Planning Engineer
Alfaal United
Total years of experience :14 years, 10 Months
• Deciding on the most appropriate engineering techniques and sequences of activities for each project stage.
• Drawing plans; using specialized design software packages.
• Ensuring plans meet the client’s specifications.
• Making estimations for timescales and costs.
• Supervising the project at all stages and providing solutions to problems.
• Collaborating with site managers, surveyors, engineers, site worker and other professionals.
• Organizing the transportation of materials.
• Ensuring procedures are carried out safely.
• Generating S-Curves, Manpower Histogram, and other graphical reports
• Working on Variance analysis.
• Procurement
• Contract Management for sub-contractors.
• Correspondence for all project issues with client/Consultant
• Project Budget & Cost Control.
• Establishing an overall project schedule
• Evaluating and validating Contractors schedules including critical path & resource analysis
• Monitoring progress and preparing forecast
• Evaluating proposed change orders
• Scenario planning to evaluate risk & opportunity
• Evaluation and monitoring of procurement linkages, key deliverables & orders
• Weekly & monthly update of project schedule & reporting requirements
• Monitoring, tracking, and reporting progress performance against baseline schedule
• Forecasts completion dates and final performance
• Identifying schedule variances and trends and make recommendations for corrective action
Studying and assesses the target dates for the project and stays completely familiar with the work and the parameters of the work program
Ensuring that all programmed activities have man hour contents in line with Company Procedures
Reviewing the existing material and equipment schedules and obtains updated delivery information from the relevant departments
Assisting the Resident Site Manager and the Construction Superintendent in the preparation of the construction plan
Preparing the site plan consistent with the requirements and availability of the drawings, specifications, target dates and definitive estimate
Ensuring that all staff and subcontractors are made aware of the site plan and appreciates the part they will need to play in its implementation
Utilizing the progress data, updates the site plan and informs those concerned when progress is falling behind and maintains a constant check on materials and equipment delivery dates through the use of a bi-weekly look-a-head schedule
Attending progress meetings and reports on the current situation and notes all changes in the forward plans and any restrictions on progress
Recording the works additional to the original requirements and all variations and revisions which must be incorporated in the site plan and informs the appropriate staff and subcontractors of any changes to their workload and any alterations to the targets previously set
collating work progress for each contract and each area and includes them in the weekly and monthly Site Reports
Reviewing and agrees with Subcontractors on programs, to ensure compatibility with project requirements
Monitoring the site progress and prepares weekly ‘look ahead’ to maintain objectives and agreed milestones
Preparing man-hour criteria for all activities i.e. histogram
Marking-up drawings weekly to assess progress to man-hours