Prepared Inspection testing plans, inspection requests logs, material submittal logs, method of statements for engineers’ inspection, execution of works and material in consultation. Preparation of all the project related reports required by the client to fulfill their needs and finalize the all documentation related to the project at the completion stage.
Key Accomplishments
Chairing and /or attending quality meetings, ensuring completion of quality-related minutes.
Monitored all the specific inspections on materials, equipment and construction/installation activities on site by QC Engineers.
Checked the conformity with the Quality Control Plan and obtain the relevant documentation.
Orderly collect, check and manage documents certifying tests, controls and inspections carried out witnessing the tests, controls and inspections carried out.
Ensure the correct implementation of the approved Inspection Test Plan according to Consultant and Client requirements.
Providing support to the site team and attending the third-party audits carried out by client organizations.
Formulated and delivered inspection request, technical data sheets, and method of statements for engineers’ inspection, execution of works, and material in consultation with Technical Engineer. Verified any technical changes required in variation orders prepared during the implementation of the projects by producing special report attached with the variation orders.
Key Accomplishments
Efficiently raised and completed RFI preparation, submission and follow up for civil works. Maintained all the required testing of materials record to attain quality of construction as per specifications and relevant SAIC & SATIP for all works under the contract performed on or off site.
Monitored all activities and materials of construction in accordance with the approved drawings and specs. Coordinated with the site engineers and Aramco inspectors for clearing designated any NCR and log book entries for inspection (Hold & Witness Points).
Conducted inspection for all materials received at site to ensure they conform Aramco requirements for Submission of Submittal and Material Data Sheets to Aramco for approval.
Successfully delivered for the quality and workmanship of each activity in all aspects of engineering construction relating to Civil, Architectural and Structural discipline interfacing the multidisciplinary processes. Prepared QA/QC documents of the complete project including certificates, calibration, test results, inspection requests, non-compliance reports and site instruction/observations, permanent materials delivered and other important QA/QC documents.
Key Accomplishments
Efficiently accomplished daily inspection and required testing of materials to attain quality of construction in the drawings and specifications for all works under the contract performed on or off site.
Actively liaised with site staff for closure of NCRs to produce NCR proposal, issue site observation, and deliver report to the QA/QC Manager, while examining activities related to the quality management system.
Reviewed the project in-depth to schedule deliverables and estimate costs; directed all onsite and offsite
constructions to supervise compliance with building and safety regulations. Performed preventive maintenance and
repairs on all equipment, directed daily operations of a building construction project, and estimated cost for bidding
on construction projects.
Key Accomplishments
* Delivered project management services and quality assurance for earthwork, concrete, infrastructure,
landscaping, andarchitectural/finishing concepts forbuildings andreview bar bending schedule for structural
steel in precast/ cast.
Actively liaised with Client and Contractor to identify technical project issues, such as evaluation of claims, variation orders, and extension of time and completion of works as per contract. Directed QA/QC plan or program and integrated materials on construction projects in compliance with plans and specifications. Competently examined all building works such as concrete, steel, wooden, aluminum, architectural and finishing works, and MEP Services external / infrastructure works. Interacted with stakeholders in multiple site meetings to discuss the overall project status, and resolve complex issues in a prompt manner.
Key Accomplishments
• Reviewed and altered operational practices, identified areas of quality failures, recommended various changes for qualitative improvement, and created control systems to avoid recurrence.
• Diligently revised multiple financial reports to manage overhead, control costs, enforce budget adherence, and assure the acceptable quality of materials, processes, and workmanship in the project work.
• Controlled and managed working of all engineering personnel, inspection of all materials, assisted resolution of all construction process and recommend improvement to all construction activities and ensured compliance to specifications and construction schedule and prepared all progress reports.
Skillfully analyzed all civil works of the project, issued of site instruction against quality standard violations at site, and generated monthly progress reports for submission to client on a timely manner. Delivered Site Instructions for non-compliance in accordance with issued construction drawings and technical specifications to the team members.
Key Accomplishments
• Steered efforts towards ensuring contractor compliance with codes, site materials, specifications, plans, commissioning of systems, shop drawings, actual as built drawings, alterations, repairs, improvements, change orders, and safety.
• Functioned in close collaboration with contractors and Resident Engineer to assess slow progress, quality control, extension of time cases, and issuance of completion certificates.
• Provided quality control, supervision and Contract administration for various building construction sites, general site work, utility relocation work, coordination and safety.
• Consistently exceeded customer satisfaction goals as project manager as well as targets for production, staff management, cost containment, and successful close-out.
• Played a significant role to ensure successful provision of engineering design and guided technical team to identify and resolve complex problems.
• Interacted daily with the clients to interpret their needs and requirements.
Performed overall quality control of the work (budget, schedule, plans, and personnel’s performance) and reported regularly on project status.
• Assigned responsibilities and mentor project team during all the construction time from handing over of sites to contractor until taking over by client on completion.
• Executed structural and finishing construction works according to drawings and Technical specifications and successfully delivered the project within the stipulated time and budget.
• Monitored and guided site supervisors at each and every step to carry out building works as per requirement of consultant by maintain quality standards.
• Prepared interim payment certificates as per work done on sites and coordinated with the consultant for verification by addressing all their concerns against completed works.
B.Sc in Civil Engineering