Senior Mechanical Engineer (Technical Office)
Hassan Allam Construction
Total years of experience :15 years, 10 Months
Project: Forum El Djazair- 5 stars hotel and apartment hotel
Responsibilities include:
- Plan, schedule, or coordinate MEP project activities.
- Review / Prepare Shop drawings and Technical submittals and Requests for Information.
- Review/ Prepare Mechanical calculation for mechanical systems (HVAC, FF, and PL).
- Prepare budget estimates, progress reports, material take off, and release contractor/worker payments.
- Prepares the mechanical part in the proposals and provides technical support during the construction phase of the project.
- Prepare technical proposals by reviewing tender documents/ drawings, prepare technical offers & put estimating costs of by coordinating with vendors/subcontractors, offers evaluation, vendors/subcontractors negotiations and BOQ/Financial offer preparation.
- Participate in solving/reporting any unexpected technical difficulties, and other problems that may arise during construction to the Technical Office Manager for discussion and proper solve.
- Prepare as-built drawings at the end of the project and hand over to the project consultant.
Responsibilities: Design review, procurement, site supervision for mechanical infra-structure networks (water supply,
drainage, irrigation, fire fighting including pumps stations, water desalination plant &sewage treatment) and internal
Plumbing and HVAC for 600 villas, 2 hotels and 6 swimming pools and a lake.
www.einhills.com
A Middle East Solar Pioneer 2014 winner
Developing and manufacturing concentrated solar thermal power using Fresnel technology.
Developing and manufacturing concentrated solar thermal power using dish technology.
Developing and manufacturing high accuracy solar tracking system
Developing Fresnel CSP self-cleaning robot.
Solar dish, tower, parabolic trough and frensel strong design experience.
Solar Projects:
1- Manufacturing, supplying and installing of solar tracker for solar tower project at the Frensh University in Egypt.
2- Manufacturing, supplying and installing of solar tracker for solar tower project at El Shorouk Academy
Contracting Projects:
1- HVAC systems testing and balancing - Mahmoudia Power Plant.
2- Technical consultant for Gas Chill company - Project: Cleopatra Plaza Alexandria - HVAC works
3- MEP Coordinator for Arabian Construction Company (ACC) - Project: PKG 50C, Emaar Uptown Cairo - MEP coordination and shop drawings for 85 villas
4- MEP Coordinator for Arabian Construction Company (ACC) - Project: PKG 67, Emaar Mivida New Cairo - MEP coordination and shop drawings for 200 villas
5- MEP Coordinator for Arabian Construction Company (ACC) - Project: Alto, Emaar Uptown Cairo - MEP coordination and shop drawings for 9 building
6- Farid Eldib Office: Fire Fighting and HVAC installation and start up
7- Residential villas : HVAC and plumbing installation and start up
8- New Azhar university - New Capital : Fire fighting works installation.
9- Officers Hotel - New Capital : Plumbing installation.
Key Project : LG Electronics Factory
Project Budget : 150, 000, 000 USD
Project Scope: Our scope was to provide and install the HVAC, Fire fighting, plumbing and compressed dry air systems across the 3 building factories.
Accomplishments: Meeting the extremely short deadline established by the client (9 months) due to production line operation schedule.
Tasks and Duties:
- Studying project specifications and submitting material for approval by consultant.
- Designing and updating Construction time schedule.
- Reporting daily progress to Project and Construction Managers.
- Assigning tasks to team members.
- Supervising the installation team
- Coordinate between different departments.
• Mechanical and plumbing design review and MEP works and disciplines coordination.
• VRV / VRF systems design including unit’s selection, piping and refnets sizing and additional refrigerant charge, system installation and start up.
• Chilled water plant design.
• Cooling load estimation and HVAC systems’ design calculations (piping, ducting and equipments)
• Designing and installing Fire Fighting System.
• Designing and installing Water Supply and Drainage Systems.
• Good knowledge of the following standards:
ASHRAE and Egyptian code for air conditioning and refrigeration
SMACNA
NFPA and LPC (BS)
• Preparation of shop-drawing based on design specification.
• Preparing bill of materials based on approved project drawings.
• Estimating manpower required per project.
• Preparing schedules and controlling workflow to ensure delivering projects on time.
• Projects planning, execution and closing.
• Ability to manage multiple projects at the same time.
• Preparing daily reports and project logs.
• Start up & commissioning of systems.
• Cooling load estimation and HVAC systems design calculations (piping, ducting and equipments)
• Preparation of shopdrawing based on design specification.
• Preparing bill of materials based on approved project drawings.
• Estimating manpower required per project.
• Preparing schedules and controlling workflow to ensure delivering projects on time.
• Projects planning, execution and closing.
• Ability to manage multiple projects at the same time.
• Preparing daily reports and project logs.
• Start up & commissioning of systems.
Certification from Daikin ME:
VRV III startup and Commissioning
VRV III Service & Checker Data Analysis