو 2001 إلى سبتمبر 2003

Vietnam) 600MW Thermal Power Plant

في Black & Veatch
  • تايلاند
  • أبريل 1999 إلى ديسمبر 2000

TECO, Ratchaburi, Thailand IPP 700MW Project
Description: TECO Combined Cycle Plant was a contract between a
consortium called TECO and Black & Veatch (Thailand

في Black & Veatch International
  • الأردن
  • سبتمبر 1995 إلى مارس 1999

2 (Indonesia) - 200MW Steam
Cycle
2)Tambak Lorok Phase-II (Indonesia) - 500MW
Combined Cycle
Description: Tambak Lorok Block-2 Combined Cycle and Phase-II
Steam Cycle Plants were separate contracts between
Sumitomo Trading Corporation and Indonesia Electricity

في Electricity Supply Board International
  • أيرلندا
  • يناير 1995 إلى أغسطس 1995

Maura Karang (Indonesia) - 250MW Combined Cycle
Plant
Description : Maura Karang Combined Cycle Plant was a contract
between Sumitomo Trading Corporation and Indonesia
State Electricity Company (PLN) for the construction of
250MW "Add On" Combined Cycle Plant and 150 kV
Substation extension including 150kV overhead lines.
ESBI Role: Conceptual Design of Balance of Plant Electrical
Conceptual Design of 150 kV Substation
Supply of 150 kV Circuit Breakers, Current Transformers,
Voltage Transformers Protective Relaying Panels,
Substation Monitoring Equipment (Tariff Metering,
Sequence of Events Recorder, Oscillograph Recorder)
Responsibility : Electrical Lead Commissioning Engineer for:
150 KV Circuit Breakers / Disconnecting Switches
Current Transformers / Voltage Transformers, Mosaic
SCADA / DCIS Control, Monitoring Equipment
Generator Step-Up Transformer, Interface with MV
LV Contractor (BVI International) with respect to
Control / Interlocking / Protection of Unit Auxiliary
Transformer and MV / LV Switchgear.

في Black and Veatch International
  • نوفمبر 1994 إلى ديسمبر 1994

Maura Karang (Indonesia) - 250MW Combined Cycle
Plant
Description: Maura Karang Combined Cycle Plant was a contract
between Sumitomo Trading Corporation and Indonesia
State Electricity Company (PLN) for the construction of
250MW "Add On" Combined Cycle Plant and 150 kV
Substation extension.
Responsibility : Construction and Commissioning Engineer for:
Installation of Medium and Low Voltage Switchgear
(6.3kV and 380V) and Transformers
Commissioning of 6.3kV, 380V Switchgear and
Transformers as well as associated protection relays.
Energization & Operation of MV / LV Switchgear

في Electricity Supply Board International
  • أيرلندا
  • يناير 1993 إلى أكتوبر 1994

Tambak Lorok (Indonesia) 3 x 100MW Simple Cycle
Power Plant
General : Tambak Lorok (Indonesia) 3 x 100MW, Power Plant was
a turnkey Contract between Sumitomo Japan and PLN
(State Electricity Co.). For Construction of Power Plant
consisting of 3 x 100MW Frame 9E GTG's, 2 x 21000
HSD Tanks, H2 Plant, 150kV Sub-Station and all related
equipment. The plant was completed November 1993.
Sub-Contractors to Sumitomo included Hazama (Japan),
Toshiba (Japan), General electric (U.S.A.) and E.S.B.I
(Ireland).
ESBI Role: Conceptual Design of power plant
Supply of Unit Auxiliary Transformers, Current / Voltage
Transformers, Mosaic Control, Relaying Panels,
Monitoring Equipment ie. Oscillograph Recorders,
Sequence of Events Recorder, Tariff Metering for 150kV
Sub-Station
Responsibility: Construction and Commissioning Engineer for:
Construction / Commissioning of 150kV Circuit Breakers,
Disconnecting Switches, Mosaic Control, Monitoring
Equipment, Protection Relays, Generator Transformers,
Unit Aux. Transformers, Medium / Low Voltage
Switchgear, Standby Generator, Over Head Line
Diversion. Interfacing with 150kV Switchgear and Gas
Turbine Generators, with Existing 150kV Sub-Station.
Construction/Commissioning of SCADA in HV
Substations, Water, Waste Water Treatment plants,
Sewage station & Gas/Oil stations
Resident Engineer for Sumitomo during Warranty Period:
Inspection and Testing of all Major Electrical Equipment
during First Inspection at End of Warranty.

في State Electricity Co
  • البحرين
  • يناير 1978 إلى يناير 1992

Generation and Sub-Station Construction of various
Projects for Electricity Directorate Bahrain.
Contracts were for equipment ranging from 11kV to
220kV, including installation / commissioning of High
Voltage Cables ie. Oil Filled, Gas Filled, XLPE.
Substations were 33/11KV 66/11kV, 132/66kV,
220/66kV indoor/outdoor type gas insulated switchgear
(G.I.S.). Installation of Scada / DCS on New / Existing
Equipment.
Responsibility: Construction / Commissioning Engineer for:
Commissioning of Switchgear, Transformers
High Voltage Cables up to 220kV.
Commissioning of Scada / DCS Equipment on Existing
New Sub-stations including Remote Control Center.
Maintenance of Equipment during Warranty Period
including First Inspection.
Energizing of Sub-stations after initial Testing /
Commissioning Works. Warranty responsibilities.
Liaise with Consultants / Contractors in all aspects of
Construction/Commissioning.
SCADA - Installation/commissioning of SCADA in ALL
HV Substations, Power Plants, Water Treatment Plants,
Gas & Oil Stations.

Transmission Engineer في Electricity Supply Board International
  • أيرلندا
  • يناير 1970 إلى يناير 1978

General : ESBI is the State Electricity Co. of Ireland.
During my tenure with ESBI, I attended College from

Electrical Engineer
  • يناير 1970 إلى يناير 1974

Construction and Commissioning of New Sub-Stations.
Extensions to existing ones, including maintenance of
Voltage levels up to 220kV.Testing / Commissioning of
High Voltage Cables from 10kV - 220kV including fault
finding, repair and re-commissioning.

الخلفية التعليمية

الثانوية العامة أو ما يعادلها,
  • في Engineering College
  • فبراير 2021

,

Specialties & Skills

Construction Consulting
Electrical Testing
Warranty
CABLING
CONTRACT MANAGEMENT
ENGINEERING
INTERNET EXPLORER
MICROSOFT WORKS
OIL PAINTING
TOSHIBA
CUSTOMER RELATIONS