Project engineer
Wakham construction company
Total years of experience :44 years, 6 Months
1 - Construction, rehabilitation and maintenance of side walk . This include all construction stages ..
--- Excavation, laying interlock, curbstone and tiles, lighting posts& irrigation works, concreting & red sand layer and earth works & asphalt works .
2 - Supervision of the execute work including quality control .
3 - Preparing payment certificates for subcontractors .
4 - Preparing of the monthly documents of payments certificates . This included drawings, work done sheets and pictures .
5 - Performing security & safety for Drib road location . This include ...
-- The works of different barriers , traffic signals , lighting site, wear safety personal to workers, secure the entrance and exists of the equipment & machinery .
6 - Provide daily reports for Riyadh municipality and follow up of the project execution .
7 - Check up the lab ours, equipment, machinery& site activities move according to safety requirements .
8 - Task of technical and administrative site as directed by the project manger .
Project: KAUST & Thuwal flood control.
Location: King Abdullah University of Science & Technology (KAUST), Saudi Arabia.
Achievements:
1-Supervision of the construction of the structures (culverts No.1 & returning walls). This includes all construction stages excavations, reinforcement, water proofing and concreting.
2-Follow up of the executed work which done by the sub-contractors.
3-Check up the site activities move according to safety requirements.
4-Performing technical and administrative activities.
5-Submission of site reports and progress of the activities.
Achievements:
1-Execution of the construction of Algunid/abuharaz road (65 Km long). This includes all constructions stages, earth works, pavement, structures (one bridge & box and pipe culverts), road furniture and erosion works.
2-Execution of the re-habitation of Algaili/Shendi road, Asphalt road consisting of re-habitation 30 Km of the road. This includes Asphalt overlays, shoulders, and road furniture.
3-Preparing payment certificates.
4- Carrying out proposed design wherever it needs .
5- Preparing the documents of the projects for the subcontractors which consist of bill of quantity
, technical specifications, and drawings & tendering .
6 -Tenders analysis, contract forms and prices preparing .
7 - Planning , budget and follow up of the project execution .
8 - Evaluation of site reports and progress of the work .
.
: Position held: supervisor engineer:
(1) Supervision of the construction of Alrenk/Fuluge road, gravel road of 150km long consisting of earth works and structures (bridges and box and culverts)
(2) Inspection and approval of the executed work.
: Position held: Assistant projects directorate.
(1) Performing engineering design and preparing the documents of the
projects which consist of bill of quantity, technical, specifications, drawings and tendering.
(2) Tenders analysis and prices preparation.
(3) Quantity survey and payment certificates preparation.
(4) Preparing the contract documents for the projects and executions reports.
(5) Follow up of the projects execution & it's construction cost control.
(6) Prequalification data preparation.
(7) Office & site works connected with the above activities.
: Position held: Resident engineer .
1. Supervision of the construction of Adar/Malout road, gravel road of (105km) long consisting of embankment, sub base and corrugated steel pipe
2. Supervision of the construction of Moglad/ Higlig road, gravel road of (235 Km) which constructed by three different contractors.
3. Preparing and approval of final payment certificate.
4. preparation of as built documents: i. As built drawings
ii. Hydraulic reports
iii. Materials reports
5. Evaluation of chains
6. Witness of arbitration clearance committee.
: Position Held: Resident Engineer
Supervision of rehabilitation of Algasr Avenue, Asphalt road consisting of double carriage way, drains & parking.
: Position held: Senior pavement engineer
Project: Port Sudan development ( Stage 1) Achievements: 1. Carry detailed engineering for pavement of Berth 15 and container stocking area.
2. Performing technical studies concerning establishment of the sea Ports engineering unit.
: Position held: Resident engineer
1. Supervision of piling construction for the project of piling to raw water intake pumping station. This include all construction stages, drilling in the river bed, reinforcement, and cast in situ for concrete piles
2. Supervision of earth work. This includes excavation, embankment construction and sub base layer for extension, Arak factory.
Position held: Executive Engineer
Project: Construction of Jeddah Touristic Town, in Saudi Arabia
Achievements
1. Supervision & execution of earth work construction.
: Position Held: Resident Engineer
1. Supervision of Building construction. This includes all construction stages foundations, concreting & reinforcement, Plastering and Brick works.
Position held: consultancy services
Project: Rehabilitation of streets & drains in
Khartoum state
1. Contract: document preparations
2. Preparing of variation orders for
different activates
3. Check up the contractors payment
certificates.
1 - Supervision of routine and periodic maintenance for the following projects ...
* Wad - Madni - Gadaref road ( 227 km)
* Medani - Sennar - Kosti road ( 220 km )
* Khartoum Province roads ( 95 km)
* Khartoum - Wad - Medani road ( 187 km )
This include asphalt overlays & patching .
2 - The routine maintenance consists of earth work, shoulders, asphalts works, bridges, drains, ersion works, road marking & signals, kilometer posts and different types of treatment & improvement activities .
3 - Construction and execution of 35 km. of the national capital roads . This includes all construction stages earth work and pavements .
4 -Detailed engineering of the rehabilitation of internal roads, Sinnar town .
5 -Pavement and rehabilitation of internals roads , West sinnar sugar factory .
6 - Feasibility studies for the following ..
* Wad -Madani - Alhoush road
* Gebal Moya link road .
June 1978: Diploma in Civil Engineering : Khartoum polytechnic