Sr. Electrical Engineer
PSC Trading and Contracting WLL
Total years of experience :30 years, 2 Months
Provide support and submittals to the state building approval body during the design stage for electrical and mechanical design concepts. The ability to manage construction projects. Provide shop drawings for submittals that include all major electrical equipment, substation MV/LV, and sub-main board panels. Ensure that all activities are performed according to the specifications and procedures of the project.
Projects: Falcon5/f-15QA Beddown Project, Al Udeid Air Base, State of Qatar Client: United States Army Corps of Engineers (USACE)
Among the Contractor's submittals, I reviewed requests for material approval, site delivery materials inspections, construction methodologies, shop drawings, and inspection
requests.
Performing electrical testing and commissioning.
Project: Reconstruction & Upgrading of Old Salwa RPS with Reservoir - Doha Qatar.
Ensure compliance with IFC drawings in all aspects of electrical construction, including ELV systems.
Ensure compliance with approved project submissions and approve material deliveries on site.
A regular inspection of the Contractor's work is conducted to ensure that it complies with the Contract Documents and accepted practices.
Identifying quality deficiencies on the job site by observing and inspecting the work, issuing
notices of non-compliance (NCNs), and reports of site observations (SORs). Resolve any issues resulting from the contractor's proposed corrective actions by reviewing, responding, and
following up with the contractor.
Project: Viva Bahriya - 02, (2B+G+M+21) - The Pearl Qatar; Doha
In charge of ensuring that electrical work is completed efficiently and
correctly.
Maintain a safe working environment at all times. Controlling documents and maintaining correspondence on site. Determine the requirements of the local authority by analyzing project contracts, specifications, quality levels, and
standards.
Projects: Capital Plaza Hotel, 33 Storey- Corniche; Abu Dhabi, UAE; Ministry of foreign Affairs (MOFA), 7 Storey - Abu Dhabi, UAE
Management, supervision, and control of installation work. Working with the Client/Consultant to execute and install works.
Determine local authorities' requirements by analyzing project contracts,
specifications, quality levels, and standards. Maintain accurate electrical drawings, shop drawings, engineering calculations, material take-offs, and surveying.
Project: Ministry of Environment Bldg., 25 Storey - West bay, Doha Qatar.; Yousef Alsai Apt., 5-Storey Residential Bldg- Bin Dirham AL Mansoura; Doha Qatar.
Check the quality and workmanship of the installation regularly.
Responsible for verifying biological data accuracy in material value forms for all electrical and instrument spare parts specifications.
Conduct site inspections and prepare corresponding reports based on project progress.
Projects: Arabian Petrochemical Co. (Petrochemya), Jubail, KSA
Performing/assisting with the cycle testing of all electrical items in the plant with SAP R/3 (System of Applications and Products in Data Processing).e testing of all electrical items in the plant using SAP R/3 (System of Applications and Product in Data Processing).
Safety measures should always be implemented—controlling documents and maintaining correspondence on site.
Projects: Arabian Petrochemical Co. (Petrochemya), Jubail, KSA; Saudi Yanbu Petrochemical Company (Yanpet), Yanbu, KSA; Arabian Industrial Fibers Company (IBN Rushd), Yanbu, KSA
Maintains electrical systems by inspecting, testing, and installing them. Conforms to the latest approved drawings and technical specifications and meets the highest quality standards. Testing, inspecting, and installing electrical systems. Conforms to the latest approved drawings and technical specifications and meets the highest quality standards.
Evaluate billings submitted by nominated contractors/suppliers. Assist the project QS in resolving variation/change orders. Conduct in-process inspection of construction works, monitor accomplishments against project schedule, and recommend
construction methodologies.
Projects: Ministry of Interior New Building, Riyadh KSA; Sayhat Dammam Sports Club, Dammam KSA; Mohammad Hussienan Villa, Riyadh KSA
Evaluate billings submitted by nominated contractors/suppliers. Assist the project QS in resolving variation/change orders. Conduct in-process inspection of construction works, monitor accomplishments against project schedule, and recommend
construction methodologies.
Project: Heart Tower Condominium - Makati, MM
Power Plant Design of Municipality of Bingawan Iloilo