ACTIVITIES

I have managed mechanical, electrical & plumbing (MEP) retrofit works at Governor House Peshawar kpk. I was also responsible for business promotion, receivables, electrical works, services and general administration in regional office Peshawar

Project Manager at Agency AL- Jazirah Engineers & Consultants
  • November 2008 to June 2010

Location of Assignment Riyadh - Saudi Arabia

Electrical Engineer
  • March 2006 to November 2008

Location of Assignment Islamabad - Peshawar, Pakistan

Electrical Engineer at Saudi Consulting Services
  • Egypt
  • September 2003 to April 2005

Location of Assignment Saudi Arabia / Attock, Pakistan

Electrical Engineer
  • November 2002 to February 2003

Location of Assignment Kohat - Pakistan

Project Engineer
  • January 1992 to January 1996

Location of Assignment Lahore - Pakistan

Senior Engineer
  • January 1988 to January 1992

Location of Assignment Tarbela - Pakistan

Project Engineer/Senior Engineer
  • January 1983 to January 1988

Location of Assignment Faisalabad/Lahore - Pakistan

Electrical Engineer
  • January 1978 to January 1980

Construction of 380 kV Yanbu - Madina and 110 kV Badr Al-Musaijeed OHTL for Madina Electric Company Cost US $ 25 million, supervising, unloading & stacking of tower steel at main storage yard by crane, fork-lift & crane mounted truck, coordinated with base camp & field camps, updating office records, conducting Inquiries, accident investigations & report writing.

Supervised erection of towers using crane for 500 kV OHTL Faisalabad Ghazi Ghat section, attended progress meetings with consultant Nespak/Harza International USA & client Wapda, cost of project was U.S $ 5 million.

XII. Name of Employing Agency Engineers International Ltd Pakistan

Peshawar
  • January 1976 to January 1977

Construction of tower foundation, erection, stringing & inspection of 220kV Mangla Burhan transmissions line cost U.S. $ 10 million & installation of telecommunication equipment in substations.

XIII. Name of Employing Agency Water & Power Development Authority

Trainee Engineer
  • May 2018 to

Location of Assignment Warsak - Pakistan
Period of Assignment 1974

I was assigned on major overhauling of unit 3 & 4 of warsak hydro power station by wapda

Education

Bachelor's degree, Electrical Engineering
  • at University of Engineering
  • January 1975

STUDY OF TARBELA HYDRO POWER SCHEME PAKISTAN. CAPTAIN OF THE CRICKET TEAMS OF PESHAWAR UNIVERSITY & ENGINEER COLLEGE. CRICKET COLOR HOLDER OF ENGINEERING COLLEGE. CRICKET COLOR HOLDER OF PESHAWAR UNIVERSITY.

Specialties & Skills

Inspection
Installation
Hydropower
ASSETS RECOVERY
CABLING
CUSTOMER RELATIONS
MICROSOFT OFFICE
PROGRESS
PROPOSAL WRITING
SUPERVISORY SKILLS
ADMINISTRATION
GOVERNMENT

Training and Certifications

Got training/ internship in Warsak hydel Power Station Peshawar Pakistan. (Training)
Training Institute:
water & power development authority Pakisatn
Date Attended:
June 1976
Duration:
488 hours

Hobbies

  • Cricket
    Received best batting prize & declared best cricketer of the year 1965 in cantonment public school Peshawar Pakistan. Captained cricket teams of Engineering College & University of Peshawar Pakisatn Cricket Color holder of Engg. and University of Peshawar Pakistan.