Supply for Central Utility Complexes (CUCs)
CLIENT Dubai Civil Aviation, Government of Dubai.
PROJECT AX201- Dubai International Airport Expansion Project (Phase II) - 132 kV Electrical Supply for Central Utility Complexes (CUCs)
DESCRIPTION The scope of the project involves
• Engineering, supply, installation, testing and commissioning of 3 Nos. New 132 kV substations (CUC-4, CUC-5 & CUC-6) consists of 132 kV GIS (ABB make), 50 MVA 132 / 11 kV transformers (ABB make), Relay & Control Panels, AC & DC
Distribution boards, 110 V & 48 VDC battery chargers and batteries.
• Engineering, supply, installation, testing and commissioning of 1 Nos. new 132 kV GIS bay (VATECH make) to the existing CUC-2 132 kV substation.
• Engineering, supply, installation, termination, testing and commissioning 132 kV Cables around the Dubai International Airport for making a 132 kV ring network by linking CUC-2, 4, 5 & 6 132 kV Substations and incoming cables from Banias S/S to
CUC-4 S/S and from Garhoud S/S to CUC-6 S/S.
• Engineering, supply, installation, testing and commissioning of SCADA & Communication system for 4 Nos. 132 kV substations, 5 Nos. 11kV substations and 400 Nos. Ring Main Units (RMUs) . The system involves Distributed Nodes (RMUs), Substation Control System (SCS) and Central Control System (CCS) . Also all the data is communicated to the DEWA Central control centre through fiber optic communication.
• Engineering, supply, installation, splicing, testing and commissioning of fibre optic cables to make a redundant communication network throughout Dubai Airport for linking 132 kV S/Ss, 11 kV S/Ss and RMUs to the SCADA & Communication System.
ROLE
GENERAL
• Coordination with client (DCA & DEWA), consultant (DAR AL HANDASA), other contractors and sub contractors for various design and construction activities.
• Responsible for assisting Project Manager, Electrical Manager & SCADA Manager.
• Preparation of Weekly & Monthly Progress report.
• Attending Weekly Project Review meeting with Client & Consultant.
• Attending coordination meeting with other contractors, client & consultant.
ELECTRICAL
Coordinated for the
• Installation, testing & commissioning of 10 Nos. 132 kV GIS bays (ABB make), 2 Nos. 132/11 kV, 50 MVA transformers (ABB make), 1 No. 48 VDC and 2 Nos. 110 VDC battery charger and battery bank (Hoppeke, Germany), Relay Panels, Control
Panels, Fault Recorder Panel (FRP), AVR Panel, Tariff Metering Panel (TMP) and AC & DC DBs at CUC-4 132 kV S/S.
• Installation, testing & commissioning of 1 No. 132 kV GIS bay (VATECH make) for the extension of live existing CUC-2 132 kV S/S.
•Installation, termination, testing & commissioning of 132 kV, 1000 mm underground cables between CUC-5 132 kV S/S and CUC-4 132 kV S/S.
SCADA & COMMUNICATION
• Installation, Testing and Commissioning of Bay Control Units (BCUs - ABB make REF 545), Substation Control System (SCS - ABB make), RTUs (ABB make RTU 560A and RTU 560E)
• System study of RMUs, design of RMU grouping, RTU location and Fibre Optic Cable route for RMU integration with SCADA system.
• Installation, splicing, testing and commissioning of Fibre Optic Cable throughout the Dubai Airport for SCADA integration.
• Installation, testing and commissioning of telecom and communication equipments like Multiplexer (FOX 515) and PAX (ABB make)
• Installation, testing and commissioning of SAS (ABB make) equipments like Engineering workstation, Operator workstations, SCADA server, GPS clock and Printers / Plotter.