Project manager
cepco
Total years of experience :12 years, 2 Months
CONTRACTION OF 380KV U/G CABLES BETWEEN KMT BSP - HVP1 S/S
Interconnection of 380/110kV jeddah cental BSP with 110kV Jeddah Network.
installation of new protection panel and replacing new GIS CT in makkah
installation of new 110 kv cable between 4 substations
From feb 2012 till know
Ras alkher damam- SAUDI ARYBIA
Technical group company / RAS AZ ZAWR POWER AND DESALININATION PLANT- PHASE 1
Duties:
-Supervisor Engineer of HRSG sys.
-Supervisor Engineer of EXHAUST BYPASS sys.
-Supervisor Engineer of GAS TURBINE sys
september 2011 Bachelor of Electrical Power Engineering Al-Baath University. Homs, Syria. - Graduation Project: A study about Improve power factor in industrial installations using simulation in Matlab