Process Manager
Wood
Total years of experience :36 years, 4 Months
Responsible for Managing and leading the process and Process control team (Licensed and Non-Licensed) to design of the NGL Fractionation Train for the Front End Engineering Design Package of the Jafurah Downstream Wasit-NGL Fractionation Facilities
Responsible for review/ approve and QC all the process deliverables.
Responsible for Optimization the selected suitable process for process configuration studies
Responsible for leading the process and Process control team (Licensed and Non-Licensed) to design of the NGL Fractionation Trains for the Front End Engineering Design Package of the Marjan Gas Processing Facilities
Responsible for check/review and QC all the process deliverables
Responsible for Optimization the selected suitable process for Process Configuration Studies
Process and U&O
Responsible for leading the process and process control team (Licensed and Non-Licensed) and U&O team to design of the NGL Fractionation Trains for the Basic Engineering Package of the Marjan Gas Processing Facilities.
Responsible for check/review and QC all the process and U&O deliverables.
Responsible for Optimization the selected suitable process for Process and U&O Configuration Studies.
Principal Process Engineer CEPSA Project (Q1 2017)
•Responsible for preparation of RVs Contingency calculation.
Responsible for assessment; re-rate, modify and replace existing equipment at Kinneil.
Responsible for the qualitative assessment of the H2S removal capability into the standby Hg filter.
Super QC Checker for P&IDs and Study reports and RVs
for Distillation Columns and RVs.
Managing all the process and engineering activities related to Carbon Capture Plant, Pipeline transport and storage in Shell Golden Eye North Sea, including all utilities and offsite.
Responsible for: Shell Athabasca Oil Sand Project Expansion II: Leading process engineering team and optimization the selected suitable process for U&O; Steam and Condensate System, Waste Water Treatment Plant, Raw Water Supply and Treatment Plant, Cooling Water System. Developing PFDs and Heat & Material balance, equipment sizing and data sheets, Preparation of technical Specifications and duty specs. Preparation of P&ID and related technical data. Review and quality control of technical document. Review of HAZOP meeting comments and actions; Material selection diagram.
Senior Project Lead Engineer Suncor Energy, Oil Sands Petro Canada Revamp Project, Millennium Naphtha Unit Plant 64 (
Responsible for: Leading process design team to develop PFD, H&M, P&ID, calculation/data sheet, PID, calculation and sizing of Pressure Safety Relief valves and Thermal Relief Valves. etc. for Shell Athabasca Oil Sand Project for Atmospheric &Vacuum distillation and Tank Farm.
HAZOP Study/Review and respond the HAZOP actions.
JTFJ (Joint Task Force Japan), South West Iran, Azadegan Oil Field Development Project, (Conceptual Design and Front-End Engineering
Technical and Commercial proposal and Estimating,
Manager-Process and HSE Engineering Department