Project Engineer, Acting Construction Manager
Ma'aden
Total years of experience :18 years, 10 Months
A 300 MM US $ Project to provide the Housing accommodation for the Ma’aden and its affiliate. The complex accommodates Construction of 4 types of 794 pre-Cast Villas and infrastructure.
Worked on the project from the Engineering stage up to close out. Wide responsibilities which include but not limited to, Review of drawings, Tendering management, review of Material Submital, Work method statement, site supervision, technical issues.
A 600 MM US $ Project to provide services for Barod Mill, Steel Plant, Water Treatment Plant, Cooling Tower, Potable Water and other utility systems to support the complex.
One of the world’s biggest petrochemical complex, a cluster of petrochemical units budgeted 15 billion US $. It has utilized 17 licensed technologies and will produce both specialty amine derivatives and polycarbonates first time in Saudi Arabia. It was a pride and privilege to work as Lead Cost Engineer in U&O under the banner of Saudi Kayan.
U&O project a 3.275 B US $ / 100 MM Hour Project to provide PMT services for Port storage and loading/offloading facilities, sea water cooling, steam supply, crude oil boilers, water treatment, blow down facilities, interconnection to Aramco, Port and other Sabic complexes and other utility systems to support the complex.
A 1 B US $ 450-MW hydro power electric Project to Facilities the services for Power Plant, Dam of height 144 m & length 317 M, double Head race tunnel of length 939 meters, Road Bye-pass tunnel of length 650 meters, and other utility systems to support the complex.