Work Experience

Total years of experience :20 years, 2 Months

Project Engineer at Saudi Electricity Company (SEC)
  • Saudi Arabia - Jeddah
  • My current job since December 2012

Projects:-
1.-STATIC VAR COMPENSATION(SVC) :-for Harmain High Speed Railway 380kV GIS for both the substations at Makkah & Madinah (HHR-1 & 6)
2.-JEDDAH SOUTH THERMAL POWER PLANT -380KV GIS SUBSTATION
3. -380/110/33kV GIS for SHUQAIQ POWER PLANT Substation

Key Result Areas:
• Installation, monitoring including all testing activities while construction of 380kV GIS Substations and TSC, TCR, Capacitors, Inductors & power Transformer for 380kV GIS & SVC Transformer as per SEC standards and practice in west and south area.
• Base Design, Detail Design, Installation, testing & commissioning of 380kV, 110kV, 33kV GIS Switchgears of 380kV Substation & SVC as well.
• Generating and maintaining monthly, weekly & daily progress status in respect of installation, Testing & commissioning of construction of 380kV GIS substation & SVC System as mentioned above.
• Gathering technical requirements and proposals of the major equipment/systems submittal by contractors as per SOW, SEC standards and practice in Central area for 132KV GIS System review & approval GIS
• Adhering the compliance statements to SEC standards and practice submitted by contractors for GIS design
• Attending progress review meeting with contractors for Construction of GIS Substation
• Implementing Environmental, Health & Safety (EHS) Best Practices & ensuring world class safety standard at site
• Ensuring Quality Management System (QMS) at customer’s site in line with organization’s corporate policies

Electrical Engineer at Saudi Electricity Company (SEC)
  • Saudi Arabia - Riyadh
  • October 2011 to November 2012

Review Overall Single Line Diagram, Equipment Layout drawing including Plan and Sections as per SEC standards and practice.
Review all technical requirements and proposals of the following major equipment/systems submittal by contractors as per SOW, SEC standards and practice.
a. 132 kV GIS Switchgear of AREVA/ABB/HEUNDAI Make
b. 132 kV GIB with SF6/Air Bushing.
c. Power Transformer 100/60 MVA - 2 Nos. 132/33/13.8 kV.
d. Auxiliary Transformer 500/1500 kVA- 33/13.8kV /0.38/0.23kV
e. AC/DC Auxiliary Power supply systems.
f. Neutral Grounding Resistors.
g. Ring Main Unit (RMU)
h. Earthing and Lighting Systems.
i. Medium Voltage Switchgears 33/13.8 kV of ABB/EPS/Siemens Make.
Review all compliance statements to SEC standards and practice submitted by contractors.
Coordination with all the teams and attending progress review meeting with contractors.

Project Manager at aarti infra projects pvt ltd
  • India - Nagpur
  • February 2011 to September 2011

Key Result Areas:
• Installation, Commissioning, Management and Planning for construction of High voltage Transmission line 132kV up to 95kM, 40MVA, 132/33/11 kV substations (total 3 nos.).
• Medium voltage line 33 kV (upto 70 kM), 11 kV line (upto 250 kM), Transformer installations (25 KVA to 200 KVA)
• Low Voltage Line (LT) upto 300 KM)
• Electrified un-electrified and Breakdown Villages.
• Underground cable whenever NH and railway crossing (3C 185, 240 sq mm)

Project Manager at sterling & wilson ltd
  • India - Nagpur
  • November 2010 to February 2011

Key Result Areas:
• Installation, Commissioning, Management and Planning for construction of High voltage Transmission line 132kV up to 95kM, 40MVA, 132/33/11 kV substations (total 3 nos.).
• Medium voltage line 33 kV (upto 70 kM), 11 kV line (upto 250 kM), Transformer installations (25 KVA to 200 KVA)
• Low Voltage Line (LT) upto 300 KM)
• Electrified un-electrified and Breakdown Villages.
• Underground cable whenever NH and railway crossing (3C 185, 240 sq mm)

Sr. Electrical Engineer at FRIGERIO CONSERVA ALLANA LIMITED
  • India
  • February 2010 to October 2010

worked as a Sr. Electrical Engineer where handling responsibilities of Designing, Installing, Commissioning and Testing of Six DG sets each having capacity of 1010 KVA and Two 33 KV/415 V, 3 MVA Substations.

Distribution and scheduling of electrical power according to load schedule from DG sets and Substations to various processing plants at FCAL which has different food processing units.

Installing, Commissioning & Testing of PLC based Control System of various equipment like Compressors, Accumulators, Ammonia pumps, Oil Pumps, Condensers, ACUs, AHUs, and different temperature maintained refrigeration plants like Chiller rooms, Cold Storage, Frozen packing and Plate freezer etc.

Power distribution and control of various drives and equipment of Rendering and crushing plant and Boiler.

Sr.Business Development Executive at R F ARRAYS SYSTEMS PVT LTD
  • India - Nagpur
  • December 2008 to November 2009

Worked as a Sr. Executive Business Development on centralized wireless Substation monitoring & Control systems using Zig-Bee and GSM technology for various Substations at ISRO, BEST and APSEB.
Worked on wireless lighting and AMR Systems for CGL and Western Railways etc.
Settled and facilitated the implementation of the company’s Business, Business Development Support- tools and systems to support quality relationship.
Timely received customer feedback and did regular follow-up’s took responsibility of production activities on as and when required basis.

Sr.Executive Engineer at LARSEN AND TOUBRO LIMITED
  • India - Mumbai
  • July 2006 to September 2008

Worked as a overall site in charge for operation, maintenance of 22 KV, 2MVA indoor substations (30 Nos.) including all electrical drives, equipments and switchgears, HT & LT panels etc. at TATA MOTORS LTD. as L&T had annual maintenance contract with TML.
Provided pure & unbreakable electric supply to all workshops at car plant of TML and substations in TML.
Attended all electric as well as tripping complaint whenever occurred in shops &substation and rectified within short period.
Maintained and operated Ring Main feeder Systems etc.
Worked as a Subject Matter Expert (SME) for L&T EBG-CIC where different collected data required for CIC (Customer Interaction Centre) and had giving training to stakeholders, core team and Surveying through all over India.
Worked as a Site in charge for erecting, commissioning and testing of LT switchgears and different drive panels at Hindustan Petroleum Corporation Ltd.(HPCL).

Project Engineer at ABB LIMITED
  • India - Vadodara
  • October 2003 to June 2006

Worked as a Project coordinator / Engineer for 400/132KV, 100 MVA Substation for PGCIL where did creation of project definition, created and changed project network, project planning, scheduling, budgeting, coasting and creation of work breakdown structure (WBS), revenue planning & booking etc.
Coordinated between site management and supply chain and customer as well like Material requisition, purchase order and vender follow upped, customer correspondence and supervised all site activities etc.
Worked as a site in charge for 132/33 KV substation for Chhattisgarh State Electricity Board at Baramkela where did all site activities such as installation, Commissioning and Testing of all HT and LT switchgears including transformer, circuit breakers, CTs and PTs. Etc.
Did all activities from site takeover to completed site handover to client.

Education

Bachelor's degree, B.E. (Electrical Engineering)
  • at Rajiv Gandhi College of Engineering Research and Technology Chandrapur
  • August 2003

Electrical Engineering

Specialties & Skills

Substation Automation
Protection
Transformer
Testing and Commissioning
Electrical Installation
Engineering

Languages

English
Expert
Hindi
Expert
Marathi
Expert
Urdu
Intermediate