Site Project Control Manager
Heavy Engineering Industries & Shipbuilding Company (HEISCO)
Total years of experience :19 years, 1 Months
Project (I): General Construction Works for the CIVIL, STRUCTURAL, MECHANICAL, PIPING, TANKS AND E&I WORKS of the EPC&C of Jurasic Production Facilities (JPF) 4 at Kuwait Oil Company (KOC) North Kuwait-for SPETCO International Petroleum Company W.L.L. at State of Kuwait. From Jun 2022 till Now.
Project (II): Execution, Completion and Maintenance of the Access Link Road to Mubarak Al Kabeer Port (MKP) in Boubyan Island at State of Kuwait. From Oct 2020 till Now.
Project (III): Cleaning and disinfection of docks and berths at Shuaiba port at State of Kuwait. From April 2021 till Now.
Project (IV): NEW GATHERING CENTER GC-32, (EARLY CIVIL WORKS AND SUPPLY AND CONSTRUCTION OF BUILDING AND SHELTERS) for Kuwait Oil Company KOC and, for Petrofac International Limited at State of Kuwait. From Jan 2021 till Now.
Duties:
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Controls Manager / Project Director/ to initiate proper corrective actions.
- Creating / Establish Project Time Schedules as well as all reports (Internal & Client /Engineer).
- Preparing / Establish Acceleration/Recovery plan for the disciplines/Project when required.
- Preparing the Delay Analysis Log as per Retrospective single base additive modeling (Impacted Baseline Critical Path) (IB-CPM).
- Supporting in preparation of the Extension of Time (EOT) Claims.
- Preparing/Presenting to Top Management Project Presentation for the subjects required and steering meetings presentation.
- Developed an effective internal reporting system along with administering internal Bi-weekly meetings which resulted in decreasing schedule delays to less than 5%.
- Checked for accuracy and consistency in progress updates, critical path and near critical activity analysis, forecasts, recovery/revised plans, client and internal progress reporting.
- Contributed and highlighted to the management any foreseeable delays or risks.
- Participated in construction progress meetings across the projects to check the updated schedules and suggest corrective actions.
- Support the cost control team during the preparation of the project’s budget.
- Analyzed the change orders and evaluated their time and cost impact.
Project (I): General Construction Works for the Compressors, Utilities and Interconnection Sub-Areas of the EPC&C of Gas Train 5 Project at MAA Refinery for Kuwait National Petroleum Company (KNPC), for Tecnicas Reunidas S.A. (TR) at State of Kuwait.
Duties:
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Control Manager / Project Manager/ to initiate proper corrective actions.
- Creating / Establish Project Time Schedules (Internal & Client /Engineer).
- Preparing Weekly/Monthly progress reports (Internal & Client /Engineer).
- Preparing / Establish Acceleration/Recovery plan for the disciplines/Project when required.
- Preparing the Delay Analysis Log as per Retrospective single base additive modeling (Impacted Baseline Critical Path) (IB-CPM).
- Supporting in preparation of the Extension of Time (EOT) Claims.
- Preparing/Presenting to Top Management Project Presentation for the subjects required.
Project (1): Supply & Construction of Storage Tanks & Construction of Civil works related to New Gathering Center, GC29 in North Kuwait for Kuwait Oil Company KOC and, for Petrofac International Limited at State of Kuwait.
Project (2): Supply & Construction of Storage Tanks & Construction of Civil works related to New Gathering Center, GC30 in North Kuwait for Kuwait Oil Company KOC and, for Larsen & Toubro (L&T) at State of Kuwait.
Duties:
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Master work progress schedule updates.
- BOQ weekly reports (Planned-Actual).
- Man-hours progress report (Planned-Actual-Earned).
- Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer/Owner.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Control Manager / Project Manager/ to initiate proper corrective actions.
- Creating / Establish Project Time Schedules (Internal & Client /Engineer).
- Preparing Weekly/Monthly progress reports (Internal & Client /Engineer).
Project: Supply, Erection, Operation and Maintenance of Gas Turbines to Upgrade Power Capacity at Sabiya Power and Distillation Plant Site.
“Sabiya OCGT Power Plant - EPC Project and O&M in Kuwait - Main Contractor”
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Master work progress schedule updates.
- BOQ weekly reports (Planned-Actual).
- Man-hours progress report (Planned-Actual-Earned).
- Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer/Owner.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Manager/Director to initiate proper corrective actions.
- Creating / Establish project Schedule (Level 1, Level 2 and Level 3) and approved from the client.
- Preparing Weekly/Monthly progress to Owner/Engineer.
- Preparing Weekly/Monthly Minutes of Meetings
Project: Design& Build and O & M for the Conversion of the Second Stage Az-Zour South Gas Turbines to Combined Cycle Plant.
“Az-Zour CCGT-2 Power Plant 2X275 MW- EPC Project and O&M in Kuwait - Main Contractor”
Duties:
-Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
-Estimating the type and quantities of resources required to perform each schedule Activity.
-Master work progress schedule updates.
-BOQ weekly reports (Planned-Actual).
-Man-hours progress report (Planned-Actual-Earned).
-Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer.
-Establish all disciplines progress curves (S-Curves) Weekly/Monthly
Senior Planning Engineer for Power Plant Project
TERGA Power Plant combined cycle 3X400 MW in Algeria - EPC Project -Main Contractor .
Duties:
Identifying the specific schedule activities that need to be performed to produce the various project deliverables.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Estimating the number of work periods that will be needed to complete individual schedule activities.
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Master work progress schedule updates.
- Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer.
- Three weeks look-ahead programs.
- Controlling changes to the project schedule.
- Preparation of the Subcontractors sub-schedules and monitoring the progress of each and reflecting their output in the Master progress Schedule.
- Assist in preparation of the consortium Monthly Progress Report to Management.
- Man-hours progress report (Planned-Actual-Earned).
- BOQ weekly reports (Planned-Actual).
- Assist in the Preparation of the Extension of Time Claims documents and schedule impacts.
- Coordination with the Contract Administration to highlight the areas of potential time impacts.
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Control Manager to initiate proper corrective actions.
- Present to top management project presentation in each monthly meeting.
- Teach talent program engineers in planning phase.(teach 5 Eng. “ 1 civil+3 Mechanical+1 Electrical”)
"El-Kureimat II power Station (750 MW Combined Cycle)"
CONSULTANT : Power Generation Engineering and Service Company "PGESCo" BECHTEL & Ministry of Electricity and Energy& CIB
Duties:
-Planning & Time Schedule.
-Contract Administration.
-Change Notices & Claims
-Contractual Correspondence to and from all Parties.
-Monitoring all Contractual aspect under the main Contract.
-Remeasurement of the Works & Monthly Client Invoice.
-Project Monthly progress Report
-Time Impact, Cost Impact
TANTA UNIV.HOSPITAL"BUDGET :150 M.L.E For "ARAB CONTRACTORS "Osman Ahmed Osman &Co
Duties:
-Planning & Time Schedule
-Tender Planning
-Contract Management
-Project Time Management
-Project Cost Management
-Project Procurement Management
-Project Communication Management
-Monthly Progress Reporting
-Claims management
Final Year Grade: V.GOOD. Overall Grade: GOOD (72.30%) 10th on the Class Cumulative. PROJECT: Construction Project Management. GRADE: EXCELLENT (96.5%).1st on the Class