Work Experience

Total years of experience :5 years, 0 Months

quantity surveyor at Qatar Speed House
  • Qatar - Doha
  • December 2021 to January 2024

In Post-contract:

* Evaluation of monthly interim payment certificates.
* Sub-Contractors nomination including PC rate, PS and Special. Proposals (ERP Systems).
* Evaluation of variation; negotiation and agreement of any dispute in variation
* Preparation of monthly financial statement and cash flow projections for client review.
* Review, negotiate & the contractors contractual claims.
* Preparing variation orders and payment certificates.
* Preparing monthly progress report, ensure monthly valuations & variations.
* Prepare & submit the cost comparison for new items, site measurement.
* Preparation of Confirmation of Verbal Instruction.
* Preparation of Request for Information.
* Preparation of Confirmation of Verbal Instruction.
* Maintaining VO Tracker, CVI Tracker, RFI Tracker, AVI Tracker & EI Tracker.

In Pre-contract:

* Preparation of Tender documents, including commercial and technical submission.
* Compiling Tender documents including commercial and technical submission.
* Preparation of Bill of Quantities, Bill of Items and Schedule of Rates based on the Client's requirements.
* Preparation of pre-tender cost estimation based on past projects and Suppliers' quotations.
* Checking the Contractors' tender queries, prepare the response of tender queries, coordination with design departments, Project Managers and prepare the tender circulars during tender stage.
* Examine and analyze the Contractors' technical and financial submissions.
* Prepare the post tender clarification letters, review post tender correspondence sends by the
Contractors'.
* Prepare the technical and financial evaluation reports to assist in the selection of Contractors'.
* Take off quantities for civil, mechanical, electrical and plumbing (MEP) & Interior fit outs works by using Auto CAD drawings, tabulating, analyzing and formulating the information to facilitate the preparation of measurement sheets in MS-Excel.
* Preparation of tender documents, RFP & RFQ, tender analysis and reporting, compilation of contract documents.

quantity surveyor at Hyundai Enginnering & Construction CO.Ltd
  • Sri Lanka - Colombo 2
  • December 2020 to November 2021

• Evaluation of monthly interim payment certificates.
• Sub-Contractors nomination including PC rate, PS and Special Proposals (ERP System).
• Preparing variation orders and payment certificates.
• Evaluation of variation; negotiation and agreement of any dispute in variation.
• Preparing monthly progress report, ensure monthly valuations & variations.
• Preparation of monthly financial statement and cash flow projections for client review.
• Review, negotiate & the contractor’s contractual claims.
• Preparation of Request for Information.
• Prepare & submit the cost comparison for new items, site measurement.
• Preparation of Confirmation of verbal instruction.

quantity surveyor at Central Enginnering Consultancy Bureau
  • Sri Lanka - Dehiwala-Mount Lavinia
  • March 2020 to October 2020

• Preparation of bar schedules, Daily site reports.
• Checking of Interim payment certificates, Final bills.
• Involved in tests such as Cube casting, Slump test, Pressure tests, Pond tests.
• Taking off join measurements.
• Attended to construction supervision works & Documentation works.

quantity surveyor at Access Engineering PLC
  • Sri Lanka - Colombo 14
  • December 2018 to January 2020

• Evaluation of monthly interim payment certificates.
• Sub-Contractors nomination including PC rate, PS and Special Proposals (ERP Systems)
• Evaluation of variation; negotiation and agreement of any dispute in variation
• Preparation of monthly financial statement and cash flow projections for client review
• Review, negotiate & the contractors contractual claims
• Preparation of cost report according to the monthly progress payments.
• Monitoring for support document for claim (COVID 19 direct and indirect effect)
• Preparation of monthly material requirement
• Lead in the preparation of IPA and variation orders. (FIDIC 1999)
• Monitoring for supporting staff’s measurement
• Preparation of reports (Sub agreement, progress report, progress presentation)
• Taking off quantities from CAD drawings.
• Preparation of tender document.

Education

Higher diploma, Quantity Surveying
  • at University of Vocational Technology
  • May 2021

Research on ‘’Construction Waste Material”

Specialties & Skills

Communications
Teamwork
Technical Skills
Time Management
Construction Management
MS Excel
Autocad
Planswift
MS Office
MS Project

Social Profiles

Personal Website
Personal Website

URL removed due to policy violation. Please contact support for further information.

Languages

English
Native Speaker
Arabic
Beginner
Tamil
Native Speaker

Memberships

Saudi Council of Engineers
  • Quantity Surveyor
  • May 2024

Training and Certifications

HSE Program (Training)
Training Institute:
Hyundai Enginnering & Construction
Date Attended:
January 2021
Duration:
60 hours
Contract Administration (Certificate)
Date Attended:
June 2019

Hobbies

  • Writing Story Book