Deal and lead a team handling various huge mining, oil & gas projects in all aspects of planning, scheduling and reporting
Leading a team of professional engineers who collaborated to establish a consulting firm that utilizes experience, expert knowledge, and technology to provide effective project management, scheduling solutions for projects throughout USA.
Leading a team In charge of all the planning, scheduling, reporting, management and monitoring duties for more than 100 projects in all design, interior design and construction projects all over Qatar.
Planning/Scheduling Engineer for 2 LNG Process Trains in support of all disciplines (Civil, UG works, structural steel, AG piping, equipment erection, electrical, instrumentation, pre-commissioning & commissioning)
Project YEMEN LNG PROJECT - LNG PLANT
Construction of 2 LNG Process Trains, Utilities and Offsites, LNG Jetty & 2 LNG Tanks.
GOLDEN MILE PROJECT of initial value exceeding a billion and forty million AED
Construction of 780 luxury apartments in 10 waterside buildings and 220 upscale shops and restaurants @ Jumeirah Palm.
EBIC AMMONIA PLANT of initial value exceeding a 505 million USD
Construction of anhydrous ammonia plant (production of 2, 000 metric tons per day) in addition to a pipeline corridor connecting the ammonia production plant to product storage tanks located in Port.
GUPCO REHABILITATION PROJECT
Rehabilitation of GUPCO existing facilities/platforms in Gulf of Suez & Egyptian Western Desert.
JCP - Jubail Chevron Philips Petrochemical
Construction of styrene Petrochemical that includes (feed fractionation / Olefins cracker / ethyl benzene & styrene monomer process units) in addition to the associated utilities and infrastructure.
DAMIETTA LNG CONSTRUCTION (5 million tons capacity) of investment around US$1.3 billion.
Construction of LNG liquefaction train, inlet gas reception area, natural gas liquids removal and fractionation area, a docking jetty for tanker loading and transportation, LNG refrigerated storage and export facilities (tanks and booms), utilities and supporting infrastructure, gas metering and treatment facilities, refrigerant condensate and LNG storage (two 150, 000 m³ PC LNG storage tanks)
GOLDEN PYRAMIDS PLAZZA PROJECT of value exceeding 322 Million USD
Construction of retail & leisure complex, 8 towers (offices /residential), single five plus star hotel, four star hotel (2 buildings), Medical centre, parking and commercial centre.
•Management for trucks workshop.
•Inspection for all electromechanical services for heavy, light trucks and power generator sets.