Provide engineering support (operate phase) to all Sarawak and Sabah asset to ensure plant reliability, safe to operate
and cost effective.
• Engineering support include below elements:
i. Provide annual review of all facilities, in terms of productivity, reliability, system uptime/downtime, HSE and cost
effective.
ii. Perform engineering study, execution plan, procurement, testing and commissioning of assigned Plant Change
Proposal as part of the MoC (Management of Change) process. Key PCPs are as below:
F23, CPDRA (WHP) and F6, F28 (WHP) PCD Network Segregation Upgrade
F23 H2S Blending Algorithm Logic Change- to ensure CPDRA (WHP) able to produce at higher capacity in
event of trunkline pressure low.
E11 PMC and TPC Water Level Control
F6 Swicth Rack Change out
M1 CI Panel including PLC Changeout
CEM Verification Exercise for Sarawak Assets- for OI (Operational Integrity requirement)
F23 IPS/FGS Changeout Project
F6 IPS/FGS Changeout Project
F23 Water Injection pump test project.
F23 K2500 Dry Gas Seal modification project.
iii. Perform annual review of Instrument and Control maintenance plan to ensure plant is maintained in accordance to
Shell RMP (Recommended Maintenance Practice) this include frequency of SCE final element (i.e. ESD valves,
BDVs, SDVs) response time.
iv. Perform updating of Tier 1 instrument and control documents, and drawing to meet Shell OI (Operating Integrity)
requirements, example of Instrument Tier 1 drawings are, CEM (Cause and Effect Matrix), Functional Logic
Diagram, Safeguarding Philosophy Control Philosophy, and Instrument Layout.
v. Lead and execute FGS and IPS logic test at vendor premise in order to update the CEM (i.e. F23, F6, and E11)
vi. Direct involvement in HAZID and HAZOP review. Example, E11 HAZOP review year 2015
vii. Direct involvement in the incident investigation, example E11 liquid carryover incident year 2015.
viii. Lead and execute plant change management process shall found that there is requirement to perform system
change, logic change or hardware change in order to operate safely and cost effective. Process include study,
engineering design, procurement and execution onsite.
ix. Lead and execute special projects because of plant change process i.e. F23 IPS/FGS upgrade, F23 IPS/FGS
upgrade, F6 PCD Upgrade, and F23 PCD Upgrade. Execution are from design stage, procurement of materials,
FAT, commissioning and SAT.
x. Perform final acceptance audit to the new platform which handed over operations (i.e. Laila Platform FAA on
2015)
xi. Perform HBA (Hardware Barrier Assessment) for the assets, A Hardware Barrier Assessment provides assurance of
the integrity status of SCEs for facilities, pipelines and/or wells through the review of all relevant records and documentation and by the physical inspection of the equipment in the field. The purpose of an HBA is to ensure the effectiveness of the Asset Integrity and Maintenance Execution processes and to be able to demonstrate integrity on SCEs to key stakeholders. This is accomplished through physically verifying the Technical Integrity of Safety Critical Element equipment.
xii. Perform coaching the frontline operations in order to operate and maintain the DCS, IPS, FGS, PCD and instruments accordingly.
xiii. Act as CSE (Control System Engineer) for the Sarawak waters, monitoring reliability for control systems (i.e. DCS, IPS and FGS).
xiv. Assist project team in terms of operations and maintenance i.e. HAZOP review for E11RB -Kasawari tie in project.
xv. Assist GK (Gumusut Kakap) project team during PCD segregation project. The scope include FAT support and testing support.
xvi. Perform IPF SIL Review for the Sarawak and Sabah facilities, namely M1, M3, F23, F6, E11, SJ and Barton.
• Supporting TMM (Topside Major Maintenance) team during shutdown/SIMOPS campaign including involvement in AAR (After Activity Review).
RECOGNITION:
• Safe and early startup up for F6/F28 shutdown and SIMOPS activity