testing and commissioning
cepco
Total years of experience :9 years, 11 Months
Testing of cables (HV-MV-LV)-
Hi pot test-
Partial discharge and Tan Delta test-
Cable fault location-
Joint and termination-
PD Test cables (Maritime yard- Dammam) For SSEM project.
Hipot Test cables ( GCC Lab - Dammam and Sea port Jeddah).
Hipot Test cables of substations for the Saudi Electricity Company (Transformer- Capacitor Auxiliary transformer).
maintenance for cables testing equipment-
calibration for testing equipment as per the international standards
Equipping and maintenance the test cars of the Saudi-
.Electricity Company
.training clients on the use of testing equipment-
construction for low voltage system and manufacturing low voltage panels.
read diagrams-
follow up with production-
prepare technical inquiries-
solving problems technical-
certified assistant in electronic engineering (Diploma)2014 control system. programmable automatic control PLC . processor programming. electric machines and measurements. power electronics.