marwan khairi, Civil Project Manager

marwan khairi

Civil Project Manager

V3 Middle East Engineering Consultants

Location
Saudi Arabia - Riyadh
Education
Bachelor's degree, Civil Engineering
Experience
20 years, 0 Months

Share My Profile

Block User


Work Experience

Total years of experience :20 years, 0 Months

Civil Project Manager at V3 Middle East Engineering Consultants
  • Saudi Arabia - Riyadh
  • April 2021 to March 2024

1- NUPCO Medical Warehouses design, used for logistic services to store medicine and its raw material in order to serve several cities in KSA.
2- Bujairi Infra and Public Realm project owned by DGCL implementing infra services (water, sewer, storm, power, irrigation & telecommunication). Also developing 4.5 km of Bujairi roads (paving, lighting landscape & furnishing).
3- MISHRAK Early Works Project within MISK City. A complex of residential and commercial buildings supervising earth works and excavation activity of 720, 000 m3.
4- Research Building and Laboratory project within KACST compound doing construction supervision till testing commissioning and handover procedures.
5- LULU Hyper Market & Cigar Lounge projects, Diplomatic quarter branch. Construction supervision of precast buildings, finishing works, MEP works and fitting works till operation.

Site Project Manager at TYPSA
  • Saudi Arabia - Riyadh
  • June 2015 to February 2020

Worked at TGNW location steel tank farm with capacity of 1 million m3 part of the mega project of 4 million m3 strategic reservoir of Riyadh city with a cost of 380, 000, 000 SAR doing the following:

- Supervise starting stage (mobilization, survey & excavation)
- Assuring that site activities are meeting with RFP and within cost, quality & time
- Providing technical advice to contractor
- Provide technical assistance to client representative
- Manufacturers visit and participate on materials inspecting
- Leading a supervision team consists of (2 civil inspectors, Surveyor, Safety Officer, Electrical and Mechanical inspectors and Welding inspector)
- Supervise subcontractors and their activities
- Reporting to vice project director
- Prepare and review variation orders when claimed and analyse them technically comparing it with the RFP and time wise
- Direct the follow up weekly meeting if the resident engineer is absent
- Review and approve contractors submittals (documents, drawings, plans, invoices…. etc.)
- Monitoring project processes and progress
- Preparing and managing daily, weekly & monthly reports to the client periodically and presentation material upon request
- Make sure that safety procedures are strictly followed
- Member on the committee of project closing stage (final handing over, testing & commissioning)

PMO Engineer at TYPSA
  • Saudi Arabia - Riyadh
  • December 2012 to May 2015

“SUPERVISION SERVICIES FOR THE FIRST STAGE PROJECTS FOR RIYADH WATER SUPPLY MASTER PLAN CONTRACTS” includes the projects 3A, 3B, 4, 11, 12, 15A, 15B, 16, 17A, 17B and SAAD LOT5. A total of 11 contracts including steel and concrete tanks, pumping stations and transmission lines with a total cost of 648, 000, 000$ doing the following:

- Quantity account and cost control for each contract separately
- Manage quantity survey and cost control for withdrawn projects and prepare the report
- Quality control over all contracts
- Prepare and review variation orders when claimed and analyse them technically and time wise
- Assure that company PMM is strictly implemented
- Review and comment on NWCs periodic update of the PMM
- Internal audit on the level of site supervision employers
- Participated in creating TYPSA recruiting standards and interview steps
- Guide the trainee students from Saudi universities on their summer practice
- Monitor document controlling system and archive program
- Review and submit monthly reports after resident engineer to the client periodically and presentation material upon request
- Preparing TYPSA invoices and VO required data
- Managing relationships and communications with the project’s stakeholders
- Member in NWC committee responsible to prepare and review RFP & contract terms for the contractors
- Review FIDIC contract terms and insure their application in case of conflict

Construction Manager at DALCO
  • Saudi Arabia - Jeddah
  • September 2011 to April 2012

1- Construction of mill feed factory with a cost of 6, 000, 000 SAR - Arabian Poultry Co.
(OMMAT)
2- Cables storage ware house with a cost of 1, 500, 000 SAR - Bahra Cables (Bin Ladin Groupe)

Doing the following:

- Guiding construction implementation Team
- Assure that work is within time and quality
- Handling cash flow and project procurement.
- Prepare and submit shop drawings
- Prepare daily and monthly report to consultant and client
- Prepare bar bending schedule
- Managing weekly progress monitoring meetings
- Prepare and follow company invoices

Technical Office Engineer at ALLIED
  • Saudi Arabia - Riyadh
  • November 2009 to September 2011

(NASCO) national security council project, subcontract with Saudi Oger at Al Yamama palace area with a cost of 30, 000, 000 SAR

Doing the following:

- Review and classify tender drawings
- Prepare shop drawings and supervise CAD draftsmen
- Submit and get approval of shop drawings
- Prepare bar bending schedule
- Help on site works implementation
- Preparing periodical reports to superior and main contractor
- Monitoring contract quantities
- Prepare and follow company invoices

Construction Manager at Al Baitar
  • Saudi Arabia - Riyadh
  • April 2005 to October 2009

- Turnkey of several branches for Bank Al Jazeera with a cost of 40, 000, 000 SAR
- Finishing works of SAUDI CERAMIC Co. head office with a cost of 10, 000, 000 SAR

Doing the following:

- Supervise starting stage (mobilization, survey, excavation and authority’s coordination
for permits)
- Prepare work plan and stick on it
- Prepare shop drawings and supervise CAD draftsmen
- Prepare bar bending schedule
- Managing weekly progress monitoring meetings
- Supervise subcontractors and suppliers
- Activities hand over to consultant
- Managing relationships and communications with the project’s stakeholders
- Make and follow up submittals to consultant
- Prepare and submit periodical reports to consultant
- Responsible of site petty cash and daily needs

Site Engineer at Al Sarif
  • Saudi Arabia - Riyadh
  • June 2001 to January 2004

Riyadh Tourism High Authority building - DQ. With a cost of 68, 000, 000 SAR

Doing the following:

- Supervise starting stage (mobilization, survey, excavation)
- Work on lean concrete and water proofing preparations
- Responsible about steel fixers team to cut and bend steel reinforcement then to prepare
later bar bending schedule to manufacturer
- Steel fixing and concrete for 9000 m3 raft foundation in stages
- Implementation of retaining walls using (DOKA) system all around the site
- Installation of scaffold for basement roof
- Steel reinforcement for basement roof and forming plant boxes in several levels
- Completely responsible about a building from scratch to finishing
- Landscape works for the outer garden
- Implementation of SECO building from scratch
- Deputy construction manager when he is absent
- Supervise and follow subcontractors on site
- Coordinate site needs with purchasing department
- Quality control and activity hand over to consultant
- Prepare daily report

Education

Bachelor's degree, Civil Engineering
  • at Near East University
  • July 2000

Specialties & Skills

Water Supply
Set Construction
Technical Support
Management
SOLIDWORKS (CAD)
TURNKEY (BUSINESS)
CONSTRUCTION
BIDDING
FOURGEN COMPUTER-AIDED SOFTWARE ENGINEERING (CASE) TOOLS
INSTALLATION
MICROSOFT OFFICE
REINFORCEMENT
RESEARCH
SKETCHUP (3D MODELING SOFTWARE)
QUALITY
SUPERVISORY SKILLS
MICROSOFT WORKS
CONSULTING
MANAGEMENT
TECHNICAL ANALYSIS
COUNCIL
BUDGETING

Languages

Arabic
Expert
English
Expert
Turkish
Intermediate

Memberships

Saudi Council of Engineers
  • Member
  • April 2012

Training and Certifications

First aid (Training)
Training Institute:
Saudi Heart Association
Duration:
20 hours
Health & Safety (Training)
Training Institute:
NASP
Duration:
35 hours