Projects & Tasks:
1. HAMAD INTERNATIONAL AIRPORT REMOTE TRANSFER BAGGAGE FACILITY (RTBF) - BAGGAGE HANDLING SYSTEM.
Tasks consist of:
• Review IFC drawings to identify infrastructure clashes in both proposed and existing utilities, highlighting potential conflicts.
• Conduct a comprehensive study of the design, identifying missing information, details, or queries, and prepare RFIs (Request for Information) accordingly.
• Assess design deficiencies in infrastructure works that may impact shop drawings and materials procurement, highlighting areas for improvement.
• Verify provided Civil 3D models in the IFC package against drawings, identifying and highlighting any issues and mismatching locations.
• Collaborate with the designer to develop combined utility corridors, ensuring efficient coordination and integration of infrastructure elements.
• Coordinate with the designer to propose technical solutions for resolving clashes identified during coordination efforts.
• Review updated IFC drawings issued by the designer, ensuring alignment with project specifications and scope of works.
• Coordinate utilities diversion within the project area, ensuring clear alignment, clash-free profiles, and proper tie-ins with existing pipelines/ducts (potable water, firewater, wastewater, 11Kv, and QAF).
• Collaborate with the designer to modify road grading and tie-ins with existing asphalt, ensuring seamless integration with infrastructure elements.
• Consult with the designer regarding various road works aspects such as road marking, signage, turning radius, curbs, and pavement layer details to ensure compliance with project requirements.
• Review updated Civil 3D models and verify the federated model for all networks, ensuring accuracy and alignment with project specifications.
2. AL-RAYYAN STADIUM SUPPORT WORK PROJECT (DN110- P06).
Tasks consist of:
• Prepare shop drawings for wet utility networks (surface water drainage, foul sewer, TSE, and potable water) based on IFC drawings, ensuring accuracy and compliance.
• Develop comprehensive details for each network component (manholes, chambers, gullies, trench/bedding, pipe arrangement, etc.) to guide construction.
• Utilize Civil 3D software to create 3D models for surface water networks, identifying clashes during shop drawing preparation.
• Generate shop drawings for dry utility networks and ducts (Ooredoo, QAF, UGN, CRA, main electrical ducts, street lighting ducts) based on IFC drawings.
• Prepare shop drawings for road works, including road layout, pavement details, traffic signs, markings, safety furniture, etc.
• Coordinate between wet and dry utilities, traffic signals, directional signs, gantry foundations, and existing utilities.
• Coordinate with interface projects for tie-in points between different systems.
• Liaise with concerned authorities (PWA, KMW, QAF, CRA, MME PPD) for project services.
• Study design changes/queries and prepare RFIs (Request for Information) accordingly.
• Address site issues and obstructions promptly.
• Coordinate and arrange with authorities for handing over project networks.
• Prepare as-built drawings for all network elements according to authorities' standards considering the coordination of third-party surveyors for GIS documentation.
- Company industry:
- Construction & Building
- Job role:
-
Civil Engineering