Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
Anuradha Sri Sampath Sugathadasa, General Manager Operations

Anuradha Sri Sampath Sugathadasa

General Manager Operations·iPCOM Consultancy

Sri Lanka

Bachelor's degree, BSc (Hons) Quantity Surveying

Work experience

Total years of experience: 17 years, 11 months

General Manager Operations

May 2020 - March 2022

iPCOM Consultancy

Kurunegala, Sri Lanka

I found this job using Bayt.com

May 2020 - March 2022

Supervising departmental heads. This often includes areas such as hiring, training and managing the performance of each employee
Developing and maintaining budgets. This can include budgets for individual departments or overall areas of the organisation.
Assisting line managers with hiring, training and managing the performance of each employee
Planning, coordinating and managing all business operations to achieve corporate goals.
Evaluating current business processes and systems

Company industry:
Construction & Building
Job role:
Consulting

Construction site manager

August 2016 - April 2018

Edward and Christie

Colombo 2, Sri Lanka

August 2016 - April 2018

Duties and Responsibilities:
• Responsible for management of material and human resources on sites;
• Finding problems & giving solutions for execution of works at site;
• Coordinate with site inspectors to check the ongoing project status and development;
• Established and implemented work schedules and adjusted them to meet project deadlines;
• Track and monitor that materials delivered to site are check and verified for correct quality, quantity and type ordered;
• Check the material quality as per prescribed standards;
• Preparing measurement sheets, bar bending schedules for reinforcement steel etc. for interim payment application;
• Execution of works according to project specifications and IFC drawings
• Inspecting the site on a daily basis to ensure conformity of the established quality/ safety standards;

Company industry:
Civil Engineering
Job role:
Engineering

Cost Consultant

May 2015 - May 2016

NEA & Partners

Dubai, United Arab Emirates

May 2015 - May 2016

Duties and Responsibilities:
• Prepare Cost Planning to meet client’s requirements and decision for budget and through most effective design options;
• Preparation of tender evaluation reports considering pre-qualification documents and evaluation strategies;
• Prepare Bills of Quantities by carry out take-off measurement;
• Review and evaluation of Contractor’s monthly progress claims;
• Preparation Post contract correspondence relating to assigned contract administration including prepare contract change notices, reporting through Cost Reports for client;
• Review the drawings and Engineer's instructions for prepare of Work Order request through in e-builder and PM-Web;
• Maintain organized files for each contract which includes the original contract, relevant correspondence, changes and amendments.

The project involved- DAMAC Towers by Paramount (79 floors) x 4 towers (AED1.06Bn), Green Community Expansion Phase-3 (210Villas, AED 460Mn), Al Safa Villas Infrastructure, Deira Waterfront Enabling Packages 3 & 13, Rukhan Development (421 Villa project), Sudair Community Infrastructure,

Company industry:
Business Consultancy Services
Job role:
Accounting and Auditing

Cost Manager

November 2011 - April 2015

Currie & Brown (CI) Ltd.

Dubai, United Arab Emirates

November 2011 - April 2015

• Assist in the provision of services as requested by Line Manager in accordance with the consultancy agreement.
• Assist in the preparation of Executive Project Reports.
• Responsible for the preparation of concept, schematic and detailed cost plans and estimates.
• Responsible for the preparation of Bills of Quantities and Contract Documents.
• Assist with preparation of tender reports and financial recommendations on award of contracts.
• Responsible for the preparation of interim valuations and certificates for works in progress.
• Assist with assessment and negotiation of variation costs as required in accordance with the respective forms as contract.
• Assist with preparation of final account statements and other financial certificates as required in accordance with the respective forms of contract.
• Ensure no work or additional work is undertaken without necessary authorization from Team Leader /Associate/Divisional Director.
• In conjunction with Line Manager assist in the implementation and maintenance of the customer care program

The project involved-
Dubai Meydan City \[Meydan Racecourse, Meydan Hotel (AED 8.8Bn)\], Meydan Beach Club Chiller Plant &Substation (AED 7Mn), Meydan Heights (AED 624.2Mn), Crystal Towers (4B + G+ M+ 17) x 2 towers (AED 139.7Mn) and Emirates Palace Yacht Club Abu Dhabi Island Package II - Main Works (AED 350Mn).

Company industry:
Business Consultancy Services
Job role:
Management

Quantity Surveyor

October 2010 - November 2011

Armada Quantities

Kandy, Sri Lanka

October 2010 - November 2011

Responsibilities: - Quantity Surveyor
• Preparation and control of tender/ contract documents with commercial and contractual control of construction and service contracts contain general administration and closeout activities
• Prepare tender documents and co-ordinate planning and quantity surveying input and issue of tender
• Preparation and confirm the scope of work with quantities for pricing the project

The project involved:-
Fit out works for Dubai Mall, Structure + Fit out works for Al Ain Armed Forces Military Camp, Structure + fit out works for the British embassy in Libya, Yabsa Bypass Road project, Car park for Dubai World, Al Bateen project, King Abdulaziz International Airport in KSA,

Company industry:
Business Consultancy Services
Job role:
Engineering

Project Quantity Surveyor

August 2010 - August 2010

Technital S. p. A.

Doha, Qatar

August 2010 - August 2010

Responsibilities: - Project Quantity Surveyor
• Undertaken contractor variations with commercial and contractual control of construction
• Prepare and analysing Engineer evaluation cost for contractor variations
• Make recommendations for the addition of provisional sums, EOT and contingency allowances based upon a careful examination of the scope of work
• Preparation contractor payment certification claims based on prepares quantity take-off, variation orders, identify cost variation from commented RFI’s and shop drawings

The project involved:-
Development Roads in North Khalifa and Markiya Zone 32 & 33 (QR 5, 096, 000.00)

Company industry:
Business Consultancy Services
Job role:
Engineering

Quantity Surveyor

December 2006 - August 2010

CDM Smith (former Wilbur Smith Associates Int. )

Dubai, United Arab Emirates

December 2006 - August 2010

• Preparation of cost estimates & comparisons for preliminary study and preliminary design stages
• Preparation of Bill of Quantities and relevant Tender Documents based on design as per principal method of measurement international
• Advise on tendering procedures, examine and analyse tenders, recommend tender awards after negotiating terms with the client and sub contractors
• Establish and maintain tendering process for set up client target cost contract
• Sub-contract procurement and management, both at pre and post tender stages
• Prepare economic feasibility studies on changes and adjustments to cost estimates
• Preparation payment certification if any additional claims prepares quantity take-off, cost analysis and variation orders, Identify cost variation from commented RFI’s and shop drawings, prepare for Client consideration after compare the tender documents & documents issued for construction
• Preparation of monthly payment applications (Invoices) for certification from Project Management
• Preparation of cost estimates using rate breakdown & comparisons for preliminary study and preliminary design stages
• Notification and reporting of contract forecasting costs and assessment of budget risk/ opportunities.

The project involved:-
Discovery Garden, Jumeirah Lake Towers Infrastructure and Landscaping, Al Furjan Infrastructure Phase-1 & Phase-2, Al Furjan Rough Grading & Infrastructure Phase-1 & Phase-2 Projects, Jumeirah Lakes Towers Extension Project, Discovery Garden Mogul-3, Infrastructure for Deira Island Front (DIF, Palm Deira) Project, Downtown Jebel Ali - Infra. Project, Improvement of Emirates Roads R902 stage-2, Intelligent Traffic System for Dubai (R669/1), Dubai Bypass Phase III, Al Ain-Nahil Road Project, Improvements of Roads Network in Hatta, Dubai Bypass IV- Part 2, Widening of Existing Dubai Bypass Phase I & II (R762/1), Dubai Fujairah Freeway Road project Contract 3, Downtown Al Ain Central area project, Dubai Outer Bypass Jebal Ali-Lihab Interchange Project, Upgrading and Beautification of Al Khawaneej Road (R868), Extension of Muscat Road (R898), Abdullah Bin Abood Road project in Ajman.

Company industry:
Business Consultancy Services
Job role:
Engineering

Project Quantity Surveyor

November 2005 - December 2006

AG Middle East & Al Nakheel Agriculture Companies

Doha, Qatar

November 2005 - December 2006

Responsibilities: - Project Quantity Surveyor
• Review the significant differences in the control budget
• Progress payment application, monitors billing and attachment
• Preparation of variations & negotiation, insurance claims, subcontractor and vendor accounts, claims and final account sub-contract valuations and certifying payments
• Prepare of material submittals and raise site/ stock requisitions as and when required
• Provide project schedule, manpower and equipment schedule
• Review and scrutinise all the technical & commercial aspects of offers prior to presentation
• Liaise with manager regarding all relevant cost information and generate periodic reports for the management review
• Coordinates with other team for preparation and supervision of progress reports, commercial issues and of as built drawings
• Update ongoing projects status information and monitoring system to evaluate budgets and administers their execution.

The project involved:-
Doha Asian Game Village Residence (US$ 25.9M), Qatar Foundation-Education city (US$ 1.2M), Wajba palace Beautification project (US$ 0.5M), Beautification of Ali Bin Abi Talib & Haloul street (US$ 0.7M), Beautification of Expansion project Rasgas (US$ 9.5M) Beau. of British Embassy (US$0.3M)

Company industry:
Construction & Building
Job role:
Engineering

Project Quantity Surveyor

March 2004 - October 2005

Pasalka Builders & Decorators (Pvt) Ltd.

Colombo 2, Sri Lanka

March 2004 - October 2005

Responsibilities: - Project Quantity Surveyor
• Requisitions for materials and equipment are communicated in a timely manner to Head Office
• Monitor status and accomplishment of payment terms and project costs
• Identified variations and preparing valuation of variations
• Closed out Accounts of the sub contractors valuations
• Responsible for cost control and resolution of contractual claims
• Coordination and meeting with other departments
• Preparation of material status report and monthly progress report
• Preparation of Loss and Expense submissions

The project involved:-
Building Projects (Factory and Show Rooms Building) For Royal Ceramic (pvt) Ltd Sri Lanka (Value US$ 10 million)

Company industry:
Civil Engineering
Job role:
Engineering

Quantity Surveyor & Site Engineer

February 2002 - March 2004

Central Engineering Consultancy Bureau - CECB

Ratnapura, Sri Lanka

February 2002 - March 2004

Responsibilities: - Quantity Surveyor & Site Engineer
• Taking off quantities from drawings and preparation of Bill of Quantities for variation claims
• Responsibility for the day to day change Management
• Team working and self management
• Coordination with interface, package contractors
• Assessment Final Account and recommends Final Payments for the Contractors

The project involved:-
Construction of Gem Centre ($20M), Construction of Postal Complex ($30M) at Rathnapura, Construction of four stories Operation theatre building site in General hospital at Balangoda ($60M), Blood bank ($1M), Sewerage System project ($50M) and MOH office ($6M)

Company industry:
Civil Engineering
Job role:
Civil Engineering

Education

College of Estate Management (CEM)

September 2014

September 2014

Bachelor's degree, BSc (Hons) Quantity Surveying

United Kingdom

University of Moratuwa

February 2001

February 2001

Diploma, NDT (Civil Engineering)

Sri Lanka

GPA (percentage): 52%

GPA (percentage): 52%

Skills

Tender Preparation
Expert
Tender Preparation
Expert
Civil Engineering
Expert
Civil Engineering
Expert
Bill Payment
Expert
Bill Payment
Expert
Financial Feasibility Studies
Expert
Financial Feasibility Studies
Expert
Auto Cad
Expert
Auto Cad
Expert
QSCAD
Expert
QSCAD
Expert
WinQS
Expert
WinQS
Expert
Well versed in taking measurements for identifying the scope of work and ability to analyse
Expert
Well versed in taking measurements for identifying the scope of work and ability to analyse
Expert
Detailed legal and construction knowledge
Intermediate
Detailed legal and construction knowledge
Intermediate
Organisation and project management skills
Intermediate
Organisation and project management skills
Intermediate
Financial and commercial acumen
Intermediate
Financial and commercial acumen
Intermediate
CAUSEWAY, CATO
Intermediate
CAUSEWAY, CATO
Intermediate
Tender Preparation
Expert
Tender Preparation
Expert
Civil Engineering
Expert
Civil Engineering
Expert
Bill Payment
Expert
Bill Payment
Expert
Financial Feasibility Studies
Expert
Financial Feasibility Studies
Expert

Languages

English

Expert

Memberships

RICS

Student

January 2010

CIOB

Incorporate class Membership Number: 1516992

May 2011

AIQS

Student

June 2011

City & Guilds

The Licentiateship Award in Civil Engineering

April 2008

IIESL

Associates Member Institution Implantation Engineer, Sri Lanka

August 2007

CIArb

Associate

August 2012