Develop and determine all standards to perform inspection and test on all producers and oversee
all testing methods, and maintain high standards of quality for all processes.
review quality of all materials at site and ensure compliance to all project specification and quality
and collaborate with department for all material procurement and maintain quality of material
Inspection and assuring quality of construction work in site including (42 story towers with crane
and self-climbing formwork, flat slab with coupler RFT)
Inspection and assuring quality of finishing work in site including (42 story towers with block work,
plaster work, Ceramic, curtain wall, wood works, false ceiling, marble, Epoxy, painting, France
metal, Graviato, glass handrail, ACP, Louver, Land mark, Landscape)
Supervise effective implementation of all test and inspection schedule and ensure adherence to all
products and coordinate with various teams to perform quality audits on processes.
Assist with engineers and inspectors to ensure knowledge of all quality standard and ensure
compliance to all quality manual and procedures and collaborate with contractors and suppliers to
maintain quality of all system.
prepare ITP and Method Statement for works.
Develop and determine all standards to perform inspection and test on all producers and oversee
all testing methods, and maintain high standards of quality for all processes.
review quality of all materials at site and ensure compliance to all project specification and quality
and collaborate with department for all material procurement and maintain quality of material
Inspection and assuring quality of construction work in site. including ( 260 Villa & Rough Grading
Work )
Inspection and assuring quality of construction and finishing work in site including (260 Villa with
block works, Isolation works, plaster works, Ceramic, Aluminum works, wood works, false ceiling,
marble, painting, Graviato, Landscape)
Supervise effective implementation of all test and inspection schedule and ensure adherence to all
products and coordinate with various teams to perform quality audits on processes.
Assist with engineers and inspectors to ensure knowledge of all quality standard and ensure
compliance to all quality manual and procedures and collaborate with contractors and suppliers to
maintain quality of all system.
prepare ITP and Method Statement for works.
Supervising on contractors who implement the towers, oversee design and construction aspects of assigned
civil projects, involve in ground work and review of A&E and statement of work, execute the work as field
engineer projects, communicate and liaise effectively with colleagues and architects, subcontractors,
contracting civil engineers, consultants, co-workers and client, think both creatively and logically to re-solve
design and development problems, compile, check and approve reports, ensure that a project runs smoothly
and that the structure is completed on time and within budget.
o North Edge Towers (Alamein) High Rise Building with 44 floors on 4200 m2 for towers, 38000m2
podium and entertainment area on 30000m2 .
o Using bored piles, isolated footing and raft for foundations
o Using PVC for insulation and tested by air pressure and holiday device, geotextile before and after
casting concrete to keep the insulation save
o Using Couplers to connect steel together.
o Using post tension for slabs.
o For formwork using self-climbing system and crane-climbing
o Making tanks in mechanical floor at 17th and swimming pool then insulation and injection to make
sure that water cannot through.
Day to day management of the site, including supervising and
monitoring the site labour force and the work of any subcontractors.
Setting out sites and organizing facilities.
Execution of project works according to drawing and ensure quality standard and consultant’s
instructions.
Liaising with any consultants, subcontractor, supervisors, planners, quantity surveyors and the general
workforce involved in the project.
Acting as the main technical adviser on site for subcontractor, crafts people and operatives.
Execution of shopdrawing for concrete works, Infrastructure and coordinate between civil and
mechanical works, which used in the following projects:
o Sewage station in the first district of the 6 October City.
o Sewage station in the Seventh of 6 October City .
o Sewage station (A)& (B) in Borg ElArab City.
Implementation lines of heavy fixed cranes, repairing the ship repair ponds, design steel buildings and
Supervising on contractors who implement the roads in Shipyard Company for the following projects:
o Steel Buildings Project in Shipyard Company, Alexandria, Egypt. This project includes the construction
of steel stores for French forkata.
o Development of roads & drainage networks in Shipyard Company, Alexandria, Egypt. Development the
entrance of the gate and the road of the ships repair ponds through establishment a network of
concrete roads and implement the fire-fighting network around the ponds in addition to supply of
drainage networks from the low level to the high level through lift room.
Included Coordinating with the surveyor and receiving the excavation, reclamation and leveling work according to the
design panels and the laying of the base layers (base and sub-base), preparing to paving of the asphalt layers and the
work of side barriers in the road for the following projects:
o Development of Naval Base (Ras El-Teen), Alexandria, Egypt. Improving the efficiency of drainage networks,
paving roads and developing the airfield at the Naval Base) Ras El-Teen).
o Regional Ring Road, Egypt. Construction of a road connecting between Dabaa and Cairo.
o Ring Road, Alexandria, Egypt. Developing and expanding the entrance of the Ring Road in Alexandria.
o Air Defense Institute, Alexandria, Egypt. Development of the Institute's road network.
o Navy College, Alexandria, Egypt. Developing the road network and expanding the training ground and
Duties included Supervising on concrete stations, quality control of concrete and all materials that used in it. Approve
the receipt of the completed civil works, preparing daily reports and the follow-up the concrete casting for the following
projects:
o Ceramica Cleopatra Mall, Tanta, Egypt. The establishment of a ceramic exhibition on an area of 1500 m2,
consists of 6 floors and basement.
o Shamal Eloronfl for armed forces compound, Cairo, Egypt. The establishment of a residential city for the armed
forces includes a recreational club, mosque, administrative building, 50 villas and 120 residential buildings.
Training at Arab Contractors Company Training at Engineering Consulting Group Training at Elsaraya For Construction