Engineer at Hitachi Zosen Corporation
  • Qatar
  • April 2016 to March 2018

E & I Project: Umm Al Houl IWPP, Desalination Plant -Qatar
Client : Umm Al Houl Power “IWPP” -Desalination Plant PMC : Mott Mac Donald, Qatar

Project Manager at Fajar Al-Khaleej Trading & Cont. Co
  • Qatar
  • March 2015 to April 2016

MEP Project: Warehouse & Offices - Ras Laffan
Client : Petrotec PMC: Qatar Design Consortium

Engineer at Tozzi Qatar
  • Qatar
  • October 2013 to February 2015

E & I Project: Polysilicon Plant - Ras Laffan
Client : Qatar Foundation PMC: QSTec Qatar Solar Technology

Senior Electrical Engineer at Sinohyrdo Corporation
  • Qatar
  • December 2012 to September 2013

Doha North Sewerage Treatment Plant
Client : Ashgal - Infrastructure Affairs PMC : Keppel Seghers Engineering Singapore Pte. Ltd.

QA/QC Manager at Sepam Qatar WLL
  • Qatar
  • January 2010 to May 2011

NDIA PMC: OBI “Bethel Oversea International" M. Cont.: CDC - Takenaka Joint Venture

Electrical Engineer at Qatar Aluminum “Qatalum Ltd.” PMC
  • May 2009 to January 2010

Responsible for field implementation, inspection and supervision for Electrical & Instrumentation Works for Qatar Aluminum Project and its related Facilities and Utilities. In Reduction Area - 14 Pot room Tending Machines, 3 Anode Jacking Frames, 3 Transfer Gantry System, 1 cathode Removal Crane and 20, 000 Anode Clamps plus corresponding J-Hooks. Paste plant. Anode baking plant. Plant wide Utilities - Electrical distribution, air, fuel gas, seawater, potable and process water and waste water. Harbor facilities - ship unloaders, alumina and coke bulk storage, handling and truck loading systems and pitch transport.
Ensure work is carried out competently and effectively, within time and budget constraints and that project objectives are satisfied. Participate in the management of reliability and integrity of the complex by working with the multi-disciplinary area integrity and reliability management team. Facilitate and develop a productive and cohesive team. Maintain and facilitate an awareness of HS&E across the discipline within assigned project.

Quality Management at PIC- Petrochemical Industries Company and PMC: Bechtel International
  • October 2008 to May 2009

Company’s

QAQC Inspector at TECHNIP Italy S.p.A
  • February 2005 to September 2007

68 00148 Roma, Italy, Tel. (+39) 06 65981
Position :

Construction Manager at Dehdari General Trading & Construction Company
  • Kuwait
  • January 2003 to February 2005

Electrical
Projects : Ali Al-Salem Airbase, Al-Jaber Airbase and Camp Bhuering New & Upgrading Projects
: Upgrading of Airbase Airfield Lighting System at Ali Al-Salem & Al-Jaber Airbase.
: Construction of new Medium Airfield Airbase Lighting System at Camp Bhuering.
: Upgrading of 11KV Distribution & Base Communication System at Ali Al-Salem & Al-Jaber Airbase.
: Various HVAC, Power and Telecommunication Projects in Kuwait US Military Camps and Sites

Project Manager at GLACT Mobile Network, Inc
  • May 2000 to April 2001

Electrical & Telecommunication
Project : Globe GSM Project, Viking-3, Phase-7, SWEsites
: ISLACOM GSM Roll-out Project, Base Transmission Stations and Cell sites

Construction Manager at SPARK Electro-Mechanical Services Company
  • May 1998 to May 2000

Electrical
Projects : Carbon Dioxide “CO2” Plant, Cebu 70.6MW Power Plant, Kanlaon Mineral Water Plant
Globe GSM Project Viking-3 and Phase-6, SWEsite

Head at Telephone System & Fiber Optics O/H & U/G Lines
  • August 1995 to January 1998

as

Construction Superintendent at Saudi Consolidated Electric Company “SCECO EAST
  • Saudi Arabia
  • December 1992 to December 1995

HV/LV - O/H & U/G Lines
Projects : Construction of Thousand kilometers of Primary and Secondary Underground Distribution system.
: Construction of Power Plants, HV / MV Substations. Outdoor and Indoor Substations and switchyard facilities.
: Installation of Pole Mounted Transformers, Capacitors, Voltages Regulators, Air Break Switches, HV Switches.
: Construction of hundreds of Primary and Secondary power supplies to Industries, Commercials & Residential
: Conversion and standardization of primary voltage to 13.8KV, 3 - Phase, 60Hz.
: Upgrading & Modification of existing power system to meet additional load requirements.

Maintenance Engineer at Saudi Services & Operating Company, Ltd. “SSOC
  • Saudi Arabia
  • May 1987 to December 1992

Gas Turbine Power Plant
P. Plant Maintained: Faras Gas Turbine Power Plant & Uthmania Gas Turbine Power Plant

Design Engineer at Dhahran International Airport & King Abdul Aziz Airbase
  • July 1982 to July 1986

planning, feasibility study, design, cost estimates and Bid Documents. Pre-qualification of documents, setting tender strategies and ensuring sufficient resources are available to complete the tenders and negotiating contract terms.
•Design electrical engineering calculations as follows: total connected load, demand and net computed load in order to get the correct size and rating of wires and cable, conduit, pipes and fittings, cable trays, hanger and support, cable ducts, trenches and hand hole, lighting illumination level, voltage drop, short-circuit, and grounding resistance. Design interior and exterior electrical layout of vertical, horizontal and high-rise buildings. Power and lighting layout. Grounding layout and lightning protection. Auxiliaries such as, intercom and paging layout, telephone layout, CCTV /CATV layout FACP. Design power and lighting layout for sports facilities, perimeter and security lighting layout, airbase and airfield lighting layout, emergency and standby generator, storage batteries, uninterruptible power supply "UPS' and emergency lighting system. Compute the size and rating of wall switches and outlets, safety switch, transfer switch, fuses, breakers, panel distribution board, switchgears and parameters, motor control centers, magnetic starter, heater, capacitor, transformer, standby generator, voltage regulator, lightning arrester, cutout fuse, conductors, poles and hardware's. Preparation of electrical working drawing, sketches & detail for construction as follows: Lighting layout, Power layout, grounding layout, Auxiliary layout, Single, schematic and wiring diagram, Schedule of load and computation.

Project Engineer at Surigao Consolidated Mining Company “SURICON
  • June 1980 to June 1982

for construction implementation, supervision & maintenance of the whole mining plant & related building facilities.
•Mine Electrical: Construction and installation 4160Volts overhead distribution lines, substation, transformer, breakers, switches, panel boards, motor controls, power and lighting, deep well pumps, submersible pumps, booster pumps, water pumps & motors.
Mill Electrical: Installation of all devices, machine and equipment such as ball mill, jaw crusher, drum scrubber, secondary and tertiary crusher pumps, motor and control, power and lighting, grounding and lightning protection, medium and low voltage switchgear, power plant - 2-950KW caterpillar generator, 69KV substation & O/H Lines. Plant Building Facilities: Mill plant building, power plant, assay laboratory, administration building, warehouse, motor pool, guest house, Jr. & Sr. staff houses, 41-units rank-in-file duplex housing church, hospital and sports facilities. Planning and scheduling; interpretation and modification of plan; materials take-off and cost estimate; expedite, monitor and request materials, tools, equipment and manpower; testing, commissioning and preparation of as-built drawing Construction highlights and reports.

Construction Engineer at Engineering & Construction Corporation of Asi
  • Philippines
  • April 1980 to May 1980

of Project Design Package as per Ecco-Asia Engineering & Construction Standards from planning, feasibility studies, materials take-off, cost estimates, man-hours, equipment hours, scope of work, preparation of working drawings, sketches and details.
•Project monitoring and scheduling. Interpretation of plans and modification.
•Study and review approved plans, specification and contract for construction.
•Expediting requisition and purchasing of materials, tools, equipment and manpower.
•Project supervision and inspection of actual electro-mechanical works as per approved construction drawing, specification and accepted engineering standards.
•Rectify any changes and revision of plan. Resolve any problems that may arise.
•Testing & Commissioning. Construction highlights and report.

Education

Bachelor's degree, Electrical And Mechanical Engineering
  • at Feati University
  • April 1976

Desalination Plant, Polysilicon Plant, Ethylene Plant, Aromatic Complex, Airport/Airbase Project, Infrastructure and Utility Company Projects.

Specialties & Skills

Site Supervision
Construction & Property
Engineering
BUDGETING
CABLING
CUSTOMER RELATIONS
CUSTOMER SATISFACTION
ELECTRICAL ENGINEERING
FRAMING
GRAPHIC DESIGN
LAYOUT DESIGN

Languages

English
Expert

Memberships

IIEE SQC
  • Electrical Field
  • June 2018

Training and Certifications

Technical Seminars (Certificate)