Bridge Engineer at HKRR Ltd
  • Kuwait
  • My current job since July 2014
Senior Bridge Engineer at HKRR Ltd
  • February 2011 to July 2014
Senior Bridge Engineer at HKRR Ltd
  • June 2011 to June 2014

Design, Construction, Finance Operation and Maintenance of Four laning of Hyderabad - Karimnagar -Ramgunadam Road (SH-1) From Km 197+ 000- to Km 235+058 in the state of Andhra Pradesh under public private partnership (PPP) on DBFOT (Toll) basis. Project Cost: INR 450Crores Client: APRDC (Total input 20 months)
Main Project features: The Package - 4 of this project corridor consists of 1 Major bridges of length of 1.1Km situated on GODAVARI River, 1ROB, 1 RUB, 7 Minor bridges and Culverts (pipe and box). The foundations of all major and minor bridges consists of Raft foundations or Pile Foundations.. There are also a variety of super structures ranging from PSC I beams, RCC I beams, solid slabs and box structures
Responsibilities:
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking & Approval of construction Methodology submitted by the sub - contractor
•Supervision of piling activities involved in the site and conducted pile load test of vertical and lateral load test.
•Supervision of execution of pile caps, open foundation, piers and pier caps as per drawings.
•Conducted Standard Penetration Tests, Plate Load Test etc.
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Checking the subsoil investigation to the structures.
•Review the staging design.
•Liaison work carried out with Local departments involved in the projects..
•Maintaining & verification of quality at all stages of work in conformation with standard specifications.
•Modify drawings as per the site conditions, liaison with client regarding daily progress; prepare the weekly and monthly progress.
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills.
•Reviewing the working drawings & BBS submitted by EPC of all structures by considering the comments of independent consultants before starting execution at site.
•Execution and supervision of all construction activities as per the RFIs submitted for inspection from time to time and supervising the work as per approved working drawing and specification for quality output.
•Responsibility includes preparation of methodologies & staging drawings, execution of structures from lay out checking up to super structure completion level of major bridges, minor bridges, Under Passes, culverts & RE Walls as per MORST&H, IS & IRC specifications.
•Planning of machinery & man power by coordinating with superiors during monitoring of works at site. Preparation of BOQ related to sub-contractors.
•Involved in weekly, monthly progress reports preparation & attending review meetings pertaining to progress & Quality.

Senior Bridge Engineer at Consortium of DLF GAYATRI&MEGHA
  • February 2011 to June 2014
Project Manager
  • June 2009 to May 2011

Structures, Terra Infra ltd
Construction of Eight Lane access controlled expressway as Outer Ring Road to Hyderabad City, Phase-IIA from Kolluru (Km. 12+000) to Patancheru (Km. 23+700) Project Cost: INR 5500 Million, Client: HUDA, Conssesionaire: CEPL (Total input 24 months)
Main Project features:
The project corridor consists of 1 Major bridges, 2 Minor bridges and culverts (pipe and box). The foundations of all major and minor bridges are RAFT foundations Pile Foundations.. There are also a variety of super structures ranging from PSC I beams to RCC I beams, solid slabs and box structures & RE Walls
Responsibilities:
•Checking & Approval of construction Methodology submitted by the sub - contractor
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking the subsoil investigation to the structures.
•Review the staging design.
•Liaison work carried out with Local departments involved in the projects..
•Maintaining & verification of quality at all stages of work in conformation with standard specifications.
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills.
•Reviewing the working drawings & BBS submitted by EPC of all structures by considering the comments of independent consultants before starting execution at site.
•Execution and supervision of all construction activities as per the RFIs submitted for inspection from time to time and supervising the work as per approved working drawing and specification for quality output.
•Responsibility includes preparation of methodologies & staging drawings, execution of structures from lay out checking up to super structure completion level of major bridges, minor bridges, Under Passes, culverts & RE Walls as per MORST&H, IS & IRC specifications

Senior Bridge Engineer
  • July 2014 to February 2011

Design, Build, Complete & Maintain Shaikh Jaber Al-Ahmad Al-Sabah Causeway Project




Design, Construction, Finance Operation and Maintenance of Four laning of Hyderabad - Karimnagar -Ramgunadam Road (SH-1) From Km 197+ 000- to Km 235+058 in the state of Andhra Pradesh under public private partnership (PPP) on DBFOT (Toll) basis.

Manager at Terra Infra Ltd
  • June 2009 to September 2010
Manager at Terra Infra ltd
  • June 2009 to September 2010
Project Manager at Terra Infra ltd
  • June 2009 to September 2009

Construction of Eight Lane access controlled expressway as Outer Ring Road to Hyderabad City, Phase-IIA from Kolluru (Km. 12+000) to Patancheru (Km. 23+700) BOT Project, conssesiire: CEPL

Manager at Maytas Infra Ltd
  • September 2007 to May 2009
Project Manager at Maytas Infra ltd
  • September 2007 to May 2009

Construction of Eight Lane access controlled expressway as Outer Ring Road to
Hyderabad City, Phase-IIA from Kolluru (Km. 12+000) to Patancheru (Km. 23+700). Project Cost: INR 3180 Million, Conssesionaire: CEPL.

Manager at Maytas Infra ltd
  • September 2007 to May 2009
Project Manager at Maytas Infra ltd
  • September 2007 to May 2009

Construction of Eight Lane access controlled expressway as Outer Ring Road to
Hyderabad City, Phase-IIA from Kolluru (Km. 12+000) to Patancheru (Km. 23+700). Project Cost: INR 5500 Million, Client: HUDA, Conssesionaire: CEPL. (Total input 21 months)

Responsibilities:
•Checking & Approval of construction Methodology submitted by the sub - contractor
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking the subsoil investigation to the structures.
•Review the staging design.
•Liaison work carried out with Local departments involved in the projects..
•Maintaining & verification of quality at all stages of work in conformation with standard specifications.
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills.
•Reviewing the working drawings & BBS submitted by EPC of all structures by considering the comments of independent consultants before starting execution at site.
•Execution and supervision of all construction activities as per the RFIs submitted for inspection from time to time and supervising the work as per approved working drawing and specification for quality output

Manager at GMR Projects Pvt Ltd
  • India
  • February 2006 to May 2007
Project Manager at GMR Projects Pvt Ltd
  • India
  • February 2006 to May 2007

Strengthening and Widening of existing 2 lane roads to 4lane from Construction Supervision Faruknagar to Jadcherala. NH-7. BOT Project

Manager at M R Projects Pvt Ltd
  • India
  • February 2006 to May 2007
Project Manager at M R Projects Pvt Ltd
  • India
  • February 2006 to May 2007

Strengthening and Widening of existing 2 lane road to 4lane from Faruknagar to Jadcherala. NH-7. BOT Project Cost: INR 3530 Million Client: National Highway Authority of India (Total input 16 months)
Main Project features:
The project corridor starts from Km34.140 at KOTTUR and ends at JADCHERALA Km 80.000 of NH-7. The corridor consists of 3 major bridges, 7 minor bridges and 44 culverts (pipe and box). The foundations of all major and minor bridges are RAFT foundations. There are also a variety of super structures ranging from 32m PSC I beams to 20m RCC I beams, 10m solid slabs and box structures.

Responsibilities:
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking the subsoil investigation to the structures.
•Review the staging design.
•Liaison work carried out with Local departments involved in the projects..
•Maintaining & verification of quality at all stages of work in conformation with standard specifications
•Checking & Approval of construction Methodology submitted by the sub - contractor
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills.
•Reviewing the working drawings & BBS submitted by EPC of all structures by considering the comments of independent consultants before starting execution at site.
•Execution and supervision of all construction activities as per the RFIs submitted for inspection from time to time and supervising the work as per approved working drawing and specification for quality output

junior Engineer at M/ Gammon India limited
  • December 1997 to November 2005

Assignment in the Project

Project Engineer at Gammon India limited
  • India
  • January 2004 to January 2005
Project Engineer at Gammon India limited
  • India
  • January 2004 to January 2005

Construction Supervision of ROB Domoria pull Jalandhar Punjab Project Cost: INR 1000 Million Client: Punjab PWD (Total input 12 months)
Main Project features:
ROB @Domoria pull Bridge in Jalandhar. The Bridge length is of 2 km. It consists of 20 members of40 mts length box girders and 200 members of 30 mts length PSC girders

Responsibilities:
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking the subsoil investigation to the structures.
•Review the staging design.
•Liaison work carried out with Local departments involved in the projects..
•Maintaining & verification of quality at all stages of work in conformation with standard specifications
•Checking & Approval of construction Methodology submitted by the sub - contractor
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub contractor bills

Assistant Engineer at Gammon India limited
  • India
  • January 2004 to April 2004

Responsibilities during Construction:
Maintaining & verification of quality at all stages of work in conformation with standard specifications. Checking & Approval of construction Methodology submitted by the sub - contractor. Checking the bar bending schedule, concrete pouring to the structures. Checking shuttering, scaffolding arrangement, curing to the structures. Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C. Setting out of alignment with reference to alignment plan and GAD. Checking the subsoil investigation to the structures. Review the staging design. Liaison work carried out with Local departments involved in the projects. Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub contractor bills.
Responsibilities during Rehabilitation:
Rectifying the cracks in the abutment & Piers (Sub-Structure) with FRP injection method & Plastering with PMC (Polymer Modified cement) Mortar & Injection grouting with epoxy for super structure as per specifications. Inspecting the roller bearing and re fixing the same as it was in good condition Replacing the defective expansion joints with water stopper Replacing the defective crash barrier wherever it is needed. Resurfacing BC with profile corrective course. Conducting core test & Non- destructive test to ascertain the concrete condition of the bridge as per specifications.

Project Engineer at Gammon India limited
  • India
  • January 2002 to January 2004
Project Engineer at Gammon India limited
  • India
  • January 2002 to January 2004

Strengthening and Widening of existing 2 lane road to 4lane from Rajamundry to Dharmavaram NH-5 BOT Project (including rehabilitation of Major Bridges) Client: National Highway Authority of India. Project Cost: INR 3250 Million (Total input 24 months)
Main Project features:
The project corridor consists of 2 major bridges, 3 minor bridges and 60 culverts(pipe and box). The foundations of all Major Bridges are WELL foundations and Minor bridges are RAFT foundations. There are also a variety of super structures ranging 50 mts Box girders, 30 mts PSC I beams, 20 mts RCC I beams, 10 mts solid slabs and box structures.

Responsibilities during Construction:
•Maintaining & verification of quality at all stages of work in conformation with standard specifications
•Checking & Approval of construction Methodology submitted by the sub - contractor
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking the subsoil investigation to the structures.
•Review the staging design.
•Liaison work carried out with Local departments involved in the projects..
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills.

Rehabilitation and Repair works for the Yerram Major Bridge (LHS) on NH5. The total Length of the Bridge is 150m consisting 5 spans of 30m each.
Responsibilities during Rehabilitation:
•Rectifying the cracks in the abutment & Piers (Sub-Structure) with FRP injection method & Plastering with PMC (Polymer Modified cement) Mortar & Injection grouting with epoxy for super structure as per specifications.
•Inspecting the roller bearing and re fixing the same as it was in good condition
•Replacing the defective expansion joints with water stopper
•Replacing the defective crash barrier wherever it is needed.
•Resurfacing BC with profile corrective course.
•Conducting core test & Non- destructive test to ascertain the concrete condition of the bridge as per specifications

Project Engineer at Gammon India limited
  • India
  • January 2002 to December 2002

Strengthening and Widening of existing 2 lane road to 4lane from Rajamundry to Dharmavaram NH-5 (including rehabilitation of Major Bridges) BOT Project Cost: INR 3250 Million

Assistant Engineer at Gammon India limited
  • India
  • January 2001 to January 2002
Assistant Engineer at Gammon India limited
  • India
  • January 2001 to January 2002

Vasai creek Bridge. Project Cost: INR 1120 Million Client: Maharastra Road Development Corporation (Total input 12 months)
Main Project features:
This Bridge is constructed in Sea of length of 2 kms connecting two city muncipalities by Rail Track. Entire components are pre fabricate on off shore and launched in position. The bridge has 45 m length Pre-cast Post tentioned Box girders and wellfoundations of 8 metres Dia sinking to a depth of 30 mts from bed level..

Responsibilities:
•Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C.
•Setting out of alignment with reference to alignment plan and GAD.
•Checking the subsoil investigation to the structures.
•Maintaining & verification of quality at all stages of work in conformation with standard specifications
•Checking the bar bending schedule, concrete pouring to the structures.
•Checking shuttering, scaffolding arrangement, curing to the structures.
•Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills

Assistant Engineer at Maharashtra Road Development Corporation
  • January 2001 to April 2001

Nov

Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C. Setting out of alignment with reference to alignment plan and GAD. Checking the subsoil investigation to the structures. Maintaining & verification of quality at all stages of work in conformation with standard specifications Checking the bar bending schedule, concrete pouring to the structures. Checking shuttering, scaffolding arrangement, curing to the structures. Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills

Assistant Engineer at Gammon India limited
  • India
  • January 1999 to January 2001
Assistant Engineer at Gammon India limited
  • India
  • January 1999 to January 2001

JJ - flyover project. Cost of Project: INR 600 Million

at Maharasta Road Development Corporation
  • January 1999 to February 1999

April
Checking the bar bending schedule, concrete pouring to the structures. Checking shuttering, scaffolding arrangement, curing to the structures. Checking and approvals of BBS and recording the monthly measurements in M-book as per IPC for sub-contractor bills Construction Supervision of bridges giving instructions to my field Engineers, daily job request, approvals, check and give approval for construction after getting approval from I.C. Setting out of alignment with reference to alignment plan and GAD. Checking the subsoil investigation to the structures. Maintaining & verification of quality at all stages of work in conformation with standard specifications

Junior Engineer at Gammon India limited
  • India
  • January 1997 to January 1999
Junior Engineer at Gammon India limited
  • India
  • January 1997 to January 1999

Vashi -CMLR flyover, Vashi, Navi Mumbai, (including rehabilitation of Major Bridges) Project Cost: INR 450 Million Client: Maharastra Road Development Corporation (Total input 35 months)
Main Project features:
This Bridge consists of precast pre-tention and post-tention Igirders. The project corridor consists of 1 major bridges of length of 1.1Km situated on GODAVARI River, 10minor bridges and 65 culverts (pipe and box). The foundations of all major and minor bridges are RAFT foundations Pile Foundations.. There are also a variety of super structures ranging from 32m PSC I beams to 20m RCC I beams, 10m solid slabs and box structures & RE Walls.
Responsibilities during Construction:
Responsilble for all civil works such as sub structures and super structure works.
•Supervision of labors day to day activities
•Preparation of bar bending schedule and submitting necessary documents to client for approval,
•Maintaining muster records and daily works report,
•Survey work and layout checking.
•Preparation of sub-contractor bills.
•Coordinating with Client
•Field and laboratory test
•Preparation of diversions as per site conditions

Rehabilitation and Repair works for the Subsidary Bridge leading to Vashi -CMLR flyover, Vashi, Navi Mumbai, The length of the bridge is 300m
Responsibilities during Rehabilitation:
•Rectifying the cracks in the abutment & Piers (Sub-Structure) with FRP injection method & Plastering with PMC (Polymer Modified cement) Mortar & Injection grouting with epoxy for super structure as per specifications.
•Inspecting the bearing and re fixing the same as it was in good condition
•Replacing the defective expansion joints with water stopper
•Replacing the defective crash barrier wherever it is needed.
•Resurfacing BC with profile corrective course.
•Conducting core test & Non- destructive test to ascertain the concrete condition of the bridge as per specifications.


Languages:
Language
Reading
Writing
Speaking
English
Excellent
Excellent
Excellent
Hindi
Excellent
Excellent
Excellent
Telugu
Excellent
Excellent

Junior Engineer at Gammon India limited
  • India
  • January 1997 to December 1997

Vashi -CMLR flyover, Vashi, Navi Mumbai, (including rehabilitation of Major Bridges) Project Cost: INR 450 Million

Bridge /Structural Engineer at Dar al Handasah
  • Kuwait
  • July 2014 to

I have sufficient experience & knowledge of supervising and monitoring of well foundation, Pile foundation, open foundation, Piers, Abutments, Bearings, I-girder, Box girder deck slab and voided deck slab with post tensioning system. He has thorough understanding and experience in international ‘best practices’ and modem bridge construction technology including bridge foundations viz. well/pier, post tensioning system of pre-stressing, casting of pre-cast PSC concrete box girder and ‘T’ girders, launching and erection of pre-cast PSC girders up to 200 M.T. weight, conducting load tests, fabrication of heavy launching steel girders, reinforced earth panel system for VOP approaches, etc.

He is well conversant with bridge construction materials, technical specifications, testing procedure, relevant IRC codes and MORTH and AASHTO specifications and standards and best practices in the construction of bridges. He is thoroughly conversant with design standards, technical specifications and statistical quality control and quality assurance procedures for construction of different components of bridges. He is also well versed with FIDIC contract conditions.
•Design, Construction, Finance Operation and Maintenance of Four laning of Hyderabad - Karimnagar -Ramgunadam Road (SH-1) From Km 197+ 000- to Km 235+058 in the state of Andhra Pradesh under public private partnership (PPP) on DBFOT (Toll) basis. Project Cost: INR 400Crores Client: APRDC
•Construction of Eight Lane access controlled expressway as Outer Ring Road to Hyderabad City, Phase-IIA from Kolluru (Km. 12+000) to Patancheru (Km. 23+700) Project Cost: INR 5500 Million, Client: HUDA, Conssesionaire: CEPL
•Construction of Eight Lane access controlled expressway as Outer Ring Road to
Hyderabad City, Phase-IIA from Kolluru (Km. 12+000) to Patancheru (Km. 23+700). Project Cost: INR 3180 Million, Client: HUDA, Conssesionaire: CEPL
•NH-7.BOT Project for strengthening and widening of existing 2 lane road to 4lane from Faruknagar to Jadcherala. Project Cost: INR 3530 Million Client: National Highway Authority of India
•ROB Domoria pull Jalandhar Punjab Project Cost: INR 1000 Million Client:
•Rajamundry -Dharmavaram NH-5 BOT Project for strengthening and widening of existing 2 lane road to 4lane (including rehabilitation of Major Bridges) Client: National Highway Authority of India. Project Cost: INR 3250 Million
•Vasai creek Bridge. Project Cost: INR 1120 Million Client:
•JJ - flyover project. Cost of Project: INR 600 Million Client:
•Vashi -CMLR flyover, Vashi, Navi Mumbai, (including rehabilitation of Major Bridges) Project Cost: INR 450 Million

Structural Engineer at Dar Al Handasah
  • Qatar
  • to
Project Engineer at Gammon India limited
  • India
  • to

Construction Supervision of ROB Domoria pull Jalandhar Punjab Project Cost: INR 1000 Million

Education

Bachelor's degree, Civil Engineering
  • at REC Warangal
  • January 1997
Bachelor's degree, Civil Engineering
  • January 1992

in

Specialties & Skills

BASIC CHECK
BRIDGES
CUSTOMER RELATIONS
FEATURES
MICROSOFT WORKS
QUALITY
RECORDING
SUPERVISORY SKILLS

Languages

English
Expert
Hindi
Expert