Sr. Site Engineer
ParklandGEO
مجموع سنوات الخبرة :28 years, 3 أشهر
Fort Hills Oil Sand Site / Suncor, North Fort McMurray, AB, Canada
.Monitor the quality of piles installation process.
.Overseeing the piling construction process and issue request for info (RFI).
.Issue non conformance report (NCR) and corrective actions.
.Review piles installation daily record and issue daily and weekly reports.
.Accept / Reject installed piles based on WEAP or PDA test report.
.Attend daily meeting and coordinate between site and office.
.Calculate the tension capacity of pile based on soil reports.
.Solve construction related issues.
• Designed and Prepared layouts and details of concrete and steel structures for CNRL Oil Sand Extraction Plant Trains 3-4
• Designed Concrete Structure such as Road Crossing, Trenches, and Cover Slabs.
• Designed Steel Structures for access Platforms, Pipe Racks, and Buildings
• Quality Control and inspection of precast concrete panels at Lafarge Edmonton for SUNCOR Coker Foundation repair.
• Designed and Produced layouts and details of concrete and steel structure for Projects such as:- o Cernavodă Nuclear Power Plant, CANDU 6, Romania
o Embalse Nuclear Power Station, CANDU 6, Argentina
• Checked Engineering Drawings Quality.
• Provided Technical Guidance To Junior Personnel
• Designed & Produced layouts and details of concrete & steel structure for Projects such as:-
o Fuel Packaging and Storage Building at Chalk River, Ontario
o Waste Management Area and Access Roads at Chalk River, Ontario
• Worked on CANDU Reactor and Nuclear Generating Plants such as:-
o Structure for Low and Intermediate Level Waste, Gentilly-2, Hydro Quebec
o Layout of reactor, service building and embedded parts of Enhanced CANDU 6
o Reactor and Service Building, Point Lepreau, New Brunswick
o Retube Canister, Wolsong, Korea
• Visited G2, Hydro Quebec Reactor Building to investigate interferences between as built structures and proposed new support.
• Checked Engineering Drawings Quality. Provided technical guidance to junior personnel
• Worked with other Disciplines to ensure project close-out
• Assisted in the development of company policies and production standards
• Inspected Municipal Construction Projects such as: -
o Retaining Walls (Maccaferri & Lock + Load) and (Durisol & Terrafix)
o Bridge, Roads, curb, sidewalk, and Viewing Steel Platform.
• Checked As-Built to ensure quality requirements is met.
• MTO Earthwork, Roads, Concrete and Drainage System.
• Managed communication between contractors and City of Hamilton.
• Attended construction meetings, and document construction site conditions.
• Checked the quality of Welded Connection of Steel Frames.
• Ensured that products are done according to the specification.
• Managed communication between clients and management
• Produced reports & charts displaying the quality condition.
• Projects such as; Al Gouna Red Sea Resort, Movenpick; consists of six groups of about 300 rooms, a main building, a conference center, restaurants, swimming pools, and landscaping that includes ponds, roads, bridges, and green areas. The total land area of the project is 250, 000m².
• Designed reinforcement's concrete structures members such as Slabs, Beams, Columns, Footings, and Retaining Walls.
• Studied the soil test report to get the allowable stresses at foundations levels.
• Studied the architectural drawing and general layout.
• Prepared all calculation sheets and drawing with all details.
B.Sc. Computer Science and Engineering