• Worked on Planning and Design of Sewerage and Drainage System for “Lahore Road Rehabilitation Project Phase-II”, which included fifteen main roads of Lahore. The Scope of services included preparation of Detailed Design, Engineer’s Estimates, Tender Documents and Construction Drawings.
• Worked on Planning and Design of Sewerage, Drainage, and Water Supply System for “Multan Road Rehabilitation/gradation project”. The Scope of work includes the preparation of PC-I, Detailed Design, BOQ, Engineer’s Estimates, Tender Documents, Technical Specifications, and Construction Drawings. The length of the road is about 13 km and the cost of the project is Rs. 4 billion.
• Worked on the Planning and Design of Storm Water Drainage System of the “Lahore Ring Road Project - Northern Loop” having a length of about 50 km. The Scope of work includes preparation of PC-I, Detailed Design, BOQ, Engineer’s Estimates, Tender Drawings & Specifications, and Construction Drawings for all packages of the project.
• Worked on “Comprehensive Sewerage and Drainage Scheme for South Lahore”. Scope of services included preparation of Inception Report, Feasibility Report, Detail Design Report, Tender Documents, Technical Specification, and PC-I. The total cost of this project is Rs.30 billion.
• Worked on “Detailed Engineering Design for lying of Trunk Sewer along Cantonment Drain, Lahore”. The area of this project is about 22000 hectares, and the total cost of this project is Rs. 3 billion. Scope of services included preparation of Detailed Design, Engineer’s Estimates, Technical Specifications, and Tender Documents of the project.
• Worked on “Preparation of Comprehensive Sewerage & Drainage Scheme for Allama Iqbal Town & adjoining Areas, Lahore”. The Scope of services included the preparation of an Inception Report, Feasibility Report, Preliminary Design Report, Detailed Design Report, Engineer’s Estimate, Tender Documents, and PC-I. Responsible for planning and design of the project. The area of this project is about 12000 hectares, and the total cost of this project is Rs.1.8 billion.
• Worked on “Laying of Sewer along Allama Iqbal Road”. The length of the road is about 3.5 km and the cost of the project is Rs. 60 million. Responsible for planning, designing, and preparing the Engineer’s Estimate.
• Worked on “Restoration of Original Cross Section of 40 ft. of Sattukatla Drain from Ferozepur Road to PECO Road Bridge”. The Scope of services included Hydraulic Design of Rehabilitated Drain, Construction Drawings of Retaining Walls, Bridges, and PC-I.
• Worked on Planning and Design of Sewerage and Drainage System for “Lahore Road Rehabilitation Project Phase-II”, which included fifteen main roads of Lahore. The Scope of services included the preparation of Detailed Design, Engineer’s Estimates, Tender Documents, and Construction Drawings.
• Worked on “Vetting of design of proposals of 32 nos. Schemes for Reduction of Stagnation Period of Rain Water at Sore Points / Ponding areas in Lahore”. Responsible for vetting design proposals submitted by WASA.
• Worked on “Engineering Studies for Area Development scheme of LDA Mustafa Town, Lahore under Lahore Rehabilitation Project Phase-II Lahore”. Later on, this project was merged into the “Multan Road Rehabilitation/up-gradation project”.
• Worked on “Design and Rehabilitation of Drainage System of Flyover at Ghardi Shaho near UET, Lahore”. The scope of responsibilities includes the preparation of Tender Documents and Construction Drawings.
- Company industry:
- General Engineering Consultancy
- Job role:
-
Engineering