Total Years of Experience: 18 Years, 1 Months
August 2011
To Present
Lead Mechanical Engineer
at ICI Pakistan (Formerly Part of the AkzoNobel Group)
Location :
Pakistan - Lahore
Worked as Lead Mechanical in the Corporate Technical & Engineering Function for the successful development of a project worth PKR 2Billion. The project scope included setting up 02 Coal Fired Boilers of 45TPH capacity each together with a state of the art Desox system and a 3MW steam turbine for power generation.
- Coordinated in development & review of Technology Evaluation & Selection Criteria Report
- Developed Project Costing Sheet to establish stringent cost control and also monitor key payment milestones.
- Developed Project Plan & Spent Plan to monitor overall progress and control timeline of activities.
- Coordinated with finance function for Project Risks identification & development of mitigation plan through arrangement of Forward Covers, Advance Payments, Insurances etc.
- Coordinated in review & development of Engineering Services and Equipment Supply Contract with China Chengda Engineering Company Limited.
- Coordinated in development of preliminary scope of work for Civil Construction to finalize civil construction contract.
- Outsourced & Reviewed the design for Outside Battery Limit Piping & Fire Water System in coordination with process counterpart.
- Carried out reviews of the Project Design submitted by China Chengda Engineering Company Limited together with the process counterpart.
- Developed Scope of Work for Mechanical Construction Contract, Contractor Selection Criteria.
- Carried out evaluation of Mechanical Works Bids, Post Bid Clarifications with contractors and finalization & award of Mechanical Contract.
- Played a key role as a Hazard Study Team Member which comprises of a complete six stage Hazard study process.
- Carried out HAZDEM & HAZCON Studies in a team to integrate safety and minimize/eliminate hazards identified.
- Reviewed Risk Assessments submitted by Contractor against the Work Method Statements and ensured compliance with the organization risk matrix.
- Reviewed the Shipment Handling Plan for safe & systemized storage of the Project Shipments weighing approximately 3000tonnes.
- Coordinated in development & review of Technology Evaluation & Selection Criteria Report
- Developed Project Costing Sheet to establish stringent cost control and also monitor key payment milestones.
- Developed Project Plan & Spent Plan to monitor overall progress and control timeline of activities.
- Coordinated with finance function for Project Risks identification & development of mitigation plan through arrangement of Forward Covers, Advance Payments, Insurances etc.
- Coordinated in review & development of Engineering Services and Equipment Supply Contract with China Chengda Engineering Company Limited.
- Coordinated in development of preliminary scope of work for Civil Construction to finalize civil construction contract.
- Outsourced & Reviewed the design for Outside Battery Limit Piping & Fire Water System in coordination with process counterpart.
- Carried out reviews of the Project Design submitted by China Chengda Engineering Company Limited together with the process counterpart.
- Developed Scope of Work for Mechanical Construction Contract, Contractor Selection Criteria.
- Carried out evaluation of Mechanical Works Bids, Post Bid Clarifications with contractors and finalization & award of Mechanical Contract.
- Played a key role as a Hazard Study Team Member which comprises of a complete six stage Hazard study process.
- Carried out HAZDEM & HAZCON Studies in a team to integrate safety and minimize/eliminate hazards identified.
- Reviewed Risk Assessments submitted by Contractor against the Work Method Statements and ensured compliance with the organization risk matrix.
- Reviewed the Shipment Handling Plan for safe & systemized storage of the Project Shipments weighing approximately 3000tonnes.
January 2014
To Present
Construction Manager Mechanical
at ICI Pakistan (Formerly Part of the AkzoNobel Group)
Location :
Pakistan - Lahore
Working with the Polyester Business on a project worth USD 10.7M to install 02 Coal Fired Boilers & 15MW Steam Turbine with integrated Utilities & Auxiliary Plants. Looking after the Engineering/Design Review & Project Execution.
October 2007
To July 2011
Project Engineer
at Fatima Fertilizer Company Limited
Location :
Pakistan
Major Projects & Accomplishments
Nitric Acid Storage & Transfer Facility at Keamari Port, Karachi
- Worked as Project Lead to develop Nitric Acid Export Facility worth PKR 150M.
- Developed a Budget & Activity Plan Sheet for the project.
- Supervised engineering consultant for Design & Detail Engineering of Civil, Electrical & Instrumentation work of the facility. Resolved all technical queries.
- Reviewed & Improved Mechanical Design Package of the facility consisting of Piping Plans, Isometrics & Part Fabrication Drawings in line with best Industry Practices.
- Developed Scope of Work for Construction.
- Evaluated 02 Stainless Steel Tanks for Fitness of use with change of Fluid Service.
Gaseous Ammonia Supply Facility at CAN Plant
- Lead the Project utilizing in-house resources for Design & Execution.
- Developed Plot Plan, Equipment Layout, Piping Plan, Isometrics, Support drawings & BOQ of the Facility.
- Coordinated with Civil, Instrumentation & Inspection interfaces for completion of overall design.
- Reviewed quotes for piping material & Comparative Statement for approval.
- Evaluated Vessels from relocated NPK Plant for Fitness of Service in-line with new Process requirements.
Nitric Acid Tanker Loading Facility Project
- Developed Plot Plan, Piping Plan, Isometrics, Support drawings & BOQ of the Facility.
- Designed Steel Structure in-house using Staad Pro & carried out load analysis.
- Coordinated with Civil, Electrical & Instrumentation sections to ensure spot-on integration of designs.
- Reviewed quotes for piping material & Comparative Statement for approval.
Ammonium Nitrate Buffer Tank Project
- Worked as Project Lead to develop AN Buffer Tank & Pumping Facility worth PKR 25M.
- Prepared requisition for Design, Fabrication & Construction of Tank.
- Reviewed Activity Plan Sheet submitted by EPC contractor for the Tank.
- Coordinated with engineering consultant for Design of Civil & Piping work of the facility.
- Reviewed Piping Plan & Isometric Drawings in line with UDHE Specification & good engineering practices.
- Coordinated with relevant interfaces for execution of Civil & Piping works.
- Evaluated Relocated Stainless Steel Tanks for Fitness of use.
Plant Integration & Utilities Project
- Worked with ‘K-Plant Engineering Systems Ltd, Japan’ to carry out Detail Engineering of the project consisting of IA/PA Package, Diesel Tank & NG Station, O/U Deaerator, Fire Water Pumping Station, Cooling Tower & Condensate Collection System.
- Prepared Package Document Lists, Piping Layouts, Isometrics & Support Drawings in line with Project Specifications & good Engineering Practices.
- Reviewed & Commented on Mechanical Design of Pipe Racks & UG Piping submitted by ‘Wuhuan Engineering Ltd, China’.
- Supervised Fabrication & Installation of Piping in IA/PA, Diesel Tank, NG Station, O/U Deaerator, Fire Water Pumping, Cooling Tower & Underground Pipeline Areas.
Engineering Reviews & Procurement
- Reviewed Design & Fabrication details of Pressure Vessels & Heat Exchangers in line with ASME BPVC Sec. VIII(Div.1) & TEMA. Coordinated with DESCON Manufacturing Ltd. & AZTECH Heat Exchangers Ltd. for resolution of technical queries during Fabrication.
- Carried out Technical Evaluation/Review of quotations received against Piping Material Requisitions and Special Piping items in-line with Project requirement & applicable International Codes & Standards.
- Carried out Technical clarification/negotiation with supplier of Piping Materials & Prepared Comparative Statement with final recommendation for management approval.
General Jobs
- Design & Coordination of Gas Turbine Ventilation Blower Project.
- Generate Welding Procedure Specification for mechanical/piping jobs against requests from maintenance teams of plants.
- Look after Design of Piping/Mechanical modification jobs proposed by Process Engineering Section after process reviews at Ammonia, Urea, NA & CAN plants.
Nitric Acid Storage & Transfer Facility at Keamari Port, Karachi
- Worked as Project Lead to develop Nitric Acid Export Facility worth PKR 150M.
- Developed a Budget & Activity Plan Sheet for the project.
- Supervised engineering consultant for Design & Detail Engineering of Civil, Electrical & Instrumentation work of the facility. Resolved all technical queries.
- Reviewed & Improved Mechanical Design Package of the facility consisting of Piping Plans, Isometrics & Part Fabrication Drawings in line with best Industry Practices.
- Developed Scope of Work for Construction.
- Evaluated 02 Stainless Steel Tanks for Fitness of use with change of Fluid Service.
Gaseous Ammonia Supply Facility at CAN Plant
- Lead the Project utilizing in-house resources for Design & Execution.
- Developed Plot Plan, Equipment Layout, Piping Plan, Isometrics, Support drawings & BOQ of the Facility.
- Coordinated with Civil, Instrumentation & Inspection interfaces for completion of overall design.
- Reviewed quotes for piping material & Comparative Statement for approval.
- Evaluated Vessels from relocated NPK Plant for Fitness of Service in-line with new Process requirements.
Nitric Acid Tanker Loading Facility Project
- Developed Plot Plan, Piping Plan, Isometrics, Support drawings & BOQ of the Facility.
- Designed Steel Structure in-house using Staad Pro & carried out load analysis.
- Coordinated with Civil, Electrical & Instrumentation sections to ensure spot-on integration of designs.
- Reviewed quotes for piping material & Comparative Statement for approval.
Ammonium Nitrate Buffer Tank Project
- Worked as Project Lead to develop AN Buffer Tank & Pumping Facility worth PKR 25M.
- Prepared requisition for Design, Fabrication & Construction of Tank.
- Reviewed Activity Plan Sheet submitted by EPC contractor for the Tank.
- Coordinated with engineering consultant for Design of Civil & Piping work of the facility.
- Reviewed Piping Plan & Isometric Drawings in line with UDHE Specification & good engineering practices.
- Coordinated with relevant interfaces for execution of Civil & Piping works.
- Evaluated Relocated Stainless Steel Tanks for Fitness of use.
Plant Integration & Utilities Project
- Worked with ‘K-Plant Engineering Systems Ltd, Japan’ to carry out Detail Engineering of the project consisting of IA/PA Package, Diesel Tank & NG Station, O/U Deaerator, Fire Water Pumping Station, Cooling Tower & Condensate Collection System.
- Prepared Package Document Lists, Piping Layouts, Isometrics & Support Drawings in line with Project Specifications & good Engineering Practices.
- Reviewed & Commented on Mechanical Design of Pipe Racks & UG Piping submitted by ‘Wuhuan Engineering Ltd, China’.
- Supervised Fabrication & Installation of Piping in IA/PA, Diesel Tank, NG Station, O/U Deaerator, Fire Water Pumping, Cooling Tower & Underground Pipeline Areas.
Engineering Reviews & Procurement
- Reviewed Design & Fabrication details of Pressure Vessels & Heat Exchangers in line with ASME BPVC Sec. VIII(Div.1) & TEMA. Coordinated with DESCON Manufacturing Ltd. & AZTECH Heat Exchangers Ltd. for resolution of technical queries during Fabrication.
- Carried out Technical Evaluation/Review of quotations received against Piping Material Requisitions and Special Piping items in-line with Project requirement & applicable International Codes & Standards.
- Carried out Technical clarification/negotiation with supplier of Piping Materials & Prepared Comparative Statement with final recommendation for management approval.
General Jobs
- Design & Coordination of Gas Turbine Ventilation Blower Project.
- Generate Welding Procedure Specification for mechanical/piping jobs against requests from maintenance teams of plants.
- Look after Design of Piping/Mechanical modification jobs proposed by Process Engineering Section after process reviews at Ammonia, Urea, NA & CAN plants.
February 2006
To September 2007
Assistant Manager Projects
at Azgard-9 Ltd.
Location :
Pakistan - Lahore
Garment Baking Oven Project
- Worked on the project to install the Baking oven as per vendor guidelines.
- Coordinated with shipping & construction teams to develop a plan for overall project.
- Assured quality & in-time completion through regular audits.
General Jobs
- Proposed Improvements in the system to nullify losses.
- Identify objectives of the project being proposed and present payback.
- Identify resources required for the Project.
- Suggested and acquired guidelines for way forward on critical issues by discussion with management.
- Develop scope of work & budget.
- Supervise & Control the project through audits to ensure quality and in‐time completion.
- Worked on the project to install the Baking oven as per vendor guidelines.
- Coordinated with shipping & construction teams to develop a plan for overall project.
- Assured quality & in-time completion through regular audits.
General Jobs
- Proposed Improvements in the system to nullify losses.
- Identify objectives of the project being proposed and present payback.
- Identify resources required for the Project.
- Suggested and acquired guidelines for way forward on critical issues by discussion with management.
- Develop scope of work & budget.
- Supervise & Control the project through audits to ensure quality and in‐time completion.