• Preparing construction Baseline for execution accordance with consultant and contractor mutual understanding.
• Update of Baseline & Recovery program and related reports e.g. Dashboard, Cost Control, KPI & Management etc.
• Monthly and weekly Progress Reports for submittal to consultants/clients.
• Weekly & Monthly Update of Work program and related Engineering Master logs.
• Identifying applicable Work Breakdown Structure (WBS) and preparing their planning, Schedule along with their resources allocations including loading and leveling of resources, equipment, deployments, and their start and end dates.
• Look ahead work schedule with real time activities.
• Preparing Resource Histograms, expected Cash Flows and S-Curve.
• Communicating with the Project Manager and project all through the process and monitoring/reporting activities of Interior and Infrastructure.
• Coordinating with MEP Subcontractor for their Engineering logs.
• Preparing labor & non-labor Resource breakdown reflecting on activities under the light of BOQ for building other than Main Hospital Building. Preparing Resource Histograms, expected Cash Flows and S-Curve for building other than Main Hospital Building.

Planning Engineer في Daary General Contracting (Rays International)
  • الإمارات العربية المتحدة - أبو ظبي
  • سبتمبر 2014 إلى مارس 2016

• Preparing Baseline Program in accordance with the contract documents, specs, Drawings & BOM/BOQ by using PRIMAVERA.
• Coordination with client and consultant for work progress and attend the meetings Project weekly/ monthly progress.
• Update of work program and progress related reports.
• Preparing Extension of Time (EOT) claims.
• Identifying applicable Work Breakdown Structure (WBS) and preparing their planning, Schedule along with their resources allocations including loading and leveling of resources, equipment, deployments, and their start and end dates.
• Look ahead work schedule with real time activities.
• Preparing Resource Histograms, expected Cash Flows and S-Curve.
• Communicating with the Project Manager and project all through the process and monitoring/reporting activities of Interior and Infrastructure.
• Maintaining and documenting the Extension of Time (including variations) for each project and pre-warning the Operations Team and management for requirement of extension of time.
• Preparing Monthly and weekly Progress Reports for submittal to consultants/clients.
• Preparing Recovery Programs for approval by clients and consultants, With prior approval by the management.

Planning Engineer في Phoenix Timber Factory LLC
  • الإمارات العربية المتحدة - أبو ظبي
  • نوفمبر 2013 إلى أغسطس 2014

★ Developed the Baseline work Schedule for projects related to Joinery & Civil Works
★ Responsible for Progress Reporting, monitoring, and had highlighted any deviation from baseline program
★ Weekly Factory and Site visit for the collection of progress data
★ Prepared cost estimate evaluation for Bill of Quantities related to Joinery & Civil Works
★ Essential study of Drawings, contract and based on tender identified the desired product requirement
★ Follow up with raw material suppliers for rate and cost estimate till end product

Planning Engineer في Areenouf Group
  • الإمارات العربية المتحدة - أبو ظبي
  • ديسمبر 2012 إلى أكتوبر 2013

• Planning & scheduling the project in accordance with the contract documents, specs, Drawings & BOM/BOQ’s by using PRIMAVERA.
• Coordination with client and contractor for work schedule and attend the meetings with related authorities for Project weekly/ monthly progress.
• Update of Baseline Program & KPI.
• Identifying applicable Work Breakdown Structure (WBS) and preparing their planning, Schedule along with their resources allocations including loading and leveling of resources, equipment, deployments, and their start and end dates. Look ahead work schedule with real time activities.
• Identifying alerts regarding work schedule.
• Preparing resource histograms and Cash Flow.
• Communicating with the Project Manager and the supervisors all through the process and monitoring/reporting activities of Interior/ Infrastructure for execution to handing over.
• Maintaining and documenting the Extension of Time. Maintaining the delay analysis & to ensure every issue is being recorded & addressed in Issue log.
• Alarming management and execution team about anticipated delays on any critical component of the project. Preparing Monthly Progress Reports for submittal to consultants or clients.
• Preparing Recovery Programs for approval by clients and consultants. Responsible for monitor the progress in the fit out / construction process and continuous checking with project schedule.

Planning Engineer في Al-Prince Engineers Ltd
  • باكستان - لاهور
  • يوليو 2011 إلى نوفمبر 2012

• Preparing Baseline Program in accordance with the contract documents, specs, Drawings & BOM/BOQ by using PRIMAVERA & MS Project.
• Coordination with client and consultant for work progress and attend the meetings Project weekly/ monthly progress.
• Update of Baseline Program, KPI and Preparing resource histograms.
• Identifying applicable Work Breakdown Structure (WBS) and preparing their planning, Schedule along with their resources allocations including loading and leveling of resources, equipment, deployments, and their start and end dates.
• Look ahead work schedule with real time activities.
• Identifying alerts regarding work schedule.
• Coordination with client and consultant for timely completion of the activities and attend the meetings with related authorities for approvals.
• To monitor the progresses in the construction process and continuous checking this with the project schedule.
• Analyze the construction sites as well as the local environments to arrange proper logistics solutions and resources in order to execute the program.
• Coordinating filed activities regarding design changes and internal scheduling with consultants and project manager.
• Responsible for the daily progress report of the Civil, Mechanical & Electrical works and informed the Site Incharge, construction manager, consultants and clients.
• Supervision, checking of subcontractor’s bill and coordinating their on-field work.

Site Engineer في Ghulam Habib Co. Ltd
  • باكستان - بيشاور
  • ديسمبر 2010 إلى يونيو 2011

• Ensure Quality of work at site.
• Prepare the bar bending schedule.
• Preparation of concrete pouring slips.
• Complete Layout for Domestic Building Works.
• Responsible for all on-site buildings construction activities.
• Supervision and Execution of all kinds of Domestic Building Works.

Intern في Metecno Pakistan (Pvt) Ltd
  • باكستان - لاهور
  • يوليو 2009 إلى أغسطس 2009

• Checking of Bill of Quantities.
• P.E.B (Pre-Engineered Building).
• Worked in L.G.S (Light Gauge Structures) under the light of BS Code and ACI.
• Estimation of Quantities, Tensile and Chemical Properties of Nut Bolt Assembly.

الخلفية التعليمية

ماجستير, LLM Construction Law & Arbitration
  • في The Robert Gordon University
  • يونيو 2022
بكالوريوس, Civil Engineering
  • في CECOS University of IT and Emerging Sciences
  • فبراير 2011

Specialties & Skills

Earned Value Management
Planning
Primavera P6
Project Control
Civil Engineering
MS Office
MS Project 2010
Primavera
Planning
Engineering Management
Primavera 6
Planning Engineer

اللغات

العربية
مبتدئ
الهندية
متوسط
الأوردو
متمرّس
الانجليزية
متمرّس

العضويات

Project Management Institute
  • Member
  • October 2015

التدريب و الشهادات

PMP (تدريب)
معهد التدريب:
Cambridge Educational Institute
تاريخ الدورة:
September 2017