Studied & Reviewed of Process flow diagram (PFDs), Process & instrumentation diagram (P& IDs), Utility P & IDs, Auxiliary P & IDs, Interconnectivity ISBL-OSBL P & IDs and LDTs supplied by UOP & Bechtel.
Preparation of Pre-commissioning & Commissioning activities related Plan, Budget, SOP, Risk Assessment, and Checklist & Formats.
Studied & Reviewed GA drawings, Datasheet for Columns, Heat exchangers, Reactors, Heaters, Vessels, Fin Fans etc.
Studied & Reviewed Cause & Effect diagram for KHT & CNHT plant supplied by UOP & Bechtel.
Preparation of Operating Manual, Pocket manual, Start up SOP, Risk Assessment, Logbook & Log sheet for new modification.
Hydrotest piping Loops system - subsystem preparation & Validation of loops system - subsystem during various stage of erection: Isometric clearance, Hydrotest clearance, Flushing and Final boxed up clearance.
Conventional flushing of loops (Card board bursting, Air blowing, Steam blowing, Water flushing & Lube oil flushing).
Non-Conventional flushing of loops (Pigging, Rotomol cleaning & Hydrojetting) of lines & equipment.
Chemical cleaning & passivation of lines i.e. Cooling Water, Compressor suction lines & equipments i.e. Heat exchangers
Catalyst & chemical loading-Unloading of reactor (Sock Load & Dense load)(including UOP+ Albemarle+ Petroval).
During start-up followed step wise procedure for catalysts likes drying, Prewetting & Sulfiding etc…
Instrument & control loop checking & validation of loops.
Prepared Punch point for every loop & follow-up with the EPCC & Licensor.
Pre-startup safety review (PSSR) of system to make system ready for safe & sure commissioning.
Training of operators for normal and emergency procedures of commissioning & start up activities.
Planning and execution of various hot tie-ins & cold tie-ins in existing running units as per HSEF safety targets, procedures and practices.
more detail review my resume.
- Company industry:
- Oil & Gas
- Job role:
-
Engineering