QA/QC Instrumentation Inspector / Engineer
Tunisian Saudi for Projects Company Ltd. (EPPM)
Total years of experience :11 years, 11 Months
Saudi Aramco.
Arabian Heavy Delivery for East West Pipeline Project (In-Plant).
Review the project scope of work, IFC drawings, quality management system, quality control procedures, and
project specifications as well as the ITPs and method of statements.
Review design documents and be fully familiar with all scope of work.
Develop and execute QA/QC work packages and procedures.
Review existing and new project documents for compliance.
Review procurement documents related to electrical and instrumentation materials.
Progressive compilation of project data records (manufacturer’s data records).
Saudi Aramco.
Fadhili Gas Program Project, Package 1&2.
Liaise with client representatives about standard codes and specifications and project requirements.
Participate in the project kick‐off meetings and conduct quality toolbox talks.
Carry out material receiving inspection.
Ensure all manufacturer’s data record sign‐offs are carried out by all relevant parties progressively and promptly.
Monitor the company’s effort to verify that electrical and instrument material and equipment supplied meet the
project specifications.
Ensure correct inventory and proper inspection records are maintained.
Saudi Aramco.
Jazan Refinery Utilities Project, Package EPC-13.
Perform inspections in the calibration shop and field.
Review of all certification and documentation to ensure validity and compliance with specifications, drawings,
manufacturing, and inspection test plans.
Provide expertise to the site team to avoid/resolve quality problems.
Perform inspection and verifications during fabrication activities by requirements of the inspection and test plans
and project specifications.
Provide early warnings of potential quality problems.
Work closely with construction personnel and advise them of quality requirements.
Saudi Aramco.
Master Gas System Phase-I 56” EWG-2 Loop-2 and 56” KAEC Pipeline Project.
Communicate effectively with clients, contractors, and any third party.
Perform duties that may be required to enhance the work.
Strive to make continual improvements in the inspection process.
Ensure that proper quality control techniques and procedures are established by the construction.
Coordinate closely with craft, supervisors, and site engineers to minimize work interference due to engineering.
Participate in the resolution of quality problems as directed.
Inspect and witness IR test and continuity check for all cable drums.
Saudi Aramco.
Al Muajjiz Terminal Rehabilitation Project (YST).
Monitor excavation jobs on the field site for laying cables, backfilling cable trench, installation of lights, glanding,
and termination of cables, etc. as per project requirements.
Monitor installation of equipment on the building site for cable tray installation, laying cables, glanding, and
termination of cables in the panel as per the client’s requirements.
Perform visual inspection and dimensional checks on all electrical‐related works such as cable tray installations,
cable pulling, wiring, conduit, junction box installations, switchgear, transformers, switch cabinets, power control
centers, motor control centers, and local control board panel installation.
Ensure that quality control is carried out during the installation phase. This shall include but not be limited to the
following items: (Wires, cables and cable glands, cable trays, batteries and chargers, navigation aids,
communication system, fire and gas panels, equipment and facilities tagging, tubing and fittings, supports and
brackets, instrument calibrations)
Petro Rabigh (Saudi Aramco & Sumitomo Japan JV).
Petro Rabigh-II Refining & Petrochemical Project (CP3&CP4)
Inspect for witness calibration, installation, loop checking & functional tests of pressure, flow, temperature, and
level instruments, Analyzers, control/On‐Off valves, Motor operated valves, Gas Operated Valves, and Fire & Gas
Instruments.
Inspect and witness IR and continuity tests for all installed cables.
Inspection of cable pulling, dressing, glanding, and termination activities and documentation.
Monitoring of hazardous area installation and inspection activities.
Installation inspection of impulse tube, and airline pneumatic air header as per hook‐up and IFC drawings.
Inspection of the field junction box, distribution box, instrumentation panel installation, and associated
documentation.
Aryan Coal Beneficiations India Limited.
600 MW Coal-Based Thermal Power Plant, Chhattisgarh
Inspect and witness all electrical installation and testing inside the 69KV substation such as 13.8KV metal clad
switchgear, 480V motor control center, battery chargers, panel boards, fire alarm and production systems,
earthing, grounding, power/control cables, normal lighting, etc.
Inspect and witness all electrical materials and equipment before installation and ensure that the material and
execution of work are by design, drawing equipment specification, and standards as per the client’s requirement.
Inspect and witness the installation of 1.5MVA, 13.8KV/480V transformer protection and fire alarm system,
communication system, and power panel boards and review the illumination design and installation of its lighting
system.
Inspection of lighting fixtures, sockets, and aviation lights.
SADARA (Saudi Aramco & Dow Chemical Company JV)
SADARA Polyethylene Train-4 Project, Saudi Arabia
YASREF (Yanbu Aramco Sinopec Refining Company Ltd.)
ECP-1 Delayed Coker Package, Saudi Arabia
Inspect and witness illumination test and motor solo run test.
Inspect and witness instrument tubing leak test/pressure test.
Checks and verifies proper tagging of electrical equipment before installation, repairs, reconditioning,
troubleshooting, testing, and maintenance work orders implementation.
Monitor construction process and perform quality surveillance as per ITP
Review and approve electrical energization packages before pre‐commissioning.
Nuclear Power Corporation of India Limited
Kudankulam Nuclear Power Project, Unit-II
Review and approve Instrumentation Loop check packages before pre‐commissioning.
Conducting a final inspection of electrical and instrumentation installation before system handover punch lists.
Reviewing and verification of As‐built construction drawings.
Carry out a variety of construction/pre‐commissioning and commissioning‐related works.
Liaise with engineering for the resolution of construction requests for clarification, site queries, and non‐
conformances.
Refer drawing to the designing team in case of major variation and seek approval of the client for the same
through QA/QC section.
Report any major quality issues to the quality manager of the project management team.
Saudi Arabian Mining Company, (Ma’aden) & ALCOA JV.
Ras Al-Khair Aluminum Smelter Project, Saudi Arabia
Review the project scope of work, IFC drawings, quality management system, quality control procedures, and
project specifications as well as the ITPs and method of statements.
Review design documents and be fully familiar with all scope of work.
Develop and execute QA/QC work packages and procedures.
Review existing and new project documents for compliance.
Review procurement documents related to electrical and instrumentation materials.
Progressive compilation of project data records (manufacturer’s data records).
Liaise with client representatives about standard codes and specifications and project requirements.
Participate in the project kick‐off meetings and conduct quality toolbox talks.
Carry out material receiving inspection.
Tamilnadu Electricity Board
Valuthur Gas Turbine Power Station, Phase-I
Tamilnadu Electricity Board
Valuthur Gas Turbine Power Station, Phase-II
Planning and execution of Installation of Electrical Equipment’s Instruments and Fire and Gas systems as per
drawing.
Collecting and issuing the input drawings to Sub Contractor & Vendors.
Technical discussions with Clients, Consultants & Vendors.
Manpower planning and organizing well in advance for avoiding surprises and early completion.
Coordination with HQ for timely availability of materials at the site.
Drawing coordination from Engineering Department.
Transformer erection & oil filtration.
Knowledge of Transformer protection, Transformer Differential Protection & REF Protection, and synchronizing
schemes.
Testing of Protection schematic involving Power Transformers.
Conducting a final inspection of electrical and instrumentation installation before system handover punch lists.
Reviewing and verification of As‐built construction drawings.
Carry out a variety of construction/pre‐commissioning and commissioning‐related works.
Liaise with engineering for the resolution of construction requests for clarification, site queries, and non‐
conformances.
Refer drawing to the designing team in case of major variation and seek approval of the client for the same
through QA/QC section.
Report any major quality issues to the quality manager of the project management team.
Active Member in Renewable Energy Club