مجموع سنوات الخبرة :23 years, 8 أشهر

Planning & Scheduling Manager في AECOM
  • المملكة العربية السعودية - جدة
  • أشغل هذه الوظيفة منذ أكتوبر 2013

Project : Riyadh Metro Project "Lines 1 & 2" - Riyadh, KSA

- AECOM is the Lead Designer for two of the six lines of Saudi Arabia’s transformational new Riyadh Metro, the largest public transportation project in the world.
- AECOM will lead a design joint venture with The BACS Consortium which includes Bechtel, Almabani General Contractors, Consolidated Contractors Company, and Siemens, which is responsible for the Riyadh Metro, Lines 1 & 2 (Blue & Green) with estimated value (10 Billion USD) Design and Build for Lines 1 and 2 of the Metro’s 6-line system.
Line 1 has a total length of 38 Km and includes 26 stations, while Line 2 stretches at 25.3 Km and includes 16 stations.
- Project component : Tunnels, Viaducts, Stations (Elevated, At-Grade, Deep Underground, Shallow underground, Transfer and Stations Signature Canopies), Emergency Egress Shafts, Roadway Re-Develop, Park & Ride Buildings and Train Maintenance Depots.

- Responsibility : assist the Project Controls Manager for Project Controls, Planning and scheduling issues .
- Preparing the Project Detailed Design Schedule with all levels to monitor the progress (actual Vs planned) and to ensure the project milestones are met.
- Preparing Monthly Time Schedule reports and Contributing in preparation of Monthly and weekly executive reports.
- Developing and implementing scheduling systems and standards for the project including progress measurement and reporting.
- Establishing and maintaining the WBS, activity, coding and resource libraries for the project.
- Coordinating troubleshooting of interface issues with other consultant and contractor time schedules.
- Directly responsible for updating of the master schedule for all Projects using the tool Primavera P6.
- Monitoring and Control the Progress of work to be adhered to planned schedules and achieving the project milestone dates.
- Analyzing basic project planning and schedule updates and delays.
- Resource allocation.
- Prepare Man-hours / Deliverables planned histogram.
- Cost Loading, Prepare Cash Flow / S-Curve
- Attended the Progress Meetings with BACS for discuss and resolve a Planning Issues for smooth execution of the project

Planning Manager (Acting) Deputy Project Controls Manager في AECOM
  • المملكة العربية السعودية - جدة
  • يونيو 2013 إلى أكتوبر 2013

Project : Tatweer Buildings Company (TBC) Schools Program - Riyadh, KSA

The program involves projects in all of the Kingdom’s 13 provinces and includes primary and secondary educational facilities, the majority of which will be new construction.

AECOM provide consultancy services to Tatweer Buildings Company to help develop and manage the delivery of 2, 100 educational facilities throughout the Kingdom of Saudi Arabia.

Responsibility :

• Assist Programs Controls Manager for Project Controls, Planning and scheduling issues.

• Prepare Program Master Time Schedules for planning, design, pre-construction and construction phases; establish and maintain scheduling systems and procedures for the Program.
• Preparing and maintaining an updated Program Master Time Schedule working with Senior Program Controls Manager.

• Preparing Monthly Time Schedule reports.

• Developing and implementing scheduling systems and standards for the Program including progress measurement and reporting.

• Administration of Primavera P6 software in Program environment.

• Establishing and maintaining the EPS, WBS, activity coding and resource libraries for the Program.

• Establishing and updating Master Program Schedule.

• Providing technical scheduling support and coordinates training needs for schedulers.

• Coordinating Program wide scheduling practices on Projects.

• Ensuring that planning and scheduling documents such as project master schedules, progress reports and S-curves are prepared properly and in accordance with contractual time schedules and frequencies by project schedulers.

• Coordinating troubleshooting of interface issues with other consultant and contractor schedules.

• Contributing in preparation of Monthly and weekly executive reports.

• Coordinating with logistics manager and project teams on program wide logistics information and infrastructure interfaces especially on schedule requirements.

• Analyzing basic project planning and schedule updates and delays.

• Preparing cost load schedules

• Analyzing of project planning and schedule updates and delays.

• Establishing standards for evaluation of designers’ and contractors’ detailed schedules.

• Contributing in development of Earned Value reports.

• Assisting and providing guidance to schedulers in analysis of extension of time claims

• Implementing and following the Company Quality Management System procedures.

Project Control & Planning Specialist (Acting) Planning Manager في AECOM
  • المملكة العربية السعودية - جدة
  • يونيو 2012 إلى يونيو 2013

Project : Knowledge Economic City (KEC) - Jeddah, KSA

Major Urban Development Program located inside the boundary of the Holy city of Madinah. With Estimated Value more than (12 Billion USD), 4.8 Million m2 Land Area, 8 Million m2 Total Build up Area.
And will become a Major Islamic Knowledge, Learning and Research Centre including information management, bio-medical research and genetic engineering. Islamic researchers, scientists, students and entrepreneurs from across the Islamic world are expected to come to live and work in this new city.


Area of Experiences : Infrastructure, Landscaping, Power Substations, Residential Buildings, Retail Malls, Mass Transit System, Theme Park, Knowledge Business Park, Schools, Commercial Buildings, Hospitals & Health Centers, Community Facilities, Public Facilities, Data Centers.

Responsibilities:

• Provide Support to Management teams in Integrated Project Planning and schedule development utilizing Primavera P6.

• Responsible for interfacing with Senior Management and the development of Project Status Reports, demonstrating confidence levels for live projects meeting planned schedule and cost commitments.

• Preparation of Design, Tender, Award, Procurement, Construction, and Completion scheduling, including the evaluation of progress, recommending corrective actions for all disciplines, and update status reports in various formats.

• Assists the Program Control Systems Manager to coordinate with Project Managers and project engineers to ensure correct implementation of project scheduling procedures and requirements.

• Reviews and closely monitors Master Development Schedule and Contractor / Consultant schedules

• Preparation and Development of Business Plan Master Schedules with Cost loading to produce the Forecast Budget S-Curve as a Strategic high level cost advice for business case .

• Define milestones for inclusion in Request for Proposals and Tender documents through detailed discussions with the Program Management Teams,

• Define interfaces between buildings/infrastructure and Construction/Operations.

• Evaluate claims and make recommendations.

• Prepare all levels of project schedules, monitor progress (actual Vs planned) and ensure project milestones are met.

• Prepare reports to management and highlight slippages and make recovery plans.

• Participate in coordination meetings as required.

• Collect information that required initiating and updating PCS records from the stakeholders.

• Directly responsible for updating of the master schedule for all Projects using the tool Primavera P6. Maintain control of a wide variety of projects running concurrently.

• Directly responsible for the preparation of the monthly schedule portion of the PCS report, including narrative and all scheduling update reports.

• Assist with tender evaluations to determine that the contractors’ schedules meet overall project time requirements.

• Responsible for reviewing / updating the KEC Scheduling Manual.

• Assists the Program Control Systems Manager for preparing and updating of Monthly and Bi-monthly reports for all approved projects.

• Assists the Program Control Systems Manager for preparing RAID report (Risks, Assumptions, Issues and Dependencies).

• Assists the Program Control Systems Manager to ensure that Risk Registers are maintained for all projects and mitigation plans are considered during both the design and construction of projects.

• Assists the Program Control Systems Manager for Pre-tender and Post tender execution in accord with KEC Procurement process.

Senior Planning Team Leader في Davis Langdon An AECOM Company (c/o TMPM)
  • المملكة العربية السعودية - جدة
  • نوفمبر 2011 إلى يونيو 2012

Project : Jabal Omar Development Project (JODP) - Makkah, KSA \nDesign and Built Project Phase-I in Makkah, Centralized Haram Zone. With Estimated Value (3.2 Billion S.R). \nThe Project Phase-I Consists Mainly from 4 Zones/10 High Rise Hotel. Every Zone consists from 10 Podium Floors (Commercial, Utilities, Parking, Main Kitchens, etc..) in addition to International Hotel (20 Floors) . Under Four International Operators (Hilton, HYATT, CONRAD & MARRIOT) . \n \nArea of Experiences : High Rise - Residential and Commercial \n \nResponsibilities: \n• Provide Planning Sub - Consultancy Service for the Main Contractor NESMA, \nI am Responsible for Engineering Scheduling & Cost Control Section (SCC) of Project Control Department, Establishing Project's Baseline Master Plan, and develop a detailed schedules using Primavera Project Planner \n \n• Create the Project Plans and Provide work direction as required in the preparation of planning, scheduling, control systems for Planning Team. \n \n• Provide staffing guidance to Engineering in the areas of planning and scheduling by analyzing and evaluating all relevant data. \n \n• Provide staffing guidance to Document Control Dept. in the areas of PCM (Primavera Contract Manager) by adding some Development and Procedure for Activation of the Data Base System. \n \n• Monitoring and Control the Progress of work to be adhered to planned schedules and achieving the project milestone dates. \n \n• Updating Project's Schedules and preparing Recovery Schedules when needed. \n \n• Weekly alarming and Progress Observation, Monitoring and follow up for Project Design Stage . \n \n• Attended Design & Planning Meetings with client (JODC, HILL, K&A) to discuss and resolve the Engineering Planning Issues. \n \n• Produced Weekly and Monthly Progress Reports. \n \n• Resource allocation \n \n• Prepare S-Curve

Senior Planning Team Leader في Saudi BinLadin Group (ABCD)
  • المملكة العربية السعودية - جدة
  • ديسمبر 2007 إلى نوفمبر 2011

Saudi BinLadin Group (ABCD), Head Office - Jeddah, KSA \n \nResponsible for a fully Integrated P6 Resourced Schedule to support the Engineering, procurement and construction of services for Platform Design & Build Program \n \nThird Project \n \n03. Aug. 2010 - Nov. 2011 \nSaudi BinLadin Group (ABCD), Head Office - Jeddah, KSA \n \nPosition : Senior Planning Team Leader - Project Control Department \n \nProject : Ministry Of interior, Correctional Facilities (MOI-CF) \nDesign and Built Project (Redesigned with Value Engineering Restrictions) with Estimated Value (5.2 Billion S.R), Distributed on Four Sites Riyadh, Jeddah, Taif and Dammam. \n \nArea of Experiences : Prison Cells, Visitation & Supporting Buildings in addition to various Service Buildings (Clinic, School, Mosque, workshops, warehouses, Training Center, Civil Defense Fire Station, etc..) with all related Infrastructure & Utilities Buildings. \n \nResponsibilities: \n \n• Responsible for Planning & Scheduling section of Project Control Department, Establishing Project's Baseline Master Plan, and develop a detailed schedules using Primavera Project Planner . \n \n• Create the Project Plans and Provide work direction as required in the preparation of planning, scheduling, control systems for Planning Team. \n \n• Provide staffing guidance to Engineering, Procurement and Construction supervisors in the areas of planning and scheduling by analyzing and evaluating all relevant data. \n \n• Monitoring and Control the Progress of work to be adhered to planned schedules and achieving the project milestone dates. \n \n• Updating Project's Schedules and preparing Recovery Schedules when needed. \n \n• Weekly alarming and Progress Observation, Monitoring and follow up for Project Different Stages (Design, Procurements and Construction). \n \n• Monitoring and Follow Up for Updated Project Schedule and Monthly Look Ahead to cover all Construction Requirements, Focus on a filters of needed activities (Drawings, Materials, etc..) coordinated with Concerned Department. \n \n• Attended Progress Meetings with client and consultant to discuss and resolve a Planning Issues for smooth execution of the project. \n \n• Produced Client / Consultant Weekly and Monthly Progress Reports. \n \n• Cost Breakdown & Resource allocation \n \n• Prepare Cash Flow & S-Curve \n \n \n \n \n \n \n \nSee Next Page for SBG-ABCD 2nd & 1st Projects …….. \nSecond Project \n \n02. June 2008 - June 2011 - Overlapped with 3rd Project (MOICF) \nSaudi BinLadin Group (ABCD), Head Office - Jeddah, KSA \n \nPosition : Senior Planning Engineer - Technical Support \n \nProject : King Saud Bin Abdul-Aziz University for Health & Science (KSAUHS) \nDesign and Built Project with Estimated Value (14 Billion S.R), Distributed on Four Sites Riyadh, Jeddah, AlHasa and AlMadinah, In addition to Claims & VO’s with approximate Value (3 Billion S.R) . \n \nArea of Experiences : Educational/Academic Buildings, Medical, Hospitals & Health Centers, Administration Buildings, Deanship, , Str. Parking’s, Sports & Recreation, Housing (Residential 200 Villas, 26 Town houses, 8 Suites Bldgs., 25 Apartment Bldgs)., Mosques, Service/utilities buildings, Hospital 560 Bed (LEED Certified), Research Building (LEED Gold), Clinical Skills and Central Labs + Infrastructure. \n \nResponsibilities: \nSee My CV \n \n \nFirst Project \n \n01. Dec. 2007 - Dec. 2008 - Overlapped with 2nd Project (KSAUHS) \nSaudi BinLadin Group (ABCD), Head Office - Jeddah, KSA \n \nPosition : Senior Planning Engineer - Technical Support \n \nProject : Ministry Of interior, Central Security Buildings (MOI-Phase II) \n \nArea of Experiences : Administration Buildings, visitors, military purposes, operations area, soldier accommodation, mosque, service area, workshops, warehouses, training areas and football field. \n \nResponsibilities: \nSee My CV

Technical Office Manager في United Business Enterprise Company
  • المملكة العربية السعودية - جدة
  • ديسمبر 2005 إلى ديسمبر 2007

Projects : \n Safwat Al-Khalideah Compound - Consists of 28 Villas with Skeleton Estimated Value (8 Million S.R) \n Shinkar Private Palace - Consists of Main Villa and Annexes, Project Estimated Value (4 Million S.R) \n \n \nArea of Experiences : Housing \n \nResponsibilities: \n \n• Attended site Progress Meetings with client and consultant to discuss and resolve a technical Construction problems arising at site for smooth execution of the project. \n \n• Monitoring and Control the Progress of work to be adhered to planned schedules and achieving the project milestone dates. \n \n• Responsible for the project documentations to be kept current at all times and accurate records are maintained with regard to submittal reviews. \n \n• Produce & Check monthly payment certificates. \n \n• Supervise and manage the construction Team to monitor construction work as per budget. \n \n• Manage manpower, Subcontractors and equipments for the particular work activity. \n \n• Check Design drawings and produce needed Details for construction. \n \n• Review construction drawings & material submittals and get Consultant Approval for use at site.

Planning & Scheduling Engineer في El-Safa for General Contracting
  • مصر - القاهرة
  • أغسطس 2005 إلى نوفمبر 2007

Projects : \n Cultural Civilization Center (6 October) - Project Estimated Value (30 Million L.E) \n Professional Training Center (Com Oshim) - Project Estimated Value (12 Million L.E) \n Sohage Museum of Antiquities (Sohage) - Project Estimated Value (8 Million L.E) \n Organization of Supervision administrative (Nasr City) - Project Estimated Value (6 Million L.E) \n \n \nArea of Experiences : Public & Governmental Buildings \n \nResponsibilities: \n \n• Responsible for Planning & Scheduling section of Project Control Department, Establishing Project's Baseline Master Plan, and develop a detailed construction schedule using Primavera Project Planner \n \n• Cost Breakdown & Resource allocation \n \n• Prepare Cash Flow & S-Curve \n \n• Updating Project's Plan and preparing Recovery Schedules when needed.

Civil Engineer في Bin Jubair Engineering Consultant Office
  • المملكة العربية السعودية - مكة المكرمة
  • أكتوبر 2003 إلى يوليو 2005

Projects : Numerous Projects Including Residential, Commercial and High rise Buildings . \n \nArea of Experiences : Residential, Commercial and High rise Buildings \n \nResponsibilities: \n \n• Produced Structural Design Drawings for Numerous Projects. \n \n• Design Review for Arch. & Structural drawings and coordinate with all Remaining Trades. \n \n• Supervised Construction site work (Skeleton) \n \n• Site Investigation and Survey for Numerous Projects \n \n• Produce Technical Reports upon Site Observation for a lot of Existing Buildings.

Technical Office Engineer في Bahadur Association for Construction & Maintenance
  • المملكة العربية السعودية - الطائف
  • سبتمبر 2001 إلى أغسطس 2003

Project : Bahadur Plaza Resort \nThe Project Estimated Value (80 Million S.R), Consists of Five Star Hotel, Commercial Center, Recreational Club, Swimming Pools, Restaurants and uncovered Landscape include Entertaining area . \n \nArea of Experiences : Residential and Commercial - Hotels \n \nResponsibilities: \n \n• Check Design Drawings and produce needed Details for construction. \n \n• Produce Shop Drawings and as built Drawings. \n \n• Quantity Survey for work activities. \n \n• Produce & Check monthly payment certificates for assigned Sub-Contractors. \n \n• Supervised Construction site work (Skeleton & Finishing)

Planning & Scheduling Engineer في Construction Consultants' Group ( CCG ) Office
  • مصر - القاهرة
  • أغسطس 2000 إلى أغسطس 2001

Project : Egyptian Red Crescent Association \nThe Project Estimated Value (13 Million S.R), The CCG was a consultant office and a sub contractor for Planning and administrating the contract for Arab Contractors' Company in the aforementioned project. \nMy Duties Direct Supervised by a Prof. Dr. Ismail Basha-Head of Construction Management Department, faculty of Engineering, Zagazig University, Egypt. \n \nArea of Experiences : Public & Governmental Buildings \n \nResponsibilities: \n \n• Responsible for Planning & Scheduling Work \n \n• Updating Project Time Schedule and preparing Recovery Schedules when needed. \n \n• Produced Client / Consultant Weekly and Monthly Progress Reports Include, \n(Histograms-Manpower-Progress-Photos- Cash flow-etc.. ) \n \n• Cost Breakdown & Resource Requirements allocation \n \n• Prepare Cash Flow & S-Curv

Planning & Scheduling Engineer في Arab Contractors Company (A.C.C.) - Osman Ahmed Osman
  • مصر - القاهرة
  • يوليو 2000 إلى أغسطس 2001

Project : Roads Administration Head Office \n \nArea of Experiences : Roads, Airports, Tunnels & infrastructures Sector \n \nResponsibilities: \n \n• Responsible for Planning & Scheduling Work \n \n• Prepare needed Schedules and Coordinate weekly Technical Workshops for Senior Engineers in all Roads Administration Sectors and Regions . \n \n• Produce a series of Technical Manuals (Monthly published) about Paving Technology, Design Mix and Paving Construction Problems avoidance, etc.., Which Distributed for Senior Engineers in all Roads Administration Sectors and Regions. \n \n• Manage and Organize for a workshop about New Paver Technology Software Program, a workshop Parties are : US army Engineering Service, Arab Contractors and Zagazig University. Instructor is a Prof. Dr. Yahiya Shahin from US-Army Engineering Service .

الخلفية التعليمية

بكالوريوس, B.Sc in Civil Engineering
  • في Zagazig University
  • مايو 2000

B.Sc in Civil Engineering from Zagazig University, Egypt, May 2000.
Construction Engineering & Management Department
Graduation Project: Construction Methods & Comprehensive Management study for “New Zifta Lock, Awarded Excellent Grade for Graduation Project, May 2000.

Specialties & Skills

Schedules
Cost Management
Project Management
Construction Management
Primavera P6
Autocad
Training
Microsoft Office
Primavera P6

اللغات

العربية
متمرّس
الانجليزية
متمرّس

العضويات

Egyptian Engineers' Syndicate - Egypt, ID (01614/23)
  • Member
  • June 2000
Project Management Institute - USA, ID (1668784)
  • Member
  • May 2010
Society of Construction Law - UK, ID (6809)
  • Member
  • December 2011

التدريب و الشهادات

PMP Preparation (Project Management Professional) (الشهادة)
تاريخ الدورة:
April 2010
صالحة لغاية:
April 2010

الهوايات

  • Negotiation Skills
    Negotiation Skills