TeamLeader Q.A\ Q.C civil Engineer
Orascom Construction Limited - Other Locations
Total years of experience :14 years, 4 Months
‐ Following up over than 20, 000 CMC Pile and HDD work for pipes under main Roads
Soil Improvement under pipe lines: Following up and inspection for soil layer under pipe lines and
follow up lab test for soil
‐
- Preparing checklists and ensure the execution team is following them
- Raising inspection requests to the consultant and following its approval
‐ Coordinate, monitor, review the sub-contractors, suppliers, samples, shop-drawings, technical data
and make recommendation where required
Working as Senior Q.C civil Engineer in PORT SAID TUNNELS UNDER SUEZ CANAL:
‐ Following up and inspection for Diaphragm wall for all zone in west side (safe haven for TBM,
transition zone, soil substitution block, reception shaft zone, cut &cover zone)
‐ following up and inspection civil work of Reception shaft, cut &cover ( U‐ section & Box‐ section )
and Emergency Shaft, Ancillary building ( Fire pumping room, water tank, impounding sump, H‐VAC
Building ), constructing of ( Road deck slab, Emergency Stairs Egress and safety Berries) in Tunnel
work
- Preparing checklists and ensure the execution team is following them
- Raising inspection requests to the consultant and following its approval
‐ Coordinate, monitor, review the sub-contractors, suppliers, samples, shop-drawings, technical data
and make recommendation where required
‐ Raising inspection requests to the consultant and following its approval
Following up and inspection for pile work (board pile, Driven Pile),
‐ following up and inspection civil work of STEAM TURBINE BUILDING, GAS TURBINE BUILDING, GAS
TURBINE TURBOSET, STRUCTURE FOR BYPASS STACK, STRUCTURE FOR HEAT RECOVERY STEAM
GENERATOR and STRUCTURE FOR H.V. GENERATOR TRANSFORMER.
‐Preparing all required reports, raise NCRs and their solutions
‐Preparing checklists and ensure the execution team is following them.
‐Coordinate between all mechanical, electrical, plumbing, etc. with civil activities.
‐Ensure the quality system and project procedure is implemented on site.
‐Checking, measuring and testing to ensure that the activities are carried out in accordance with
relevant standards and specifications.
‐Coordinate, monitor, review the sub-contractors, suppliers, samples, shop-drawings, technical data
and make recommendation where required.
‐Raising inspection requests to the consultant and following its approval
worked as a construction engineer in 15 towers for youth housing
Project. Towers are based on 117 board pile (dim.60, length 30 m) and responsible
for pursuance all drawing with a good quality and with available equipment in site
worked as a construction engineer of civil department in
Finishing work of Administrative building and some element of mechanical foundation
worked as a construction engineer in all foundation of steel
structure foundation and observed all steel combinations and foundation of
Rolling machines.
_________________________________________________
2011-2012
Working as civil Q.C Engineer at Kharafi National (West Damietta Power Plant Project. Simple Cycle Gas Turbine Units 500 MW) fast track project.
2011 LoLoaa office for contracting and general imports
2010-2011
Working as civil Q.C Engineer at Archirodon Construction (Overseas) co.S.A
(Damietta Power Plant Project. Simple Cycle Gas Turbine Units 500 MW),
(Fast track project)
2010 EL-Agouz office for contracting.
Summer 2009 Training in El_Zohary company as a site construction for 112 towers.
Summer 2008 Training in Ftaih company, Constructing opera (piles, Anchors, Sheet pile, Beams, Columns, slab (flat slab, solid slab, rib slab, hollow block) etc
Summer 2007 Training in El_Nasr company as a site construction.